AGENDA
City Council Special Meeting
April 24, 2019
4:00 PM, City Council Chambers
FOR THE PURPOSE OF:
Authorization for City Manager to spend contingency dollars for Project 51112: utility
work for 425 Rio Grande
1
Page 1 of 2
MEMORANDUM
TO:Mayor and City Council
FROM:Robert Schober, Project Manager
THROUGH:Jeff Pendarvis, Interim Capital Asset Manager
DATE OF MEMO:April 24, 2019
MEETING DATE:April 24,2019
RE:Rio Grande Pl.Utility Project –Change Order for Road Base
Improvements and Establishing a New Project Number for Said
Improvements
REQUEST OF COUNCIL:Staff requests approval of a contract change order for the Rio Grande
Utility Work Project and that the change order be assigned to a new project number. This change
order will be to the existing Shaw Construction Guaranteed Maximum Price contract for the
utilities work approved by Council via Resolution 15-2019 on February 11, 2019. The rationale
for the request is due to unforeseen underground conditions in the road base and a desire to repair
the base prior to the summer tourist season.
Change Orders:
1)Sub excavation & Imported Fill –Rio Grande Pl.
Background:During excavation for the deep utilities, site observations by the
Geotechnical Engineer of Record on 4/23/19 identified unforeseen unsuitable soils at
varying depths that could potentially impact the performance and longevity of the new
street surface. The recommended action of the engineer is sub excavation of the poor
soils beneath the new road surface to a depth of approximately 2 ft and import of a Class
6 road base to ensure a suitable base for the new road.
Cost Impacts:The cost impact of the additional excavation and imported fill is
$379,298.53
This change order involves work beyond the scope of the utility replacement project and beyond
the purpose of the utility funds. As such, staff is proposing to track these costs separately under
a new project number. If City Council approves this resolution, it will be requested that City
Council appropriate funds from the Asset Management Plan Fund balance during the second
reading of the spring budget supplemental on May 13, 2019.
RECOMMENDED ACTION:Staff recommends that council approve Shaw Project Change
Order #010 and transfer of the change order to a new project number. The recommendation
reduces community impact by addressing the condition while the site is already under
construction and closed to public access.
2
Page 2 of 2
ALTERNATIVES: The City could forgo this work and only repair the area disturbed by the current
excavation. With this alternative, it is likely the City will experience road base deterioration accelerated as
a faster pace through failing pavement and sidewalks.
Exhibit A –Shaw PCO #010
3
RESOLUTION #53
(Series of 2019)
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ASPEN,
COLORADO, AUTHORIZING A CHANGE ORDER FOR PROJECT 51112 –
425 RIO GRANDE PLACE UTILITY WORK, CREATING A NEW PROJECT
NUMBER AND ASSIGNING THE CHANGE ORDER TO THE NEW PROJECT
NUMBER AND THE CITY MANAGER TO EXECUTE THE CHANGE
ORDER.
WHEREAS, there has been submitted to the City Council Contract Change
Order between the City of Aspen and Shaw Construction GMP for Project 51112 –
425 Rio Grande Place utility work a true and accurate copy of which is attached
hereto as Exhibit “A”;
WHEREAS, City Council wishes to establish a new project with project
number 51120, for Rio Grande Place Road Base improvements and assign the
change order to that new project number.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF
THE CITY OF ASPEN, COLORADO,
That the City Council of the City of Aspen hereby approves that Contract
Change Order between the City of Aspen and Shaw Construction GMP for Project
51112 – 425 Rio Grande Place utility work a copy of which is annexed hereto and
incorporated herein. In addition, the City Council establishes a new project with
project number 51120, for Rio Grande Place Road Base improvements and assigns
the change order to that new project number and does hereby authorize the City
Manager to execute said change order on behalf of the City of Aspen.
INTRODUCED, READ AND ADOPTED by the City Council of the City of
Aspen on the 24th day of April 2019.
Steven Skadron, Mayor
4
I, Linda Manning, duly appointed and acting City Clerk do certify that the
foregoing is a true and accurate copy of that resolution adopted by the City
Council of the City of Aspen, Colorado, at a meeting held April 24, 2019.
