HomeMy WebLinkAboutagenda.council.worksession.20100302ASPEN CITY COUNCIL
WORK SESSION
TUESDAY, MARCH 2, 2010
4:30 P.M.
CITY COUNCIL CHAMBERS
Burlingame Phase II Commissioning Agent Selection Recommendations
II. Burlingame Phase II Contractor at Risk Selection Recommendations
7Lj
THE CITY OF ASPEN
MEMORANDUM
TO: Mayor and City Council
FROM: Chris Everson, Affordable Housing Project Manager
THRU: Scott Miller, Capital Asset Director
DATE OF MEMO: February 26, 2010
MEETING DATE: March 2, 2010
RE: Burlingame Phase II Commissioning Agent Selection
Recommendation
REQUEST OF COUNCIL: The Burlingame Phase II Commissioning Agent selection
committee is recommending Engineering Economics Inc. as the Commissioning Agent for the
Burlingame Phase II Integrated Project Delivery design effort. The initial contract amount for the
conceptualization, criteria design and detailed design phases of the Integrated Project Delivery
design is $25,830.00.
Future Council approval would be required to add the implementation documents phase by
addendum which would be an additional $25,240.00. Future Council approval would also be
required to add the construction phase by addendum which would be an additional $128,895.00.
PREVIOUS COUNCIL ACTION: In work sessions with City Council on June 30, 2009 and
October 20, 2009, staff presented a detailed projected cash flow for the 2009 & 2010 Burlingame
Phase II IPD design effort. At that time, staff presented projected total costs for the IPD design
effort of $4.3 million. City Council instructed staff to design the contracts with an initial contract
amount for the conceptualization, criteria design and detailed design phases of the IPD design
process with the potential to add the implementation documents phase at a later date by
addendum.
BACKGROUND: Per the recommendations of the Construction Experts Group (CEG) in 2008
and the subsequent approval of the CEG recommendations by City Council, staff is moving
forward with the Integrated Project Delivery (IPD) model approach for the design of Burlingame
Phase II.
The IPD model entails that the City hire an Owner's Agent, an Architect/Design Team, a
Contractor at Risk and a Commissioning Agent for the IPD process.
Page 1 of 2
THE CITY (W ACPFN
DISCUSSION: The Commissioning Agent evaluation process and recommendation rationale is
outlined in detail in "Exhibit A".
A letter from John Slotkin, a public volunteer on the selection committee and member of the
Construction Experts Group, is included as "Exhibit B"
FINANCIALBUDGET IMPACTS: The budget for the design phase portion of the
Commissioning Agent role is $103,730.00. This contract would provide a savings of $52,660.00
against the design phase budget.
ENVIRONMENTAL IMPACTS: All of the finalists evaluated have communicated a strong
commitment to providing an analysis of environmental considerations as part of the IPD process
which will consider first -cost implications as well as long-term cost considerations as compared
to effectiveness in mitigating environmental impacts. Those decision -making studies will be
presented to Council for consideration during the IPD design effort.
RECOMMENDED ACTION: The selection committee is recommending contract award of
contract as described.
PROPOSED MOTION: Staff requests approval from Council to put this contract on the March
22, 2010 consent agenda
CITY MANAGER COMMENTS:
ATTACHMENTS:
"Exhibit A"
PowerPoint presentation describing the evaluation process and recommendation rationale
"Exhibit B"
Letter from John Slotkin, public volunteer on the selection committee and member of the
Construction Experts Group
Page 2 of 2
..
city c f Burlingame Phase 11 lPD Team Selection
Aspen March 2.2010 Pagel %%
li a e RX a 1wftl c
Affordable Housing Phase 11
Integrated Project Delivery Team Selection
****Commissioning Agent
Aspen City Council Work Session
March 2, 2010
I h
C ify of Burlingame Phase II IPD Team Selection
As pe n March 2 2010 Page 2
Commissioning Agent Summary Description
❖ Participates in all phases of the design and construction
❖ Consults on the design of building systems, energy efficiency
❖ Consults on analysis of potential sustainability certifications
such as Building America or LEED
•:• Formal peer reviews of MEP systems designs
❖ Develops a detailed commissioning plan
❖ Specifications for installation, testing, balancing, training and
turnover of all building systems
❖ During construction, coordinates with the contractor to ensure
systematic implementation of the commissioning plan
❖ Verifies and documents system functionality meets owner's
goals
..
