HomeMy WebLinkAboutagenda.council.worksession.20091124MEMORANDUM
TO: Mayor and City Council
FROM: Aaron Reed, Construction Mitigation Officer
THRU: Trish Aragon PE, City Engineer
Scott Miller, Capital Asset Manager
DATE OF MEMO: November 19, 2009
MEETING DATE: November 24, 2009
RE: Construction Management Plan Modifications
REQUEST OF COUNCIL:
The Engineering Department seeks Council approval regarding modifications to the Construction
Management Plan Requirements Manual. These changes are:
• New restrictions for onsite manufacturing
• Alterations to the holiday schedule and the creation of a restricted zone to be refered to as
the Central Resort Area (CRA)
• Streamlining the permitting process for Smuggler Mountain Superfund Soil Removal
Permits.
PREVIOUS COUNCIL ACTION:
City Council approved the creation and implementation of the Construction Mitigation Program
in April of 2006, below is a timeline of this program.
• Apri12006: the City creates the Construction Mitigation Program to reduce the impact of
construction on the general public, to provide a liaison between the City, contractors, and
the general public. This is accomplished by requiring contractors to submit a plan
detailing how they intended to meet all city codes during construction.
• March 2007: the Original Plan Requirement Manual is drafted and presented at a
worksession.
• Apri12007: edits from the March worksession aze incorporated into the "Plan" these edits
included an established haul route, restricting hours from 12 hours a day to 10 hours a
day, creation of the Aspen Holiday list which included federal holidays and special
events in Aspen like the Food and Wine Classic.
• Apri12007: Alteration of start and end time for work days Sam-6pm
• May 2007 re-instatement of original start and end times lam-Spm
• January 2008: Expansion of the program to include inspections on all active projects
regazdless of impact. Additional inspections were also added these included sediment and
Page 1 of 4
erosion control, and parking. The table below provides a quantitative description of CMP
activities.
Activi
Sites with CMP's
Red Tags Issued
Citizen Construction Complaints
Construction Parking Permits
Encroachment Permits
2009 2008 2007
205 155 29
13 17 45
42 105 81
88 91 No Data
89 179 205
BACKGROUND:
• Manufacturine Activities: In April of 2009 the City Manager's Office, Building,
Engineering, and Environmental Health Departments began receiving noise complaints
from neighbors of 17 Shady Lane regazding stone cutting. After conducting site visits
with residents and one with Council it was determined that the contractor was in
compliance with the current CMP requirements. However, several neighbors continued to
express concern, primarily due to the chronic nature of the situation.
• Holiday Hours: In June the Department also processed requests to grant holiday
construction closure exemptions to projects in outlying neighborhoods such as Cemetery
Lane, McSkimming Lane, in addition to the Commercial Core.
• Superfund Permittine: In October the Environmental Health Department, Engineering
Department, and Building Department chose to streamline the "Smuggler Mountain
Super Fund Site Soil Removal Permit" process by allowing the Engineering Department
to take on issuance, tracking, and reporting associated with the requirements under the
Smuggler Mountain Super Fund Soils.
DISCUSSION:
Manufacturine activities:
Issue: City staff has received repeated complaints regazding the impacts and duration of specific
stone cutting operations. The project located at 17 Shady Lane has a very labor intensive design
for stone veneer. This design required labor to cut large pieces of stone (18"x10"x3") into much
smaller pieces (6"xl"x3"). This portion of the project lasted for over a year and had a significant
impact to the neighborhood. This operation was actually within the limits set by the municipal
code, however, the chronic nature of the work created increasingly irritated complaints.
Proposed Changes: Staff is proposing modifications to the noise suppression section of the
requirements manual to better address the concerns related to long term nuisance issues. These
would be activities that have been defined as manufacturing, as well as other noise producing
activities that could take place offsite. These modifications would require that all manufacturing
Page 2 of 4
activities are conducted offsite, reducing the duration and overall impact to surrounding
neighborhoods. Additionally, if a further modification to the material is required to fit the
material then hours of operation will be limited to gam-Spm Monday thru Friday.
Refer to Sections 11.3 and 11.4 of Attachment "A" for the proposed changes to the Construction
Management Plan
Holidav Hours:
Issue: The Current manual requires that all construction sites within the City of Aspen are closed
for construction during designated holidays. During some of these closures, especially the Food
and Wine Classic and Christmas week, several exemptions aze granted to contractors in outlying
areas with the understanding that the work will have less of an impact to the resort feel of the
community.
Proposed Changes: Staff is proposing a new geographic zone in town to help address the
impacts of construction while at the same time maintaining the resort feel of the community.
This zone is being referred to as the Central Resort Area (CRA). The geographic boundaries
minor the expanded pay to pazk area. This boundary was chosen because the azea is impacted
heavily during special events and the winter /summer tourist season. The adoption of the CRA
would allow work in the "non-core" neighborhoods that which are less impacted during the peak
seasons. The boundaries of this zone would extend from Cleveland Street west to First Street and
from Summit Street North to Francis Street. Refer to Attachment `B".
Below is a summary of the current requirements and the proposed changes to the holiday
closures for construction. The changes allow for additional work days outside of the CRA,
increasing production during the holidays and certain special events in Aspen.