Linda Manning, City Clerk
5
Pending Change Order
No. 010
Aspen, CO 81611
425 Rio Grande Place
City of Aspen Civic Space Relocation - City Offices Project No: 10081-02
PCO No. 010 Contaminated Soils in Rio Grande Place Date Sent:
Transmitted To:
Aspen, CO 81611
Description of Proposal:
From:
Brian Thomas, Project ManagerRobert Schober,
Tel: 970-248-2619
Fax:
Email: brianthomas@shawconstruction.net
Aspen, City of
130 Galena Street
Shaw Construction LLC GJ
Cost Summary for Item : 1 Contaminated Soils in Rio Grande Place
QuantityDescriptionPhase Unit Price Amount
324,604.80 324,604.80LS 1Contaminated Soils in Rio Grande Place002300- -010
2 feet over excavation of Rio Grand Place to remove contaminated soils with import backfill per CTO
specs
$324,604.80Net Total for Item 1:
Description Percentage Amount
3,018.82Liability Insurance 0.93%
1,947.63Warranty Reserve 0.60%
2,142.39P&P Bond 0.66%
1,201.04Builders Risk 0.37%
18,143.85Profit 5.45%
$26,453.73Subtotal:
$351,058.53Total Item #1:
Time Extension:NONE
Cost Summary for Item : 2 Add Alternate Provide & Install Geogrid under road
QuantityDescriptionPhase Unit Price Amount
26,112.00 26,112.00LS 1Contaminated Soils in Rio Grande Place002300- -010
Add Alternate, Provide & Install Geogrid under road
$26,112.00Net Total for Item 2:
Description Percentage Amount
242.84Liability Insurance 0.93%
156.67Warranty Reserve 0.60%
172.34P&P Bond 0.66%
96.61Builders Risk 0.37%
1,459.54Profit 5.45%
$2,128.00Subtotal:
$28,240.00Total Item #2:
Time Extension:NONE
Page 1 of 2
Exhibit A - PCO#010
6
Pending Change Order
No. 010
Aspen, CO 81611
425 Rio Grande Place
City of Aspen Civic Space Relocation - City Offices Project No: 10081-02
Grand Total PCO #010:
Total Time Extension:NONE
$379,298.53
Submitted By: Authorized By: Aspen, City of
Signature _________________________ Date ________
Name _________________________________________
Signature __________________________ Date ________
Name __________________________________________
I authorize Shaw Construction to proceed with the work noted above and agree to pay for the work.
Robert Schober, Brian Thomas, Project Manager
Shaw Construction LLC GJ
Page 2 of 2
7
Shaw Construction 4/24/2019 2' Over Excavation in Road
Aspen City Offices- Utility Relocation
425 & 455 Rio Grande Place
Aspen, CO
Bid Breakdown Qty Unit Cost Unit Xtd Cost Comment
2' Over excation below 8" base in road & 2' outside curb Excavate 7 Days
Fill & Compact 8.5 Days
Deliver/Return Smooth Drum 1 ls @ 2,370.00$ each 2,370.00$
Transport 5 hrs @ 150.00$ p/hr 750.00$ Deliver 336
Pilot cars 10 hrs @ 60.00$ p/hr 600.00$ Deliver 336
Transport 4 hrs @ 120.00$ p/hr 480.00$ Deliver D-6
336 56 hrs @ 220.00$ p/hr 12,320.00$ Excavate
GPS 56 hrs @ 125.00$ p/hr 7,000.00$ Excavate
D6 56 hrs @ 180.00$ p/hr 10,080.00$ Excavate
GPS 56 hrs @ 125.00$ p/hr 7,000.00$ Excavate
Lrge Smooth Drum 28 hrs @ 180.00$ p/hr 5,040.00$
Labor 192.5 hrs @ 50.00$ p/hr 9,625.00$
End/Side Dumps 387.5 hrs @ $121.00 p/hr 46,887.50$ Haul off fill
336 34 hrs @ 220.00$ p/hr 7,480.00$ Grade
GPS 34 hrs @ 125.00$ p/hr 4,250.00$ Grade
D6 68 hrs @ 180.00$ p/hr 12,240.00$ Grade
GPS 68 hrs @ 125.00$ p/hr 8,500.00$ Grade
Lrge Smooth Drum 68 hrs @ 180.00$ p/hr 12,240.00$ Grade
End Dump 562.5 hrs @ $121.00 p/hr 68,062.50$ Deliver 3/4" road base
Labor 221 hrs @ 50.00$ p/hr 11,050.00$ 2 Labors
Water Truck 75 hrs @ 110.00$ p/hr 8,250.00$ Moisture condition road base
938 Wheel Loader 75 hrs @ 160.00$ p/hr 12,000.00$ Moisture condition road base
Supervision 31 hrs @ 100.00$ p/hr 3,100.00$
249,325.00$
Other
Traffic control 1 ls @ -$ each -$ Is not included
Dump fees 155 loads @ 44.00$ p/load 6,820.00$
Compaction Testing 8 days @ 275.00$ p/day 2,200.00$ HP GeoTech
9,020.00$
Materials
3/4 Base 4716 tn @ 14.05$ p/tn 66,259.80$
Total 66,259.80$
Total 324,604.80$
Add Alternate
Provide & Install Geogrid under road
336 8 hrs @ 220.00$ p/hr 1,760.00$
938 Wheel Loader 8 hrs @ 160.00$ p/hr 1,280.00$
Labor 57 hrs @ 50.00$ p/hr 2,850.00$ 4 Labors
5,890.00$
Other
Freight 1 ls @ 1,200.00$ p/ls 1,200.00$ Allowance-waiting for price
1,200.00$
Materials
Tensar TriAx TX5 Geogrid 9 roll @ 1,200.00$ each 10,800.00$ Allowance-waiting for price
Mirafi 180 N 12 roll @ 643.50$ each 7,722.00$
Stutsman-Gerbaz Inc.
30376 Highway 82
Snowmass, CO 81654
970 923-2734
8
Misc.1 ls @ 500.00$ p/ls 500.00$
Total 19,022.00$
Total 26,112.00$
Notes Traffic control is not included.
ROCK CLAUSE, FROST CLAUSE & DEWATERING CLAUSE
Add to current Maintainance Bond if required.8,950.00$
9