Acity cif Burlingame Phase II IPD Team Selection '�•� _ x
spen March 2. 2010 Page 3
i r r�
Commissioning Agent Phase -by -Phase
Design
Initial
Contract
Minor
Contract
Addendum
(Requires
future Council
approval)
Construction
Major
I Contract
Addendum
(Requires
future Council
Approval)
city )r Burlingame Phase II IPD Team Selection
r
Aspen March 2 2010 Page 4
Commissioning Agent Selection Committee:
**.*John Slotkin - Public volunteer, Construction Experts Group
':' Scott Miller - City of Aspen, Capital Asset Director
****Shaun Rourke - City of Aspen, Senior Engineering Technician
****John Laatsch - City of Aspen, Capital Asset Project Manager
's' Steve Bossart - City of Aspen, Capital Asset Project Manager
'®° Chris Everson - City of Aspen, Affordable Housing Project Manager
Ih �,.
city of Burlingame Phase II IPD Team Selection
Aspen March 2 2010 Page 5 .r -
Commissioning Agent selection Timeline
❖ October 20, 2009
City Council budget approval for 2010 Burlingame phase II
IPD design effort
❖ October 21, 2009
RFQ issued, 8 participants, 5 finalists were issued the
RFP
❖ December 23, 2009
RFP issued, 5 participants, 3 finalists were interviewed
❖ January 15, 2010
Fixed -fee proposals received
City, 1-f Burlingame Phase II IPD Team Selection
Aspen March 2, 2010 Page 6
Commissioning Agent RFC
Firms were asked to provide the following information:
Firm Overview: firm description, ownership structure, company
mission, background of the company and principals
Project Experience: size
references, affordable housing
emphasis mountainous setting,
involvement
& value of each project, project
and/or residential relevance,
sustainable certifications, scope of
y Firm Capabilities: firm's overall capabilities as they relate to
each phase of the IPD process
Personnel: qualifications of the firm's principals, in-house team
leader and the proposed team members
Financial Standing: bankruptcies, lawsuits, liens, letter from
firm's financial institution stating firm's financial stability
"Exhibit A"
city 6f Burlingame Phase II IPD Team Selection
Aspen March 2 2010 Page 8 -- }
Commissioning Agent RFC Evaluations
Finalists of the RFQ process: (invited to participate in the RFP)
❖ Beaudin Ganze
❖ EMC
❖ Engineering Economics Inc.
❖ Lightly Treading
❖ ME Group
❖These finalists demonstrated stronger multifamily
residential commissioning experience, excellent firm
leadership and stronger financial standing.
he
Acity of Burlingame Phase If IPD Team Selection '•-
spen March 2 2010 Page 9 t ..
Commissioning Agent RFP
Firms were provided a detailed scope of work and contracts and
were asked to provide the following information:
Firm Overview: firm description, ownership structure, company mission, background of the
company and principals
Project Experience: size & value of each project, project references, affordable housing
and/or residential relevance, emphasis mountainous setting, sustainable certifications, scope of
involvement
Project Team Qualifications: qualifications of the principal -in -charge and the proposed
project team members, proposed roles and decision -making capabilities for the project, current
resumes
Financial Standinq: bankruptcies. lawsuits, liens, letterfrom firm's financial institution
stating firm's financial stability
Proposed Services: detailed description of the services proposed during each phase of
the project
Proposed Staffing: proposed staffing and billing rates for each team member in each
phase of the project
Proposed Fees: phase -by -phase breakdown of fixed fees, detailed staffing & billing rates
lhn
c n; ,f Burlingame Phase II IPD Team Selection
AsV
` ,e n March 2. 2010 Page 10
commissioning Agent RFP Evaluations
Proposals were evaluated in the following areas:
Each selection team member studied, compared and contrasted the
proposals from each firm and provided quantitative evaluations. The
quantitative evaluations were then compiled and discussed in an open
environment and were vetted among the team to arrive at three finalist firms
to participate in interviews.
