HomeMy WebLinkAboutagenda.council.worksession.20100907C�
THE Ory of ASPEN
MEMORANDUM
TO: Mayor and City Council
FROM: Chris Everson, Affordable Housing Project Manager
THRU: Scott Miller, Capital Asset Director
DATE OF MEMO: September 3, 2010
MEETING DATE: September 7, 2010
RE: Burlingame Phase II Phasing and Demand
REQUEST OF COUNCIL: Direction requested
PREVIOUS COUNCIL ACTION: On July 12, 2010, City Council formalized conceptual
approval of major elements of the Burlingame Phase II concept master plan.
BACKGROUND: On August 17, 2010, staff provided City Council with an update on the 50%
Detail Design plans. At that time, it was suggested that staff return on September 7 to discuss
potential phasing for the construction of the development, and staff was instructed to bring
proformas for the various phasing scenarios being considered.
DISCUSSION: In considering construction phasing options for Burlingame Phase II, the design
team has recognized the following issues:
❖ Phasing of unit deliveries is more than just a construction management challenge
❖ Construction efficiency is desirable to keep costs down
Financial constraints must be considered
❖ Care must be taken to avoid flooding the market (demand concerns)
It is desirable to minimize impacts to the neighborhood
❖ Flexibility is desirable in case of external forces
❖ If implementation must stop, a livable community should remain
❖ Individual phasing scenarios may be good at addressing some priorities, but not all
Although there are a number of more complex ways of looking at potential phasing options, this
memo will focus on only four simplified phasing options A, B, C and D as follows:
Page 1 of 5
C�
THE CITY or ASPFN
Op tion A: Construct and deliver 167 units in a single construction mobilization effort lasting
approximately 36 months with no breaks.
A 36 month schedule would ma ximize construction efficiencies and minimiz the duration of
neighborhood impacts, but would also put 167 new housing units on the market on a schedule
that may not provide adequate opportunity for market absorption and could thus prove more
costly than any savings that could result from the construction efficiencies that come with
building all at once.
Staff understands that City Council is not interested in building the whole Phase II development
at once, but this scenario provides a baseline understanding of the cost impacts of building more
quickly as opposed to building more slowly.
Op tion B: Construct and deliver two separate groups of approximately 83 units each,
utilizing two separate construction mobilization efforts with a gap of 5 years
between each of the two construction efforts.
Constructing two groups of approximately 83 units each in two separate construction efforts
would still provide a large enough scale of construction to create a high level of construction
efficiency. In between the two construction efforts, a five -year stop is assumed, during which
time a livable community will be left for homeowners to enjoy. Construction impacts will
adversely affect the neighborhood during the second construction effort, but the market will have
five years to fully absorb the first group of units before the second construction effort would
begin. In the event that market absorption occurred sooner, the second construction effort could
be kicked off sooner. If the market absorption takes longer than anticipated, the second
construction effort could be delayed until the entire first group of units has been purchased.
lion C: Construct and deliver three separate groups of approximately 55 units each,
utilizing three separate construction mobilization efforts with a gap of 1 year
between each of the three construction efforts.
Constructing three groups of approximately 55 units each in three separate construction efforts
would provide some construction efficiency, but the burden of construction impacts would be
shared by many more families. In between the three construction efforts, there would be two 1-
year construction stops during which time a livable community would be left for homeowners to
enjoy. Construction impacts would adversely affect the neighborhood during the second and third
construction efforts, but the market would have a year to bounce back from the first group of 55
units and a second break of an additional year to absorb the second group of 55 units. If the
market absorption takes longer than anticipated at any time, the next construction effort could be
delayed until the entire group of previously delivered units has been purchased.
Page 2 of 5
C�
THE CnY of ASPEN
Op tion D: Construct and deliver four separate groups of approximately 42 units each,
utilizing four separate construction mobilization efforts with a gap of 1 year
between each of the four construction efforts.
Constructing four groups of approximately 42 units each in four separate construction efforts
would create the least construction efficiency of the options presented here. The burden of
construction impacts would borne by hundreds of families.
During each of the I -year construction stops between each delivery of approximately 42 units, a
livable community would be left for homeowners to enjoy. The market would have a year to
bounce back from each group of approximately 42 units delivered. If the market absorption takes
longer than anticipated at any time, the next construction effort could be delayed until the entire
group of previously delivered units has been purchased.