Thanks Xmas Xmas New Years Presidents Memorial Food 4` of Labor
giving Week Day Day Day Day & July Day
Wine
Current
Restriction
Entire City closed closed closed closed closed closed closed closed closed
Limits
Proposed
Restriction
Central Resort closed closed closed closed closed closed closed closed closed
Area CRA
Outside CRA closed open closed closed open closed open closed closed
i.e. "non-core"
Refer to Section 4_2 of Attachment "A" for the proposed changes to the Construction
Management Plan
Sunerfuud Permittiue:
Page 3 of 4
Issue: The Current process requires that additional departments make onsite inspection to
provide oversight and confidence that requirements are met. Tracking of sites activities takes
place in multiple departments within the City, and this has lead to some delays in identifying
projects with a smaller impact.
Proposed Changes: City staff has made alterations to the Smuggler Mountain Superfund Site
Soil Removal Permit to stream line the process and ensure the sites are captured in regular
inspections. Efficiency and customer service will be improved by having one less department
sign-off on building permits, and by having construction mitigation staff already onsite
monitoring superfund compliance.
Refer to Section 8_2 of Attachment "A" for the proposed changes to the Construction
Management Plan.
FINANCIAL IMPLICATIONS:
Staff does not anticipate additional costs to the City, however, potential costs to contractors
specifically relating to offsite manufacturing, may be increased. Contractors may also realize a
financial gain by allowing work outside of the CRA, and therefore increasing production during
specific holiday periods.
ENVIRONMENTAL IMPACTS:
Limiting onsite manufacturing will ensure more reasonable noise impacts on neighbors during
construction projects. Allowing construction in non-core neighborhoods on certain holidays will
have noise impacts, but they are not likely to be significant. Having Smuggler superfund site
permitting done by CMO's who are already onsite will provide better oversight of institutional
controls.
RECOMMENDED ACTION:
City staff recommends the adoption of new policies outlined above as well as the adoption of the
Central Resort Area.
ALTERNATIVES:
Council may select any of the above recommendations asalterations to the current Requirements
Manual.
CITY MANAGER COMMENTS:
ATTACHMENTS:
Attachment A: Construction Management Plan
Attachment B: Central Resort Area Map
Page 4 of 4
Attachment A
THE CITY OF ASPEN
CONSTRUCTION MANAGEMENT PLAN
REQUIREMENTS MANUAL
Construction projects that exceed 1000 SF of soil disturbance and/or 400 SF of building demolition,
improvement, or renovation (interior and/or exterior) must submit a construction management plan in
accordance with this manual.
Prepared by:
Engineering Asset Management Department
130 S. Galena St.
Aspen CO 81611
970.920.5080
November 2009
Please provide:
2 Paper Documents -Engineering Department
1 Electronic Document - EngineerCity@ci.aspen.co.us
Specifics: 8.5 x 11 or 11x17 sheets only & 2-hole punch
Revised 11/16/09
City of Aspen
TABLE OF CONTENTS
1.0 GENERAL
1.1 PURPOSE
1.2 APPLICABILITY
1.3 DEFINITIONS AND TERMS
1.4 REFERENCES
2.0 PROJECT INTRODUCTION
2.1 DISTURBANCE AREA
2.2 LOCATION
2.3 DESCRIPTION
3.0 PROJECT DOCUMENTATION
3.1 PERMITS /OTHER DOCUMENTS
3.2 PUBLIC NOTIFICATION
3.3 PROJECT SIGN
3.4 CONTACT DESIGNATION
4.0 PROJECT IMPLEMENATION
4.1 DATES OF CONSTRUCTION
4.2 HOURS OF CONSTRUCTION
4.3 SEQUENCE (PHASING) OF CONSTRUCTION
4.4 ADJOINING PROPERTY OWNERS
4.5 PROJECT FENCING
4.6 PUBLIC HEALTH AND WELFARE
4.7 NATURAL ENVIRONMENT
5.0 PARHING MANAGEMENT
5.1 PARKING MANGEMENT FORM
5.2 EMERGENCY VEHICLE ACCESS AND ORDINANCE 35
5.3 CONSTRUCTION PARKING DETAILS
5.4 STAGING AREAS
5.5 CONSTRUCTION TRAILER, MATERIALS STORAGE, AND WASTE
MANAGEMENT
6.0 TRA1
6.1
6.2
6.3
6.4
6.5
?FIC CONTROL
GENERAL
HAUL ROUTES
ONSITE VEHICLE LIMITATIONS
DELIVERY REQUIREMENTS
TRAFFIC CONTROL PLAN
7.0 PEDESTRIAN PROTECTION
7.1 GENERAL
Revised 11/16/09 2
City of Aspen
8.0 SEDIMENT AND EROSION CONTROL
8.1 REQUIREMENTS
8.2 SMUGGLER MOUNTIAN RESTRICTIONS
9.0 FUGITIVE DUST CONTROL
9.1 FUGITIVE DUST CONTROL PLAN
9.2 REQUIREMENTS
10.0 EMISSIONS
10.1 GENERAL
10.2 EMISSIONS FROM DIESEL POWERED ENGINES
11.0 NOISE SUPRESSION
11.1 GENERAL
11.2 NOISE SUPPRESSION PLAN
11.3 REQUIREMENTS
11.4 SPECIFIC RESTRICTIONS RELATED TO MANUFACTURING ON SITE
12.0 ENFORCEMENT
12.1 CONSTRUCTION MITIGATION OFFICER
12.2 CORRECTIVE ACTION
12.3 INSPECTION REPORTS
APPENDICES
A -Required Project Sign
B -Parking Management Form
C -Haul Route Map
D -Noise Suppression Plan, Techniques and Equipment
E -Smuggler Mountain Superfund Site Map
F -Central Resort Area Map
Revised 11/16/09
3
City of Aspen ~
1.0 GENERAL
1.1 PURPOSE
The purpose of this Construction Management Plan Manual is to provide a consistent
policy under which certain physical aspects of construction management will be
implemented. The elements contained in this document are related to the development
process. It is intended that they apply to both public and private work designated
herein.