Ih,
city 6f Burlingame Phase II IPD Team Selection `-•�
Aspen March 2. 2010 Page 11
Commissioning Agent RFP Evaluations
Invited to interview
❖ Beaudin Ganze
•:- EMC
❖ Engineering Economics
❖ These three finalists demonstrated similar level of fees
proposed, stronger multifamily residential experience,
stronger financial standing
city 6f Burlingame Phase II IPD Team Selection
March 2 2010
Aspen Page 12
Commissioning Agent RFP Evaluations
❖ After the interviews, the selection committee felt it
necessary to gather additional information for further
clarification
❖Additional information requested:
Beaudin Ganze: Clarification of detailed description
of proposed services on a phase -by -phase basis
EMC: Clarification of fees and description of
construction phase services
Both firms were forthcoming with the additional information, however it
was taken into consideration that EEI had provided a high level of detail
in their proposal and thus did not require additional clarification.
"Exhibit A"
ComMISMoning Services
EE1
gG,
EMC'
4.2.1 Conceptualization
4.2.1.1 Consult on the development of owner's requirements for the following systems: Heating,
Ventilating, Fire Alarm, Sprinkler, Domestic Hot Water, Solar Preheating, Ground -source Preheating,
✓
✓
✓
Photovoltaic, Other (see section 8 below)
4.2.1.2 Consult on the early design to meet owner's requirements
/
✓
�/
4.2.1.3 Participate in conceptual construction methodology analysis from commissioning perspective
✓
✓
�/
4.2.1.4 Number of on -site meetings dedicated to this phase
1
1
4.2.1.5 Number of personnel dedicated to the above number of on -site meetings
2
2
1
2
4.2.2 Criteria Design
4.2.2.1 Consult on the development of owner's requirements for the systems listed above to develop th
owners requirements into project design criteria that address systems function, performance, and
✓
✓
✓
maintainability
4.2.2.2 Early design review: first -cost and long-term cost considerations, potential system performanc
problems, energy -efficiency improvements, indoor environmental quality issues, operation and
✓
✓
�/
maintenance considerations
4.2.2.3 Consult to identify potential problems early, before they can affect later phases of the proje ci
and cause delays or require corrections
✓
✓
✓
4.2.2.4 Participate in final construction methodology analysis from commissioning perspective
✓
v
✓
4.2.2.5 Number of on -site meetings dedicated to this phase
1
4.2-2.6 Number of personnel dedicated to the above number of on -site meetings
2
1
2
1
2
c fy of Burlingame Phase II IPD Team Selection
As pe n March 2 2010 Page 14 j
Commissioning Agent - Fee Proposals
Of the three finalists:
✓ Beaudin Ganze is the low bidder
✓ Engineering Economics is second
✓ EMC is highest
ACItYof Burlingame Phase II IPD Team Selection
spen March 2. 2010 z
Page 15
Commissioning Agent Recornmenclati
Enqineerinq Economics Inc.
Selected unanimously by the committee
Best understanding of the City's needs for this project
Fee proposal provides the best level of service for the
price (i.e. best "bang for the buck")
Best qualifications and multifamily residential
experience for commissioning projects
Solid financial standing
Strong references and proven track record on
commissioning projects
Most detailed description of services proposed
Scored the highest in all key categories of evaluation
c iy � f Burlingame Phase 11 IPD Team Selection "y
As pe n March 2. 2010 Page 16
Commissioning Agent RFP Evaluations
Positive references for Engineering Economics
were verified by the selection committee from
representatives on the following Engineering
Economics projects:
Cascades Residences, Vail, CO
Mountain View Residences, Vail, CO
Pitkin County Public Works, Aspen, CO
Viceroy Hotel, Snowmass Village, CO
rhn
City (af
Aspen
Burlingame Phase II IPD Team Selection "•
March 2, 2010
Page 17
Discussion?