Proforma Assumptions:
Assumptions in the proformas below include a July 2011 construction start with 3% per year
escalation on all costs and 2% per year escalation on all sales revenues. Additional assumptions
for all proformas shown here include revenues resulting from a category mix equivalent to
Burlingame Phase I. Financing costs would be in addition to costs shown. All of the proformas
assume 100% site grading and utility installation occurs up front.
Although many of these factors are impossible to accurately predict, they are nonetheless held
constant for all of the proformas presented in this memo. Economic factors will undoubtedly
affect the accuracy of the proformas below, but the intent of comparing these proformas is to
give Council an idea of how different phasing options might affect overall project performance.
The proformas below are based on the 50% Detail Design plans created by OZ Architecture and
the 50% Detail Design estimate created by Haselden Construction and additionally based on due
diligence regarding soft costs, fees, cash flows and contingencies by Owner's Agent, Rider Levett
Bucknall and are subject to change as the design continues to be developed. These proformas are
based on current working estimates and cannot be guaranteed at this time. Extensive detail is
available upon request. The team is currently in the process of creating 100% Detail Design plans
which will be the basis for a 100% Detail Design estimate and GMP proposal from Haselden
Construction.
Page 3 of 5
70
THE Clry of ASPEN
Burlingame Ranch Phase it
Comparison of Phasing Scenario Protect Estimates
nw.2 aeptemier2010 Estimates for Phase II construction Phasing Options
Phase 1 Option A Option B Option C Option D
(Actual Q 91 (1 Sequence @ (2 Sequenoes @ (3 Sequences @ (4 Sequences Q
Units) 197 units) -83 nits ea) -55 units ea) -42 units es)
Proposed direction:
In the case of each construction phasing scenario, there is no way of knowing how the market
will respond to the first group of units delivered. A detailed market study utilizing a combination
of survey questions and market data could try to predict how the market would respond, but
relying on such a study may prove as precarious as relying on recent Aspen/Pitkin County
Housing Authority lottery bid counts.
The purpose of the housing lottery is to provide a fair chance for local workers to obtain housing
given high demand and low supply. The question of adequate demand as it relates to what might
be the appropriate size of any first delivery of units at Burlingame Phase II creates the potential
for a situation where supply could outweigh demand — the opposite situation for which one would
employ the use of a lottery.
Related to the question of whether or not adequate demand exists, one recent suggestion is to
avoid the use of a lottery and to pre -sell units to local workers who would be required to qualify
with APCHA and place a deposit on a housing unit. The original suggestion was, for the sake of
fairness, to open up the first 80 units (roughly half of Burlingame Phase II) for pre -sale and to
offer the balance of units via lottery. The size of the first group of units to be constructed and
Page 4 of 5
Prior Incurred Soft Costs (Sunk costs Incurred at the time of Phase 1)
1,078,404
1,078,404
1,078,404
1,078,404
2010 Planning 8 Design Budget
2,451,880
2,451,880
2,451,880
2,451,880
2011 Planning a Design Budget
1,500,000
1,500,000
1,500,000
1,500,000
a] rf � non
Offsite Infrastructure (Sunk Costs incurred at the time of Phase 1)
4,295,377
4,285,377
4,295,377
4,295,377
Mitigation Projects (Sunk Costs incurred at the time of Phase l)
3,563,104
3,563,104
3,563,104
3,583,104
Offsi[e Storm Sewer(ModiFCation to existing)
305,000
305,000
305,000
305,000
Site Infrestucture -Gas Supply (Estimate by Haselden Construction)
100,000
100,000
100,000
100,000
Site Infrastucture - Electrical Underground (Estimate from utilities Dept)
300,000
300,000
300,000
300,000
Site Infrastructure - Electrical Supply (Estimate from Utilities Dept) 750,000
�e�".Et�.r��l' �!rfical GpnsiNphpn, );1g4aldeltE!{ilate
750,000 750,000 750,000
Proposed direction:
In the case of each construction phasing scenario, there is no way of knowing how the market
will respond to the first group of units delivered. A detailed market study utilizing a combination
of survey questions and market data could try to predict how the market would respond, but
relying on such a study may prove as precarious as relying on recent Aspen/Pitkin County
Housing Authority lottery bid counts.
The purpose of the housing lottery is to provide a fair chance for local workers to obtain housing
given high demand and low supply. The question of adequate demand as it relates to what might
be the appropriate size of any first delivery of units at Burlingame Phase II creates the potential
for a situation where supply could outweigh demand — the opposite situation for which one would
employ the use of a lottery.