These standards cannot anticipate all situations. They are intended to assist, but not to
substitute for competent work by design and construction professionals. The City of
Aspen does not intend to limit any innovative or creative efforts that could result in
better quality, greater cost savings, or both. Any proposed departure from the manual
will be judged on the likelihood that such variance will produce a comparable result,
adequate for the user and City resident over the duration of the improvement/project.
If the project changes ownership or contracting services change, the City Engineering
Department must be notified, and must agree to comply with an approved CMP in
writing. Any departure from the approved CMP must be submitted in writing and
approved by the City Engineer. The approved construction management plan must be
kept onsite.
1.2 APPLICABILITY
This manual shall govern the construction and development of all public and private
construction projects in the City of Aspen. These regulations shall apply to all
commercial, industrial, residential, and mixed use developments which disturb 1000 SF
or greater or require demolition, improvement, or renovation (interior and/or exterior)
of 400 SF or greater within any twelve-month period.
1.3 DEFINITIONS AND TERMS
Construction Management Plan - A Construction Management Plan is a combination of
diagrams, documents, drawings, and specifications that clearly define the steps that will
be taken to demonstrate how the impacts to the community will be minimized. How the
impacts associated with any construction project will be managed. Herein described as
"Plan" throughout the remainder of this policy.
Construction Mitigation Officer - An appointed employee of the City of Aspen whose
charge is to ensure that all aspects of a Construction Management Plan are followed,
and to further ensure that the impacts associated with construction activities within the
City of Aspen aze effectively managed and impacts associated with those projects are
the least necessary to accomplish the project.
Disturbance Area - A portion of land where topsoil or native soils have been removed
for purposes of construction (development).
Revised 11/16/09 4
City of Aspen
Best Management Practices (BMP's) -Schedules of activities, prohibitions of
practices, maintenance procedures, and other management practices to prevent or
reduce the pollution of waters of the state. BMP's also include treatment requirements,
operating procedures, and practices to control site runoff, spillage or leaks, waste
disposal, or drainage from material storage.
Tree Dripline and Protection Zone -Use the longest branch of the tree as a radius from
the center of the tree and make a circle. The circle is then defined as the dripline and
thus is the tree protection zone.
Final Stabilization -Uniform vegetative cover has been established with a density of at
least 70 percent ofpre-disturbed levels.
1.4 REFRENCES
A. City of Aspen Policy 205-A Right-Of--Way Permit Requirements
B. City of Aspen Policy 204-A Revocable Encroachment License Application
C. City of Aspen Construction and Mitigation Standards for Work in the Public
Rights-of--Way
D. City of Aspen Municipal Code Titles 13, 21, and 26
E. City of Aspen Ordinance 35
F. Manual on Uniform Traffic Control Devices for Streets and Highways - 2003
Edition
G. Colorado Deparhnent of Public Safety General Permit Part IB
H. Colorado Department of Transportation M&S construction standards
I. Colorado Department of Public Health and Environment -Air Pollution Control
Division
2.0 PROJECT LOCATION
2.1 DISTURBANCE AREA
The Plan shall describe and compute the total project disturbance area. Soil disturbance
shall be kept to a minimum. Construction staging and phasing shall occur, where
applicable, to minimize soil disturbance time.
2.2 LOCATION
A project vicinity map shall be included in the Plan. The map should accurately depict
general project location within the City of Aspen and also delineate project extents.
The map shall be a scaled drawing that includes a directional arrow and adjacent street
descriptions.
2.3 DESCRIPTION
The Plan shall include an overview of the construction project including background
information, proposed development type and general information. The proposed effect
on public utilities such as storm sewer, sanitary sewer, water main, etc. should also be
described.
Revised 11/16/09
City of Aspen
3.0 PROJECT DOCUMENTATION
3.1 PERMITS /OTHER DOCUMENTS
The contractor shall maintain all applicable local, state and federal licenses and permits
that apply to the construction project. Applicable permits shall be listed, described and
copies of the documents shall be attached in Plan appendices. In addition to permits all
PUD's, Subdivision Improvement Agreements, and Related City Ordinances must also
be attached in the Plan appendices.
3.2 PUBLIC NOTIFICATION
A project update shall be provided to the public on a basis no less than monthly, via
website, newspaper, on-site notices, or other accepted means of notification (per
request of the City of Aspen). The first public notification shall occur no later than 10
days prior to construction. The update shall include a description of the current project
phase, list any traffic and/or pedestrian concerns, and describe hauling/staging
operations.
The above notification shall specifically be distributed to neighbors located within 300
feet of the project property.