Questions?
-
"Exhibit B"
John Slotkin
Aspen Colorado
02/24/2010
As a member of the original Burlingame construction experts group I was asked
to participate in the phase two commissioning agent committee. I was the only
private citizen to partake.
WE studied eight proposals from top to bottom.
Arrived at five proposals through an elimination process
We scored them on every aspect one could imagine, from Leed projects, to
previous work in our county, financials, and many of their projects around the
country.
With discussion and due diligence we arrived at four final bidders
Interviews were held with three of these companies and after discussion we
arrived at two finalists.
Our job was to find the best company for our needs.
I would also add a company that will still be operating down the line since
this project might take quite a while to restart
Engineering Economics, and Beaudin Ganze ,and EMC the three finalists,
proposals were again dissected and many aspects of their proposals were again
evaluated.
Engineering Economics was our unanimous choice.
"Exhibit B"
The reason was simple although their bid was a few thousand dollars more
the offer and breakdown of services were a much better deal and the spectrum
was far better than Beauden Ganze.
This was the best and most efficient offer across the board. In the long run it
will save this project much more.
From my point of view I thought the financials of these bidders were
imperative since this project won't take place for quite a while, in this economy
it was important to choose a company I felt that would still be in a responsible
position down the line.
I would like to add how lucky the town of Aspen is to have Chris Everson,
Scott Miller, Shaun Rourke, Steve Bossart, and John laatsh watching out for
Aspen's best interest.
It was an honor to work with the selection committee and sincerely hope our
recommendation is carried out by our town council.
John Slotkin
THE CITY OF ASPEN
MEMORANDUM
TO: Mayor and City Council
FROM: Chris Everson, Affordable Housing Project Manager
THRU: Scott Miller, Capital Asset Director
DATE OF MEMO: February 26, 2010
MEETING DATE: March 2, 2010
RE: Burlingame Phase II Contractor at Risk Selection Recommendation
REQUEST OF COUNCIL: The Burlingame Phase II Contractor at Risk selection committee is
recommending Haselden Construction as the Contractor at Risk for the Burlingame Phase II
Integrated Project Delivery design effort. The initial contract amount for the conceptualization,
criteria design and detailed design phases of the Integrated Project Delivery design is
$122,174.00. Future Council approval would be required to add the implementation documents
phase by addendum which would be an additional $54,925.00 for a total design phase contract of
$177,099.00.
PREVIOUS COUNCIL ACTION: In work sessions with City Council on June 30, 2009 and
October 20, 2009, staff presented a detailed projected cash flow for the 2009 & 2010 Burlingame
Phase II IPD design effort. At that time, staff presented projected total costs for the IPD design
effort of $4.3 million. City Council instructed staff to design the contracts with an initial contract
amount for the conceptualization, criteria design and detailed design phases of the IPD design
process with the potential to add the implementation documents phase at a later date by
addendum.
BACKGROUND: Per the recommendations of the Construction Experts Group (CEG) in 2008
and the subsequent approval of the CEG recommendations by City Council, staff is moving
forward with the Integrated Project Delivery (IPD) model approach for the design of Burlingame
Phase II.
The IPD model entails that the City hire an Owner's Agent, an Architect/Design Team, a
Contractor at Risk and a Commissioning Agent for the IPD process.
DISCUSSION: The Contractor at Risk evaluation process and recommendation rationale is
outlined in detail in "Exhibit A".
A letter from Peter Louras, a public volunteer on the selection committee and member of the
Citizens Budget Task Force, is included as "Exhibit B"
Page 1 of 2
0
THE CITY of ASPEN
FINANCIALBUDGET IMPACTS: The budget for the design phase portion of the Contractor
at Risk role is $280,500.00. This contract would provide a savings of $103,401.00 against the
design phase budget.