Related to the question of whether or not adequate demand exists, one recent suggestion is to
avoid the use of a lottery and to pre -sell units to local workers who would be required to qualify
with APCHA and place a deposit on a housing unit. The original suggestion was, for the sake of
fairness, to open up the first 80 units (roughly half of Burlingame Phase II) for pre -sale and to
offer the balance of units via lottery. The size of the first group of units to be constructed and
Page 4 of 5
7LJ
THE CrrY of ASPEN
delivered could be based upon the number of units that could be pre -sold in such an effort.
Utilizing such a system may help the community address the question of demand and how to
appropriately size the fast delivery of units at Burlingame Phase II.
FINANCIAL /BUDGET IMPACTS: The current scope of work for the Burlingame Phase H
Integrated Project Delivery team does not include a marketing campaign for the pre -sale of
housing units. If Council were to direct staff to work with the Housing Authority to design such a
pre -sales effort, additional costs would need to be estimated and a marketing component would
likely need to be added to the effort.
Additionally, the IPD design team is closing in on its completion of 100% Detail Design and
needs approval to begin work on the Implementation Documents phase of the design effort which
will take the team through PUD approval and will deliver buildable plans to the City. The IPD
team consultant contracts were set up, at the request of City Council, to run through 100% Detail
Design and to have the ability to add the Implementation Documents phase of the design by
addendum. The 2010 IPD design effort is substantially under budget, and revenues are greater
than originally projected. Staff requests that Council direct staff to place the Implementation
Documents phase of the IPD team consultant contracts on the next available consent calendar.
ENVIRONMENTAL IMPACTS: Please review the above statements on construction impacts.
RECOMMENDED ACTION: Staff requests direction from Council to pursue consensus with
APCHA and Pitkin County for the described pre -sales effort. Additionally, staff requests
direction from Council to place the IPD team contract addenda for the Implementation
Documents phase of the Burlingame Phase H IPD design effort on the next available consent
calendar.
CITY MANAGER
ATTACHMENTS:
Exhibit A: PowerPoint Presentation
Page 5 of 5
Burlingame Ranch Phase II
Integrated Project Delivery Design
Construction Phasin
Aspen City Council Work Session
September 7, 2010
❖ On August 17, 2010 Council was presented with information about:
1. Unit floor plans
2. Site landscape / unit owner patio areas
3. Architectural character
4. Snow drop / public safety
5. Mechanical systems recommendation
6. Construction phasing
At that work session, staff was directed to return on Sept 7 with construction
phasing options including estimates for each of the phasing options.
Today's agenda:
1. Construction Phasing
2. Proposed Direction
Quick review:
Higher -speed
❖ Greatest cost
efficiency
❖ Greatest risk of
over - supply
❖ Lowest ability to
adapt to external
forces
❖ Shortest duration of
neighborhood
impacts
❖ Highest intensity of
neighborhood
impacts
❖ Least flexibility
❖ Medium cost
efficiency
❖ Measured risk of
over - supply
❖ Ability to adapt to
external forces
❖ Balance of duration
and intensity of
neighborhood
impacts
❖ Balanced Flexibility
Lower -speed
implementation
❖ Lowest cost
efficiency
❖ Lowest risk of
over - supply
❖ Greatest ability to
adapt to external
forces
❖ Longest duration
of neighborhood
impacts
❖ Lowest intensity
of neighborhood
impacts
❖ Greatest flexibility
Construction Phasing: Continuum
Although there are many options and details related to each construction
phasing option, for the purposes of simplifying today's high -level discussion,
the phasing options have been simplified to the following:
Option A: Construct and deliver 167 units in a single construction mobilization effort
lasting approximately 36 months with no breaks. (This option is shown only for
baseline proforma comparison.)
Option B: Construct and deliver two separate groups of approximately 83 units each,
utilizing two separate construction mobilization efforts with a gap of 5 years between
each of the two construction efforts.
Option C: Construct and deliver three separate groups of approximately 55 units
each, utilizing three separate construction mobilization efforts with a gap of 1 year
between each of the three construction efforts.
Option D: Construct and deliver four separate groups of approximately 42 units each,
utilizing four separate construction mobilization efforts with a gap of 1 year between
each of the four construction efforts.