The Plan shall designate a project representative, date, and time for a required
preconstruction meeting. The purpose of the meeting is to discuss the project and
summarize the project specific Construction Management Plan. The contractor and
subcontractors are required to attend the meeting. Utility personnel, applicable City
departments, the Roaring Fork Transit Authority, neighboring property owners, and the
Aspen School District shall also be notified.
3.3 PROJECT SIGN
A project sign shall be constructed and posted that includes the items shown in
Appendix A: Required Construction Sign.
The sign shall be posted in a location where it is readable from the street or driveway
and shall meet criteria in City Municipal Code 26.510.030B4.
3.4 CONTACT DESIGNATION
The Plan shall have a contact list with associated phone numbers located at the front of
the document. The list will include: the owner, contractor appointed overall site
supervisor, a state certified safety officer, a state certified traffic control officer, and a
state certified erosion control representative. Other information shall include city and
county phone numbers, fire department, police department, Roaring Fork Transit
Authority (BETA), school district, and all applicable utility company contact
infonmation. The contact list should include hospital contact information and the
Emergency 911 reminder.
Revised 11/16/09
City of Aspen
4.0 PROJECT IMPLEMENTATION
4.1 DATES OF CONSTRUCTION
Dates of construction shall be specified in the Plan. Any work being performed within
City ROW shall be completed as per the City of Aspen Right of Way permit
requirements.
4.2 HOURS OF CONSTRUCTION
Construction hours shall be limited to lam -Spm Monday through Friday and gam -
Spm on Saturday. No construction is permitted on Sundays, a••~~° ~'°°a °• "'~°°
r'°°*~- °~ ~° r••°°'~'-~-'°° •'•~• e°••a°°` 4`n of July day and/or weekend if it falls on a
Friday or Monday, Memorial Day and Labor Day weekends, Thanksgiving Day,
Christmas Day, New Yeazs Day. °~a a..a..,. «,.° ~,._:....,,°.. .. °°,. i,,~i~c , i, ~_ During
Presidents Day, the Food & Wine Festival in June (Friday thru Sunday) and during the
Christmas week (12/25-1/1) projects located in the Central Resort Area are not
permitted to work. These areas are defined in Appendix F.
All activity that generates noise in excess of 80 decibels requires a noise suppression
plan and is restricted to operating between the hours of gam and Spm Monday through
Friday.
4.3 SEQUENCE (PHASING) OF CONSTRUCTION
A construction schedule including all project phasing, with item details, and specific
item completion dates or duration of phasing is required.
The schedule shall be developed using Microsoft Project or a program of greater
capabilities as approved by the Engineering Department.
4.4 ADJOINING PROPERTIES
No person shall excavate on land close enough to a property line to endanger any
adjacent public street, sidewalk, and alley, other public or private property, or
easement, without supporting and protecting the property from any damage that might
result from construction operations.
4.5 PROJECT FENCING
All construction areas shall have anon-removable construction fence or other approved
device securely placed around the areas to be protected. The fence shall be six feet (6')
in height and constructed out of chain-link fence with mesh windscreens (visual
barriers). Decorative construction fences may be allowed at the discretion of the City
Engineer. Please see Section 11 for fencing noise suppression techniques.
Revised 11/16/09
7
City of Aspen
4.6 PUBLIC HEALTH AND WELFARE
All construction projects located within the City of Aspen shall uphold utmost respect
to public health and welfaze and be reflected in prepared Plan.
4.7 NATURAL ENVIRONMENT
Project construction shall be oriented to minimize harm to all aspects of the City of
Aspen's natural environment. All tree and natural resource protection measures must
be identified in the Plan and in place prior to the commencement of any construction or
demolition activities. Refer to section 13.20.020b of the Municipal Code for tree
protection and removal requirements and process.
The Plan must contain a site map showing exact tree protection fence location and
accurate tree driplines (refer to Section 1.3 for dripline definition).
Proposed projects should be consistent with the character of existing land use in the
surrounding area.
5.0 PARHING MANAGEMENT
5.1 PARKING MANAGEMENT FORM
A Parking Plan must be requested, specified and submitted as part of the CMP.
5.2 EMERGENCY VEHICLE ACCESS AND ORDINANCE 35
The contractor shall maintain continuous emergency vehicle access, on and azound site,
including but not limited to police, fire, and ambulance services. This includes projects
adjacent to roads and alleys.
All Plans shall include a cony and show compliance with Ordinance 35.
5.3 CONSTRUCTION PARKING DETAILS
Specific construction pazking spaces/areas may be requested for use by craftsman,
subcontractors, and contractors involved in the site construction process. The City
allows minimal onsite parking with public transportation as the preferred method of
transportation. Transportation options may include, but aze not limited to carpool,
vanpool, public transportation, paid shuttle for transporting workers to the site, etc.
No construction parking will be permitted within the free two-hour residential parking
areas without a valid permit.
5.4 STAGING AREAS
The Plan shall specify construction staging azea locations. Alleyways are preferred
short term staging locations without blocking access to neighboring properties. The
number of truckloads expected to and from the site should be estimated (including soil
Revised 11/16/09
City of Aspen
hauling and materials transport). The timing and duration of the transport vehicles
should also be noted.