ENVIRONMENTAL IMPACTS: All of the finalists evaluated have communicated a strong
commitment to providing an analysis of environmental considerations as part of the IPD process
which will consider first -cost implications as well as long-term cost considerations as compared
to effectiveness in mitigating environmental impacts. Those decision -making studies will be
presented to Council for consideration during the IPD design effort.
RECOMMENDED ACTION: The selection committee is recommending contract award of
contract as described.
PROPOSED MOTION: Staff requests approval from Council to put this contract on the March
22, 2010 consent agenda
CITY MANAGER COMMENTS:
ATTACHMENTS:
"Exhibit A"
PowerPoint presentation describing the evaluation process and recommendation rationale
"Exhibit B"
Letter from Peter Louras, public volunteer on the selection committee and member of the
Citizens' budget Task Force
Page 2 of 2
lh� _
city =--f Burlingame Phase II IPD Team Selection
Aspen
March2. 2010 Page 1
Affordable Housing Phase 11
Integrated Project Delivery Team Selection
****Contractor at Risk
Aspen City Council Work Session
March 2, 2010
c ty ,f Burlingame Phase II IPD Team Selection r'
As pe n March 2. 2010 Paget
Contractor at Risk Summary Description
❖ Participates in all phases of the design effort
❖ Consultation on constructability, means and
methods
❖ Analysis of stick -built versus modular versus
panelized
❖ Estimates the project and creates the GMP bid
❖ City Council may choose to source the
construction of the project to the contractor at risk
❖ Alternatively, City Council may choose to bid the
project out
I h ,.
ACity 6f Burlingame Phase II IPD Team Selection
spen March 2 2010 Page 3
Initial
Contract
Design
Minor
Contract
Addendum
(Requires
future Council
approval)
Phase-
Construction
Major
Contract
Addendum
(Requires
future Council
Approval)
_l h�
cIcy, 6f Burlingame Phase II IPD Team Selection
Aspen ...
March 2 2010 Page 4
Contractor at Risk Selection Committee
sus Peter Louras - Public Volunteer, Citizens' Budget Task Force, CPA
•'.o Bob Daniel - Public Volunteer, Construction Experts Group, Developer
❖ Scott Miller - City of Aspen, Capital Asset Director
•:° Tricia Aragon - City of Aspen, City Engineer
•o• Shaun Rourke - City of Aspen, Senior Engineering Technician
+ John Laatsch - City of Aspen, Capital Asset Project Manager
•e°
Steve
Bossart -
City
of Aspen,
Capital Asset Project Manager
'®°
Chris
Everson
- City
of Aspen,
Affordable Housing Project Manager
Ih
City oof Burlingame Phase II IPD Team Selection
Aspen March 2. 2010 Pages
Contractor at Risk Selection Timeline
*.**October 20, 2009
City Council budget approval for 2010
design effort
❖ October 21 2009
RFQ issued, 10 participants, 6 finalists
Burlingame phase II IPD
❖ December 23, 2009
RFP issued, 6 participants, 3 finalists were interviewed
*.**January 15, 2010
Fixed -fee proposals received
❖ January 29 and Februa
19, 2010
Received additional information, as requested
c tT h Burlingame Phase II IPD Team Selection
Aspen ..