Construction Phasing: Simplified
❖July 2011 construction start
❖ 3% per year escalation on all costs
❖ 2% per year escalation on all sales revenues
❖ 100% site grading and utility installation occur up -front
❖ Category mix equivalent to Burlingame Phase I
****Financing costs are not included
Although many of these factors are impossible to accurately predict, they are nonetheless held
constant for all of the proformas presented in this memo. Economic factors will undoubtedly
affect the accuracy of the proformas below, but the intent of comparing these proformas is to give
Council an idea of how different phasing options might affect overall project performance.
The proformas below are based on the 50% Detail Design plans created by OZ Architecture and
the 50% Detail Design estimate created by Haselden Construction and additionally based on due
diligence regarding soft costs, fees, cash flows and contingencies by Owner's Agent, Rider
Levett Bucknall and are subject to change as the design continues to be developed. These
proformas are based on current working estimates and cannot be guaranteed at this time.
Extensive detail is available upon request. The IPD team is currently in the process of creating
100% Detail Design plans which will be the basis for a 100% Detail Design estimate and GMP
proposal from Haselden Construction.
Construction Phasing: Proforma Assumptions
Burlingame Ranch Phase 11
Comparison of Phasing Scenario Project Estimates
far. 2 Sepien*w 2010
1 Estimates for Phase 11 Construction Phasing Options I
Phase 1
Option A Option O
Option C
Option D
(A CUMI 1@ 91
(1 sequence a (2 Sequences a
(3 Sequences @
(4 Sequences I@
Units)
167 units) -63 nits ea)
-55 units as)
-42 urns ea)
Prior Incurred Soft Costs (Sunk costs incurred atthetimeofPhase1)
1,078,404
I.G74404
1,076.404
1AM404
2010 Planning ti: Design Budget
2.451.880
2,451,,880
2,461,880
2,451,850
2011 Planning 8 Design Budget
_....._ _.,. ._ „�.. .....
1.3 00,000
... .. ,..�,:—
1.50D 1 500„000 1,5M,000
.uu ^spa++. ...✓x. r flvamiS' ••"SF1Tf.4 R14 AS•- X^�"_MSE
CIWte Inias4uct re (Smic Costs ivarrred at the tine of Phase 1)
Mligation Projects (Sunk Costs incurred at the time of Phase 1)
Ofisia SGenn Sewer (Modification to existing)
Silo ifirastuct re- Gas Supply ( rnste by Haselden Construction)
Sibs triastudure- Electrical Underground (Estwrate from Uses Dept)
42951377
4.285.377
3,5631104
3,583,104
306,006
305.000
100.000
100.000
300.000
300,000
750,000
750,000
4296.377
4296,377
3,563,104
3,-AM104
305.000
306,1)00
100.000
108;000
300,000
300,000
Ste iriastruchra - Electrical Supply (Estimate from Militias
Construction Phasing: Proformas
Burlingame Ranch Phase II
Estimated Project Cost
N TOTAL ESTIMATED UNITSALES REVENUES ETOiAL ESTIMATED SUBSIDY
f frf frr
Fl. . - 012011104:11
N rfr frr
f rfr rrr
F 057, f 1 I l i
Total Project Cost and Subsidy
Phase 1 Option A Option a Option C Option D
[Actum' OLD 91Unftsl t1 Sequence CD 167 units) (2SequencestR 93 nits es) J3' SequencesLD - SS units 14 Sequences Lb -42 units
eal eal
Burlingame Stanch Phase II
Estimated Project Cost (Per Unit)
1• TOTAL ESTIMATED SALES REVENUE PER UNIT ■TOTAL ESTIMATED SUBSIDY PER UNIT
iw;wu
soDn4o
$578,210
$618,126
$563,435
$620,416
$641,499
SWAIM
4W.I=
30f1AW
2WAW
1W.00o
M1
phase 1 Option A Option B Option G Option D
(Actual 0 91 Units) tl Sequence 0187 units) (ZSequences i@ ^83 nits w) [3Sequenoes 0 ^55 units m) 145e;uenoes 0 —42 units my
Per Unit Cost and Subsidy
1) Staff requests direction from Council to pursue
consensus with APCHA and Pitkin County for the pre -
sales effort described in the attached memo to Council.
2) Staff requests direction from Council to place the IPD
team contract addenda for the Implementation
Documents phase of the Burlingame Phase II IPD design
effort on the next available consent calendar.
Proposed Direction