City of Aspen personnel can limit project staging locations, number of trucks, and
duration of operations depending on project location and site sun•oundings.
Projects that require crane operations and have little or no setbacks aze required to use a
tower crane. The City prefers electric type cranes to reduce noise and fumes.
Right-of--Way encroachments are used as a last resort in all cases. In the case where a
ROW encroachment occurs, a permit must be obtained from the City Engineering
Department.
5.5 CONSTRUCTION TRAILER, MATERIALS STORAGE, AND WASTE
MANAGEMENT
As specified in Section 5.1, construction trailer, job materials storage, portable
restrooms, waste management and recycling container locations shall be clearly
designated on the project site plan. Loose job material storage is not allowed in ROW
under any circumstance.
The City of Aspen Engineering Asset Management Department strongly recommends
job trailer, waste management containers, and portable restrooms be stored on private
property and not within City ROW.
The City of Aspen re uires recycling of construction materials. In instances where
recycling containers cannot be accommodated onsite, the City Engineering Department
will consider locating recycling containers within public ROW where feasible. The
encroachment permit fee will be waived if it pertains to recycling containers. If at any
time such a container is not being used for recycling operations, the property owner will
be responsible to pay at least three months calculated land lease fee.
The City of Aspen requires recycling of materials, both conventional and construction
related, according to this document and City of Aspen Municipal Code (26.575.060).
Recycling requirements included in this section do not supersede project specific
Efficient Building Program (EBP) requirements.
Project site conventional recycling of co-mingled materials (plastics #1-#7, tin,
aluminum, and glass), and cardboard must have an assigned space/area and be
separated on-site during the project. These materials may not be disposed of in the
trash.
During the demolition phase of a project, deconstruction related activities aze required
(recycling and/or salvaging). Concrete and scrap metals must be sorted and kept
separate on-site and must have an assigned space/area.
Revised 11/16/09
City of Aspen
Field inspections will occur throughout the permit process. If sorting of materials is not
occurring onsite, other means of verification may be provided to City of Aspen as
deemed appropriate.
Per municipal code, any dumpster or other trash receptacle that is used for food refuse
must be constructed in such a manner as to render it bear proof. All containers shall be
adequately covered at all times until transferred to the landfill. The City of Aspen
municipal code states it shall be unlawful to permit accumulated debris, litter, or trash
on any construction site to blow or scatter onto adjoining properties.
An onsite hazardous material spill cleanup kit is required, as specified by the City
Engineer, that contains, at a minimum, a 25 pound bag of Floor-Dri (or equal),
absorbent pads, and other spill kit materials.
6.0 TRAFFIC CONTROL
6.1 GENERAL
All traffic control operations shall be managed by the designated certified traffic
control supervisor.
6.2 HAUL ROUTES
The City of Aspen has designated specific project haul roads throughout the City
(Appendix C). The project must follow the designated routes and specify any
additional routes necessary to complete hauling operations. Project haul routes shall be
oriented to minimize traffic congestion and maximize pedestrian safety.
6.3 ONSITE VEHICLE LIMITATIONS
All construction related vehicle activities shall be defined. Maximum vehicle weights
and sizes shall be specified.
6.4 DELIVERY REQUIREMENTS
Traffic control required for deliveries must be fully coordinated with the City of Aspen
Engineering Deparment. Roads will not be closed under any circumstances, unless
granted permission from the City of Aspen Engineering Department.
The maximum number of delivery vehicles onsite must be specified, along with the
hours the deliveries will occur, and any exceptions to the delivery schedule.
Delivery and Heavy Duty Vehicles must have a visible sign on the vehicle that
specifies the project contractors name and phone number.
Delivery vehicles and all other onsite vehicles are not allowed to idle for more than five
(5) minutes, with the exception of generators or PTO type operations. The general
contractor must include an idling policy in the Plan that meets City requirements.
Revised 11/16/09 10
City of Aspen
6.5 TRAFFIC CONTROL PLAN
A preliminary Traffic Control Plan (TCP) shall be submitted as part of the Construction
Management Plan if necessary to be determined by City Engineer. The TCP shall be
completed by a State Certified Traffic Control Supervisor and must conform to the
most current edition of the Manual of Uniform Traffic Control Devices for Streets and
Highways (MUTCD). The TCP shall contain all information specified in Section
6C.01 of the MUTCD.
A School Traffic Control Plan should be submitted in addition to the TCP in school
areas according to Chapter 7A of the MUTCD, If the project is not located in a school
area, but abuts a school bus stop or school walk route, extra traffic control personnel
and devices shall be implemented to ensure school pedestrian safety.
7.0 PEDISTRIAN PROTECTION
7.1 GENERAL
The Plan shall comply with pedestrian safety per City code 21.04.060, MUTCD
Chapter 6D, the Americans with Disability Act, and IBC Chapter 33.
8.0 SEDIMENT AND EROSION CONTROL
8.1 REQUIREMENTS
A Storm Water Pollution Prevention Plan shall be completed along with the CMP,
according to Colorado Department of Public Health and Environment Water Quality
Control Division General Permit Part IB.
The main objective of the storm water management plan shall be to identify Best
Management Practices, which will minimize erosion and sediment transport.
In addition to the Colorado Discharge Service Permit (the program) requirements, the
following apply:
1. Stock piles must be protected with erosion control devices.
2. Mud tracking ramps (rock construction entrances) are required and
implemented per the most current version of the Colorado Department
of Transportation M&S construction standards.