March 2 2010 Page 6
ontractor at Risk RFQ
Firms were asked to provide the following information:
Firm Overview: firm description, ownership structure, company
mission, background of the company and principals
Project Experience: size & value of each project, project
references, affordable housing and/or residential relevance, emphasis
mountainous setting, sustainable certifications, scope of involvement
Firm Capabilities: firm's overall capabilities as they relate to each
phase of the IPD process
Personnel: qualifications of the firm's principals, in-house team
leader and the proposed team members
Financial Standing:_ bankruptcies, lawsuits, liens, letter from
firm's financial institution stating firm's financial stability
Th
Ac4Y of Burlingame Phase II IPD Team Selection
spen March 2. 2010 Pagel
Contractor at Risk RFQ Evaluations
Qualifications were evaluated in the following areas:
❖ Management Experience and Capabilities
Qualifications of the firm principals
Qualifications of the proposed team members
Preconstruction services experience and capabilities
❖ Building Experience and Capabilities
Large-scale construction experience and capabilities
Multifamily construction experience and capabilities
Public projects experience and capabilities
Green building experience and capabilities
❖ Financial Stability & Capacity
Financial Standing
Size and scale of projects completed
Bankruptcies, lawsuits, liens
Each selection team member studied, compared and contrasted the
qualifications of each firm and provided quantitative evaluations. The
quantitative evaluations were then compiled and discussed in an open
environment and were vetted among the team to arrive at the six finalist
firms to participate in the RFP.
i I I'?
City caf Burlingame Phase II IPD Team Selection
Aspen
March 2 2010 Page 8
Contractor at Risk RFQ Evaluations
Finalists of the RFQ process. (invited to participate in the RFP)
••• C FC
❖ Evans Chaffee Construction Group
❖ Fenton Construction
❖ Haselden Construction
❖ R.A. Nelson
❖ Shaw Builders
❖ The finalists generally had extensive large-scale
multifamily residential experience, excellent team
leadership and stronger financial standing
I he
city of Burlingame Phase II IPD Team Selection �-•-
Aspen March 2. 2010 Page 9
Contractor at Risk RFP
Firms were provided a detailed scope of work and contracts
and were asked to provide the following information:
Firm Overview: firm description, ownership structure, company mission, background of the
company and principals
Project Experience: size & value of each project, project references, affordable housing
and/or residential relevance, emphasis mountainous setting, sustainable certifications, scope of
involvement
Project Team Qualifications' qualifications of the principal -in -charge and the proposed
project team members. proposed roles and decision -making capabilities for the project, current
resumes
Financial Standing: bankruptcies, lawsuits, liens, letter from firm's financial institution stating
firm's financial stability
Proposed Services' detailed description of the services proposed during each phase of the
project
Proposed Staffing: proposed staffing and billing rates for each team member in each phase of
the project
Proposed Fees: phase -by -phase breakdown of fixed fees. detailed staffing & billing rates
c t'y{ " r Burlingame Phase II IPD Team Selection
Asri
e 1 1 March 2 2010 Page 10 �J'
Contractor at Risk RFP Evaluations
Proposals were evaluated in the following areas:
❖ Experience & Qualifications:
r Relevant experience
Project team qualifications
References
:® Proposed Services:
. Project understanding
Proposed services
Proposed staffing
Financial:
Fee proposal
Financial standing & bonding
Bankruptcies, lawsuits, liens
Each selection team member studied, compared and contrasted the
proposals from each firm and provided quantitative evaluations. The
quantitative evaluations were then compiled and discussed in an open
environment and were vetted among the team to arrive at three finalist firms
to participate in interviews.
the
c4 ,->f Burlingame Phase II IPD Team Selection
Aspen r
March2 2010 Page11
Contractor at Risk RFP Evaluations
Invited to interview
•:• CFC / John Olson Builder
❖ Haselden Construction
❖ Shaw Builders
❖ All three had detailed fee proposals, strong multifamily
residential experience, strong financial standing and
scored highest within the evaluation criteria
c t'y of Burlingame Phase II IPD Team Selection
;a
Aspen March 2 2010 Page 12
Contractor at isk RFP Evaluations
❖ After the interviews, the selection committee felt that
additional information should be requested
❖ Additional information request #1
Additional information request #1 focused on depth of experience based
on total dollar volume of work over the past three years for:
Mid -range versus high -end residential construction
Multifamily construction by construction methodology
Commercial versus residential construction
Single most expensive construction project
Public versus private work
Projected overhead & profit for Burlingame II
Projected general conditions for Burlingame II
This information was received and incorporated into the evaluations
he
ACity 6f Burlingame Phase II IPD Team Selection
spen March 2 2010 Page 13
Contractor at Risk RFP Evaluations
❖ For further due diligence, the selection committee chose
to ask for additional information a second time:
❖ Additional information request #2
Audited Financial Statements
Quality control/assurance procedures & protocols
Experience modification worksheets (insurance claim history)
Subcontractor prequalification & selection process
Work completion history
General liability loss runs for past 5 years
Pending litigation
BIM service description
General conditions matrix identifying service levels
This information was received and incorporated into the evaluations
rrC..1.�Mlr err
PRECONSTRUCTION FEE
CONSTRUCTION FEE
GENERAL CONDITIONS
DIKED I UUa I Iu ussncrc
WORK HEADING
SHAW HASELDN CFC
SHAW HASELDN CFC
SHAW HASELDN CFC
SHAW HASELDN CFC
PROJECT MANAGEMENT
1. AKhMchad CZ-F dWWd Selection
x
Sinrchad Camullartt Sdacdon
x
Sam : Additia a items Wshown here
HASELDN CFC
SHAW HASELDN CFC
SHAW HASELDN CFC
SHAW HASELDN CFC
CONTRACT DOCUMENT COORDINATION
SHAW
t. reel con
x x
x x x
constucbm con &rd9el
x x
3. Cmahucbon con offot a
x
CFC
AdWmW items not shown here
CFG
SHAW
HASELDN
CFC
SHAW
HASELDN
CFC
SHAW HASELDN
SUBCONTRACTOR SELECTIONIPURCHASING
SHAW HASELDN
1. Set Crietia
X x x
x
x
2 Remnnew COn� Me1tpM
x x x
x
25e*cum
3. RewrrenerM CarNeceor Awanf hnev
x x x
Only: AddMonal items not ahorrn here
HASELDN CFC
SHAW
HASELDN
CFC
SHAW
HASELDN
CFC
SHAW HASELDN
CFC
TRACT DOCUMENT COORDINATION
SHAW
bi Reviewand Recmvnnndims
X x
xx
x x
xx
XwucbMitll
x:Additional
Review andRecamnende6ons
Work Scopn9
contactor
hemsnotshownhereTE
SHAW HASELDN
CFC
SHAW
HASELDN
CFC
SHAW
HASELDN
CFC
SHAW HASELDN
CFG
STAFF
ject Ewadive (time essodated wim project)
lStmoffT
X
X
X
x
x
xxject
xxmr*
stgiwn xjent
rdenga
xxisdnt
ssmWe
SHAW HASELDN
CFC
SHAW
HASELDN
CFC
SHAW
HASELDN
CFC
SHAW
HASELDN
CFC
. Additional items not shown hereEL&LODGING
f Travel Cost ablate
X
x
x
x
x
tyr
x
x
x
Project Stilt Movin
I
x
x
x
x
Staff SulrwKlence Costa
x
x
x
x
5. Stdf ttauai me
Sam Only: Adddiond items not shown hero
i---A
ciri of Burlingame Phase II IPD Team Selection
Aspen
March 2 2010 Page 15
to
Contractor at Risk RFP Evaluations
❖ Comparison of Overhead & Profit and General Conditions Costs
These costs apply ONLY to the construction phase, not design phase
Contractor's construction phase fees are much larger than
preconstruction fees
Committee was cautious about selecting a contractor with low design
phase costs and high construction phase costs
c tv r Burlingame Phase II lPD Team Selection
Aspen
March 2 2010 Page 16
Contractor at Risk RFP Evaluations
Preconstruction Fixed -Fee Proposals
* These fixed -fee proposals apply to the design phase only.