3. Onsite concrete and tire washout stations aze required. Location and
operation procedures shall be described in Plan.
4. City inlets, gutters, swales and irrigation ditches shall be protected
with erosion control devices and such projection maintained for the
duration of the project.
5. A description of procedures used to protect and maintain in good and
effective operating condition the erosion sediment control measures
until final stabilization is required.
Revised 11/16/09 11
City of Aspen
Onsite sediment and erosion control operations shall be managed by a state certified
erosion control supervisor.
8.2 SMUGGLER MOUNTAIN RESTRICTIONS
All projects located within the Smuggler Mountain Superlimd Zone (Appendix E) are
required to meet additional standards for erosion control measures and are required to
file an additional soil removal permit. These requirements shall be instituted on all
projects disturbing (excavating or exposing) more than one cubic yard of soil. All
projects located in the superfund site will also be required to handle disturbed and
excavated soils with an additional level of care.
1. A Smuggler Mountain Superfund Site Soil Removal Permit must be
completed prior to any soil disturbance in this area. (Appendix E)
2. All contaminated soils must be disposed of at a duly licensed and
authorized facility, usually the Pitkin County Landfill, and the
receiving location must be made aware of the contaminated nature of
the soils.
3. Soils must be contained and covered at all times unless actively being
worked. Working will be defined as moving, compacting, backfilling,
exposing, or grading the soils at least once in a sixty minute period. If
any stockpile of soil is to be left for more than sixty minutes it must
be contained and covered.
4. Containment and Covering is required. This can be accomplished
tlrrough the use of anon-permeable tarp placed below the stockpile
and the same type of material shall be used to cover the stockpile.
5. After completion of the project an uncontaminated soil cap will be
required. This cap shall consist of twelve inches of clean fill or
gravel. This can also be accomplished by paving the area with asphalt
or concrete.
6. In order to obtain a "clean letter" from the City of Aspen, which, will
be required prior to the release of the Certificate of Occupancy, all of
the above conditions roust be met.
9.0 FUGITIVE DUST CONTROL
9.1 FUGITIVE DUST CONTROL PLAN
All projects that result in fugitive dust emissions must submit a fugitive dust control
plan and file an application for a construction permit with the Colorado Department of
Public Health and Environment.
The approval of a Dust Prevention and Control Plan does not relieve the owner or
contractors of the responsibility to implement whatever additional measures may be
required by the City Engineer to properly prevent and control dust.
Revised 11/16/09
12
City of Aspen
9.2 REQUIREMENTS
The plan shall demonstrate that the discharge of dust from the construction site will not
occur, or can be controlled to an acceptable level depending on the particular site
conditions and circumstances.
1. The plan shall address site conditions during construction operations,
after normal working hours, and during vazious phases of construction.
2. The plan shall include the name and the 24 hour phone number of a
responsible party.
3. If the importing or exporting of dirt is necessary, the plan shall also
include the procedures necessary to keep the public streets and private
properties along the haul route free of dirt, dust, and other debris.
4. When an entire project is to be graded and the subsequent construction
on the site is to be completed in phases, the portion of the site not
under construction shall be treated with dust preventive substance or
plant materials and an irrigation system.
5. All phased projects shall submit a plan demonstrating that dust will not
be generated from future phase areas.
For all construction within the site, the contractor shall have a water truck available for
dust control. Wetting shall be completed once three times a day under dry conditions
or as directed by the City Construction Mitigation Officer.
Vehicle speeds should not exceed 15 mph on construction access roads and
construction site.
10.0 EMISSIONS
10.1 GENERAL
All vehicles and equipment used on site will be properly maintained such that the
engines will function within manufacture's standards or parameters.
10.2 EMISSIONS FROM DIESEL POWERED ENGINES
Emissions from diesel engines operated within the City of Aspen shall be of a shade or
density no darker than 40% opacity, except for starting motion no longer than 10
seconds or for stationary operation not exceeding 10 seconds.
11.0 NOISE SUPRESSION
11.1 GENERAL
The noise limit for construction is 80 decibels measured at the property line of the
construction site. All construction equipment shall be adequately muffled and
maintained to minimize project noise. The installation of noise bazriers is the minimum
technique to suppress noise, especially when jack hammering of concrete occurs.
Revised 11/16/09
13
City of Aspen
11.2 NOISE SUPPRESSION PLAN
All activity that generates noise in excess of 80 decibels at the property line requires a
plan and is restricted to operating hours identified below. The plan will include
information on noise blocking methods, techniques, and common equipment and
activities that require noise suppression_(Refer to Appendix D).
11.3 REQUIREMENTS FOR ACTIVITIES EXCEEDING 80 DECIBELS
1.
includes but not limited to the use of compressors, generators,
jackhammers, power equipment, nail puns, drilling machinery, earth
moving equipment and similar loud construction activities. This does
not restrict quiet work inside and outside that does not require a power
source, including a battery, on Saturday.
2. Notify neighbors within two hundred fifty (300) feet of the project
informing them of the kinds of equipment, expected noise levels and
durations of loud work. Including the variation of noise levels during a
typical construction days may be helpful. Such notification must be in
writing and be done seven (7) days prior to the starting time of the
project. Communication with neighbors can prevent complaints from
arising, and resolve concerns before there is a problem. Provide a
phone number where the foreman can be reached prior to the start of
the job.