Of the three finalists:
✓ Haselden is the low bidder
✓ CFC is the second lowest bidder
✓ Shaw is the highest bidder
the
Acity of Burlingame Phase II IPD Team Selection "�•� t
spen March 2010 Page17 _
Contractor at Risk RFP Evaluations
❖ Throughout the entire process, the selection committee
unanimously agreed that Haselden clearly ranked best and
highest:
Cif'y 6f Burlingame Phase II IPD Team Selection
Aspen March 2 2010 Page 18 1 i
Contractor at Risk RFP Evaluations
❖ Positive references for Haselden construction were
verified by the selection committee from
representatives on the following Haselden projects:
Roaring Fork School District
Eagle County
Eagle County School District
National Renewable Energy Laboratory
Aspen Valley Hospital
Lodge at Mountaineer Square, Crested Butte
c r'%e f Burlingame Phase Il IPD Team Selection
AeSp '"-
� ( March2,2010 Page -- i
i
Contractor at Risk Recommendation
Haselden Construction
Selected unanimously by the committee
Demonstrated the best understanding of the City's
needs for this project
Excellent qualifications and the most public experience
Strongest demonstrated financial standing
Comprehensive, very strong proposed team
Lowest preconstruction fee proposal
Lowest general conditions and overhead & profit
Strong references and proven track record
Most detailed description of services proposed
Scored the highest in all key categories of evaluation
"Exhibit A"
"Exhibit B"
February 24, 2010
The City of Aspen City Council
City Hall
130 S. Galena St
Aspen, CO 81611
Dear Councilmen:
I have been a citizen member of the Contractor at Risk Selection Committee since
the group was officially organized on December 9, 2009. Our committee was
charged with the responsibility of making a recommendation for the Contractor at
Risk role in the City's Integrated Project Delivery (IPD) Team for Burlingame
Ranch Phase II.
It is the role of the Contractor at Risk to develop preconstruction recommendations
and specifications regarding building systems designs, construction means,
scheduling and construction costs, as well as be the contractor at risk for the
construction of the project.
Citizen Role:
As a private citizen of Aspen, I saw my role as twofold: first, to participate in all
aspects of the committee's work to arrive at a final recommendation for the
Contractor at Risk; and, second, to provide objective oversight and an independent
voice for the community in the overall process.
With regards to the first role, the committee was very diligent and purposeful in its
work with all committee members having an equal voice. To complete the task at
hand, assignments were given, documents were reviewed, and evaluation forms
were completed, compiled, and later discussed in open meetings. Discussions
during a number of meetings led to additional information requirements from
respondents to the RFP. Each committee member participated fully in each step of
the process, and as a private citizen, there were no aspects of the work that I wasn't
fully involved with.
11�111:71m 3i
2
On the second role, I was impressed with how City Staff organized the overall
recommendation process, how committed they were to identifying the very best
contractor at a reasonable price and how objective they were in evaluating the
strengths and weaknesses of different proposals. In addition, Staff was very
respectful of the City's Request for Qualifications (RFQ) and Request for Proposal
(RFP) processes. The overall process was well organized; all necessary material
was provided in a timely fashion; evaluation techniques and forms were fair and
objective; and the overall process was very open and candid. Each and every
committee member was conscientious about completing assignments and attending
meetings. As a private citizen, less familiar with the overall IPD process, I asked
many questions which were always answered candidly with the necessary facts to
satisfy my concerns.
In summary, I want to commend all members of the committee for their efforts
during this recommendation process, but in particular Chris Everson and John
Laatsch who played important leadership roles in guiding the overall effort.
...............................................................................
As a member of the Citizens Budget Taskforce (CBTF) in 2008, I also want to
commend City Staff for following through and implementing the many different
recommendations of the CBTF, and the related recommendations of the
Construction Experts Group, regarding capital project management and planning.
The IPD process was one of those recommendations and it is very comforting to
know our many recommendations are being embraced and implemented as
intended.
Finally, I recommend that more citizens of our community find the time to
volunteer and serve on committees or taskforces to learn more about how our
municipal government operates and gain a better appreciation for the many
hardworking staff members performing so many valuable functions for our
community.
Sincerely,
Pete Louras
260 Mountain Laurel Dr.
Aspen, CO 81611