3. Operate equipment in accordance with manufacturer's specifications
and with all standard manufacturers' mufflers and noise-reducing
equipment in use and in properly operating condition.
4. Post notices to inform workers, including sub-contractors, about the
basic noise requirements, as well as specific noise restrictions, to the
rp oiect.
5. Install noise barriers around all equipment/activities specified in Table 1
of Appendix D Noise barriers not only significantly reduce construction
noise, but they also provide an extra benefit of "hiding" the noise
producing sources, thus increasing a neighbor's tolerance.
6. Move portable loud equipment including generators, compressors, and
cement mixers to different sides of the property to reduce impacts on
individual neighbors.
7. The use of radios on the site before 8:00 am is not allowed.
Revised 11/16/09
14
City of Aspen
11.4 Specific restrictions related to manufacturing on site.
restrictions will be placed on those activities. The primary concern is that extending the
manufacturing efforts must be conducted off site or in such a manner as to not
contribute to any long term noise impacts off of the property.
Activities will be considered manufacturing if alterations to a material that is readily
was delivered as a rough cut product to the site and each of the stones were to be cut
square and fit into place. In this example the stone cutting is considered the
additional work to fit the stones would be permitted on site.
All work which requires a limited amount of additional manufacturing to achieve the
12.0 ENFORCEMENT
12.1 CITY CONSTRUCTION MITIGATION OFFICER
A City Construction Mitigation Officer shall be assigned to each construction project.
The City Construction Mitigation Officer will complete random site visits to determine
if the project is following approved Plan and City requirements. The officer is not
intended to take the place of a City of Aspen building inspector.
12.2 CORRECTIVE ACTION
The City of Aspen will enforce construction mitigation corrections as follows:
1. The first corrective action is a verbal warning and explanation of the
violation with a timeframe for wmpletion.
2. The second corrective action is a written warning or correction notice
with timeframe for compliance.
3. Third and final notice is a "Stop Work Order" (red tag). If a stop work
order is issued, no more work can be completed until the violation is
corrected.
Failure to correct violations and/or any threat to public safety could subject the owner,
contractor or both to a fine of $1000 a day as determined by the municipal court.
Revised 11/16/09
15
City of Aspen
12.3 INSPECTION REPORTS
The Construction Mitigation Officer will complete construction inspection reports. All
reports are public and will be kept in the City Engineering Asset Management
Department.
Revised 11/16/09
16
Attachment B
m
m
0
0
~a
m
s
U
Z ~~
n~
W
'O
nV/'
W
~~
W
U
0
MEMORANDUM
TO: Mayor and City Council
FROM: Engineering Department
Tyler Christoff, Project Manager
Trish Aragon, City Engineer
THRU: Randy Ready, Assistant City Manager
DATE OF MEMO: November 20`~ 2009
MEETING DATE: November 24, 2009
RE: Main Street Pedestrian Safety Improvement Options
SUMMARY: Staff is updating City Council on current Main Street pedestrian safety, issues,
concerns and projects.
PREVIOUS COUNCIL ACTION:
In 2004, Aspen City Council directed staff and provided funding to implement the Following
pedestrian/traffic improvements.
• Purchase and installation of new on street Yield to Pedestrian signage
• Purchase of four new radar trailers for use by the Police Department
• Improved crosswalk striping with new applicator.
Installation of pedestrian activated beacons at key locations
In 2005, City Council authorized Tabor funding for several pedestrian projects. These projects
included the Main Street Sidewalk connection between 5`h and 7`h, various ADA ramp
improvements throughout the City among others.
Ina 2008 City Council Work session, staff was directed and provided funding to implement the
following pedestrian/traffic improvements:
City Council directed the committee to move forward with Main Street Median design,
Mill Street/Rio Grande Improvements Design, East of Aspen Pedestrian Connection
Design, and Gibson Ave sidewalk construction.
Two or three electronic speed signs were to be purchased and placed in various locations
(with solar panels) in the City. This item was later removed from the 2009 Budget due to
lack of funds.
City Council identified pedestrian improvements along Aspen's Main Street as one of the ten
Best Year Yet Goals to be complete by the end of 2009. Staff pursued development of the
project in an accelerated time frame based on Council direction to construct a one (1) block
"test" section of an enhanced pedestrian crossing azea to Main Street as soon as possible. This
project attempted to create safer and easier pedestrian crossings of Main Street at the
intersections through the use of center planted medians, enhanced pavement materials, street
plantings and improved lighting at strategic locations. The Main Street Streetscape project
would have a secondazy, equally important benefit by enhancing the visual quality of the
comdor for both motorists and pedestrians.
Staff and SGM presented the proposed design as it has been developed to date to the HPC Boazd
on Januaryl4th 2009. The HPC members did not support the proposal as presented, expressing
criticism to the idea of any kind of raised landscape medians in the center of the Main Street
con•idor. The HPC believed that center landscaped medians were "too urban", and a change that
was completely out of historic chazacter of a wide open corridor flanked by tall stately street
trees.
Staff held a Public Open House, January 28`h in City Council Chambers to solicit public
comment on this proposal.
After a public open house and a subsequent City Council work session the Main Street Median
Project was tabled. However, funding is still required to close out this project.
Remaining funding from the Main Street Median project was set aside be used to design and
implement alternative pedestrian improvements along the Main Street Corridor.
BACKGROUND:
Staff examined various treatments in addition to or in replacement of central medians. Various
factors including general safety, precedence, space constraints, maintenance, accepted
engineering design practices and climate have made these alternatives infeasible. Below is a
summary of the alternatives examined by staff and subsequent reasons why these alternatives are
not recommended:
Temporary Median Planter Boxes -This treatment would involve placing a number of
large landscaped planter boxes along the centerline of Main Street to create a temporary
and removable median treatment.
Constraints: Planter boxes create a crash hazard on high volume roadways such
as Main Street. During a meeting with Colorado Department of Transportation
(CDOT) representatives it became clear that this would not be an approved
treatment in CDOT right of way due to crash hazards.
Intersection Bulb Outs -Bulb outs would change the existing Curb line at pedestrian
crossings. This `bulb' would allow for shorter crossing distances and increased
pedestrian visibly.
Constraints: Bulb outs cannot be placed in RFTA bus routes. Due to the turning
radius of RFTA buses and the outbound bus lane, this treatment would have
limited application. Street maintenance and snow plowing activities would also
be impacted. In addition bulb outs are difficult to for non vehicular traffic such as
bicycles to navigate due to the changing lane width, and unpredictable
interactions with traffic.
Pedestrian Flags -This pedestrian program is intended to change driver behavior and
increase pedestrian visibility by providing cross walk users a small flag to carry as they
cross the roadway.
Constraints: Current municipalities with flag programs have no Engineering
studies to provide data on the program. Communities with this program report an
average use rate around 18% among pedestrians. Large scale public education
campaigns have been launched in communities whose program has lasted more
than 3 years. These public outreach campaigns have been critical in keeping these
programs operational. Staff time is required to replace and move flags. Flag
usage tends to distribute flags unevenly; staff is then required to periodically
redistribute the flags in order for the program to function. High theft rates of flags
and flag infrastructure occur. Studies done by psychology students have shown
no change in driver behavior when pedestrians with flags are present. Various
cities including Berkley, California have eliminated the flag program after a year
due to lack of participation and the drain on City resources.
Pedestrian Activated Flashing Lights -Flashing light systems similaz to the ones in place
on the Original Curve and 8`h Street attempt to alert motorists that pedestrians are in or
entering the crosswalk. These systems can be installed adjacent to the edge of pavement
or overhead by a traffic signal boom.
Constraints: Due to high average daily traffic and limited sight distances these
lighting systems have limited effectiveness on roadways like Main Street. The
Main Street corridor is filled with obstructions such as historic buildings,
landscaping and topography that make these system difficult for motorists to see
and respond to.
DISCUSSION: The Pedestrian and Traffic Safety committee provided City Council with a list
of potential pedestrian improvement projects in July of 2009. Council directed staff to pursue
one project related to Main Street. Staff was directed to finance the design and construction of
two alternative material crosswalks with funding from the Public amenity fund. Staff is
currently developing a request for proposals to begin the design process. In addition to these
physical improvements Staff would like to form a citizens Main Street Pedestrian Safety
Committee due to the large amount of interest by the general public.
Colored/Alternative Material Crosswalks
Installation of colored concrete or other alternative material in pedestrian crossing zones
on the Main Street comdor provides strong visual delineation of pedestrian crossing
zones. Allows unfamiliar motorists to recognize where pedestrians may be present. Staff
would recommend a phased installation of these crossings starting at Garmisch Street and
working west, and at Hunter Street and working east. Colorado Department of
Transportation (CDOT) reacted favorably to this concept during initial meetings because
of its benefit to pedestrians.
Constraints: Changes to the CDOT Right of Way will require approval. Treatment is
difficult to see in the winter. Deterioration possible from current to snow plowing
activities.
Cost.• $25,000 per crossing
Formation of a Citizen's Main Street Pedestrian Safety Committee
Due to the large amount of public interest in Main Street pedestrian safety staff has
suggested that a Citizens committee be formed. Residents who have expressed interest in
pedestrian safety and Main Street will be contacted; in addition staff will advertise the
formation of this body in local newspapers and on the City's website. Staff will run
meetings with this committee to gather citizen input and present the opportunities and
constraints of the current Main Street corridor.
Constraints: Citizen guidance must be appropriate for the given site and be approved by
CDOT and the City's Engineering Department to recommended as appropriate treatments
for Main Street.
Cost: Staff time depending on the duration of this committee.
ENVIRONMENTAL IMPACTS: The Aspen Area Community Plan and City Council
commitments have directed the community to keeping traffic at 1993 levels in perpetuity. At the
same time, Aspen is now considered a maintenance area for PM-10 (particulate) pollution and
must continue reducing vehicular traffic, the major source of particulate pollution, in order to
sustain this maintenance status. To continue meeting both of these goals, it is imperative that
Aspen provide a safe pedestrian and bicycle environment for its residents and visitors.
Implementing a variety of safety improvements will encourage continued pedestrian and bicycle
activity which reduces traffic congestion, decreases air pollution and preserves a small town's
vibrancy.
CITY MANAGER COMMENTS: