HomeMy WebLinkAboutresolution.council.008-13 RESOLUTION #e (Series of 2013) A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ASPEN, COLORADO, APPROVING A CONTRACT BETWEEN THE CITY OF ASPEN AND BURLINGAME PHASE II CONTRACT AMENDMENT FOR ADDITION OF VERTICAL CONSTRUCTION OF BUILDINGS 1 — 4, AUTHORIZING THE CITY MANAGER TO EXECUTE SAID CONTRACT ON BEHALF OF THE CITY OF ASPEN, COLORADO. WHEREAS, there has been submitted to the City Council a contract for Burlingame Phase II Contract Amendment for Addition of Vertical Construction of Buildings 1 - 4, between the City of Aspen and Haselden Construction, a true and accurate copy of which is attached hereto as Exhibit "A"; NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF ASPEN, COLORADO, That the City Council of the City of Aspen hereby approves that Contract for Burlingame Phase II Contract Amendment for Addition of Vertical Construction of Buildings 1 - 4, between the City of Aspen and Haselden Construction, a copy of which is annexed hereto and incorporated herein, and does hereby authorize the City Manager to execute said agreement on behalf of the City of Aspen. INTRODUCED, READ AND ADOPTED by the City Council of the City of Aspen on the 14th day of January 2013. • ichael C. Aland, Mayor 1, Kathryn S. Koch, duly appointed and acting City Clerk do certify that the foregoing is a true and accurate copy of that resolution adopted by the City Council of the City of Aspen, Colorado, at a meeting held, January 14, 2013. Kath n S. Koch, City Clerk RIB Rider Leven Bukn � 1675 Larimer Street Suite 470 Denver,Colorado 80202 T:+720 904 1480 January 4, 2013 Mr Chris Everson email: chris.everson @ci.aspen.co.us Affordable Housing Project Manager City of Aspen 130 South Galena St Aspen, CO 81611 BURLINGAME RANCH PHASE II 2013 PHASE 2A VERTICAL—BUILDINGS 1 THROUGH 4— HASELDEN GMP ADDENDUM Dear Chris, The purpose of this letter is to summarize our recommendation regarding the Haselden 2013 Phase 2a GMP. CONTRACT ADDENDUM Rider Levett Bucknall (RLB), Janet Lawler-McDaniel from the legal firm Benjamin, Bain, Howard and Cohen (BBHC) and the City of Aspen have been very active over the past month compiling the A195 GMP Contract Addendum which will form the basis of the 2013 Phase 2a vertical construction work. RLB is privy to many construction contracts and the efforts by BBHC in the earlier phases of the project have provided a sound base contract (which was not altered during recent contract negotiations). We are satisfied that the A195 GMP addendum currently contemplated serves to adequately control the City of Aspen's risk. Four specific components of this addendum were focused upon with Haselden and BBHC: • Understanding the 2% Bidding and Award Allowance • Mitigating and managing any potential risk of escalation (particularly in lumber which saw.a 48% increase over the last 12 months and 29% in the last quarter!) • Having the buildings completed in 2013 to allow sale and occupancy • Agreeing the GMP price and ensuring no cost overlap with the Access/Infrastructure package We note that two critical factors affect the GMP addendum, a/timely Notice to Proceed to the General Contractor by February 01, 2013 and b/ uplift of the Building Permit to enable a start on site on April 01, 2013. A minor item defining the duration from substantial completion to final completion will need to be resolved as the contract schedule is finalized. Page 1 of 2 January 04, 2013 RLB I Rider Levett Buckna« Chris Everson, Affordable Housing Project Manager BURLINGAME RANCH PHASE II 2012 ACCESS INFRASTRUCTURE PACKAGE —CONTRACT ADDENDUM AND HASELDEN GMP 2013 PHASE 2A VERTICAL—BUILDINGS 1 THROUGH 4— HASELDEN GMP ADDENDUM Phasing of the project has created some complexities with scope, particularly for site work and earthwork. In October, considerable work was also done to reduce the initial GMP cost through value engineering, alternates and targeted savings. The GMP submitted is well compiled, reasonable and sufficient to complete the 2013 Phase 2a work. RLB queried some cost items in the GMP at the time of CoA budget submission, and Haselden felt these were still necessary to be retained within the GMP and order to complete/carry out the work. RLB will be active in tracking expenditure against these line items. We are comfortable with the General Conditions inclusions and value ($1,192,000; 7.1%) and other allowances of 12.4% carried in the total. The larger allowances include the civil scope and the bidding allowance and these will be resolved with the subcontractor re-bid Haselden is planning to carry out until January 28tH As such, we recommend the Haselden GMP is accepted for$16,779,287 and the A195 GMP Contract Addendum is executed. CONCLUSION Overall, the Haselden GMP appears to be well compiled, reasonable and sufficient to complete the 2013 Phase 2a work. Allowances included in the GMP are reasonable and appropriate for the project scope. We are satisfied the GMP covers the scope of the 2013 Phase 2a package and we recommend acceptance of the A195 GMP addendum with the Contract Sum of$16,779,287. We trust this is of assistance. Please contact me for any queries relating to this memo. Sincerely, Rob Ta for Associate Principal, BE,PSP Rider Levett Bucknall Ltd Page 2 of 2 O 2 AIA Document A195-2008 Exhibit C Guaranteed Maximum Price Amendment This Exhibit is incorporated into the Agreement dated the 22nd day of March in the year 2009. for the following PROJECT: Burlingame Ranch Phase II Aspen,Colorado ARTICLE A.1 §A.1.1 PHASE II GUARANTEED MAXIMUM PRICE—48 UNIT VERTICAL CONSTRUCTION Pursuant to Section 4.2.2 of the Agreement,the Owner and Contractor hereby amend the Agreement to establish a Guaranteed Maximum Price("GMP")for Phase II—48 Unit Vertical Construction of condominium units for sale to private residential owners,Buildings 1 through 4. As agreed by the Owner and Contractor,the Guaranteed Maximum Price is an amount that the Contract Sum shall not exceed. The Contract Sum consists of the Contractor's Fee plus the Cost of the Work,as that term is defined in Article A.3 of this Amendment. §A.1.1.1 The Contract Sum is guaranteed by the Contractor not to exceed Sixteen Million,Seven Hundred, Seventy- Nine Thousand,Two Hundred and Eighty-Seven Dollars(16,779,287.00),subject to additions and deductions by Change Order as provided in the Contract Documents. This amount includes the deduct of$78,720.00 for overlapping General Conditions between the Civil Infrastructure scope of Work and the Vertical Construction scope of Work. The Contractor shall submit a revised Guaranteed Maximum Price Estimate within 14 days of Contract execution to align with this guaranteed Contract Sum which will become Exhibit 113. The amount by which the sum of the(i)actual Cost of the Work,plus(ii)the Contractor's Fee, is less than the Guaranteed Maximum Price, defined herein as"Savings", shall be shared between the Owner and Contractor. The sharing ratio shall be fifty percent(50%)to the Owner and fifty percent(50%)to the Contractor. The Contractor's portion of the Savings shall be paid at the time of the Final Payment,as provided for in the Agreement. §A.1.1.1.2 Contractor's Fee: The Contractor's Fee for Work performed after the establishment of the GMP will be 3%of the Cost of the Work.No fee shall be added to expenditure of the Contractors Contingency or the Final Bidding&Award Allowance. §A.1.1.1.3 The Contract Sum identified in Section A.1.1.1 above includes within it an amount for General Conditions of One Million,Two Hundred Sixty-Eight Thousand,Four Hundred Twenty-Seven Dollars ($1,192,000.00), which is$1,268,427 reduced by$76,427 for the overlapping of General Conditions between the Civil Infrastructure and Vertical Construction, subject to additions and deductions by Change Order as provided in the Contract Documents. General Conditions will be billed at actual costs. Contractor must not move Work from General Conditions to subcontract trades or self-performed work without a signed Change Order. §A.1.1.2 ITEMIZED STATEMENT OF THE GUARANTEED MAXIMUM PRICE The Contractor shall provide an Exhibit 1B which will be an itemized statement of the Guaranteed Maximum Price which conforms to the GMP amount in the Agreement,organized by trade categories,allowances,contingencies, General Conditions, the Contractor's Fee,and other items that comprise the Guaranteed Maximum Price. §A.1.1.3 The Guaranteed Maximum Price is based on the Implementation Documents identified below. The GMP includes all the Work required to complete the Phase 11 Vertical Construction Work. The Contractor guarantees that the Contract Sum will not exceed the GMP price provided that this GMP Amendment is executed before February 1,2013 and a Notice to Proceed is issued by February 1,2013. The Contractor's GMP includes a Final Bidding&Award Allowance($310,000.00)to cover costs with the final subcontractor awards and subcontract execution in accordance with article A.3.4.of this amendment. This allowance Page 1 of 10 shall also be used to cover added costs,if any,associated with post GMP submission documentation reflecting the Accepted Cost Trend log scopes not otherwise reflected. •OZ Architecture-Burlingame Ranch Phase II-Addendum 02 -November 09,2012 •OZ Architecture-Burlingame Ranch Phase II-Volume 04 drawings-November 09,2012 Contractor shall provide a detailed log of these awards and provide reconciliation of the allowance within 45 days of the Notice to Proceed.All savings from this allowance shall be returned to the Owner. Any shortfalls in this allowance shall not be cause for an increase in the GMP. §A.1.1.3.1 The Contractor's GMP includes a 2%Contractor's Contingency for the Contractor's exclusive use to cover costs defined in this Section A.1.1.3 to cover costs to expedite the schedule for non-excusable delays,and other unanticipated costs which are properly considered reimbursable as a Cost of the Work but do not form the basis for a Change Order as a result of changes in the scope of the Work. §A.1.1.3.2 The Contractor shall report and reconcile the Contractor's Contingency to the Owner on a monthly basis. Contractor's Contingency will be allocated to specific line items in the Estimate through the use of a Change Order signed by the Owner and Contractor, including a description of the items covered by the Contractor's Contingency, and the Contingency amount will be reduced accordingly. §A.1.1.3.3 The Owner shall not unreasonably withhold approval of a Change Order to utilize the Contractor's Contingency so long as(a)the contingency amount does not increase or exceed the GMP, (b)the Contractor utilizes the Contractor's Contingency for items required for the Project that are otherwise recoverable as Costs of the Work under the Contract Documents, or(c)the Contractor's Contingency is used for items outlined in clauses(1)through (3)below: .1 Scope of the Work that is unclear, incomplete or conflicting on the Contract Documents but which is Work consistent with the Contract Documents and reasonably inferable as being necessary to produce the intended results. .2 Additional resources necessary to recover lost time for non-excused delays. If overtime is required to maintain the schedule, the Contractor shall obtain the Owner's prior written approval before moving forward with such overtime. .3 Delays caused by market,labor,material or transportation conditions,labor disputes,weather or other causes which are costs of the Work but do not justify an increase in the GMP. §A.1.1.3.4 The Contractor's Contingency is not available for use by the Contractor for mistakes that result from Self- Performed Work secured through competitive bidding, mistakes of subcontractors or vendors, subcontractor's warranty work,or manufacturer's warranty work. §A.1.1.3.5 The Contractor's Contingency is not available for use by the Owner for allowance overruns, changes in the Scope of Work,differing or changed site conditions,or design errors. §A.1.1.3.6 At Final Completion of the Project, any Contractor's Contingency remaining in the Final GMP will be returned 50%to the Owner and 50%to the Contractor in the shared Savings in Section A.1.1.1. §A.1.1.4 Allowances and Alternates included in the Guaranteed Maximum Price,if any: The Allowances included within the GMP are as follows: 1 Earthwork(includes updated cost on trend log with Bldg. 5) $ 1,259,424 2 Vehicle Control Signage $ 7,500 3 Pavement Markings $ 6,000 4 Transit Benches $ 3,200 5 Grass Seed for Areas Outside Area of Disturbance $ 4,500 6 Independent Soil Testing for Landscaping $ 10,000 7 Irrigation Infrastructure $ 32,520 8 Irrigation Pump Station $ 150,000 9 Pump house#2 on 15.2 $ 100,000 10 Miscellaneous Flashings&Counter flashings $ 20,000 Page 2 of 10 §A.3.1.2 Where any cost is subject to the Owner's prior approval,the Contractor shall obtain this approval prior to incurring the cost.The parties shall endeavor to identify any such costs prior to executing this Agreement. §A.3.1.3 LABOR COSTS §A.3.1.3.1 Wages of Contractor's Own Forces or Own Personnel,which are defined as construction workers directly employed by the Contractor to perform the construction of the Work at the site or,with the Owner's prior approval, at off-site workshops. Overtime for non-exempt employees may be charged at 1.5 times the Burdened Hourly Rates identified in Exhibit 3B. §A.3.1.3.2 Wages or salaries of the Contractor's supervisory and administrative personnel when stationed at the site with the Owner's prior approval,based on actual hours devoted to the Project. Salaried,exempt employees of Contractor will not be paid an overtime premium,and will not charge the Project for more than 40 hours in any week. Wages or salaries of officers of the company,Project Executives,Construction Executives, Senior Project Executives or above will not be reimbursed under any circumstances. Contractor's approved supervisory and administrative personnel for Phase II-Vertical Construction include a Superintendent,a Project Manager,and a Project Engineer at the rates identified in Exhibit 3B. These rates must not include allocation for subsistence,per diems,housing,travel,vehicle allowances,gas,merit pay, incentive pay,profit sharing or bonuses. Person included Status(full-timelpart-time) Rate($0.00) Rate(unit of time) Sen.Project Manager Part Time See Exhibit 3B Hour Project Manager Full Time See Exhibit 3B Hour Gen. Superintendent Full Time See Exhibit 313 Hour Project Superintendent Part Time See Exhibit 313 Hour Project Engineer Full Time See Exhibit 3B Hour Environmental/Safety Engineer(s) Part Time See Exhibit 313 Hour MEP Coordinator Part Time See Exhibit 3B Hour §A.3.1.3.3 Wages and salaries of the Contractor's supervisory or administrative personnel engaged at factories, workshops or on the road,in expediting the production or transportation of materials or equipment required for the Work,but only for that portion of their time required for the Work and devoted to the Project. Salaried,exempt employees of Contractor will not be paid an overtime premium,and will not charge the Project for more than 40 hours in any week. §A.3.1.3.3.4 Contractor's project personnel stationed at the Contractor's principal office or offices other than the site office,will not be charged to this Project without the Owner's prior written approval. With the Owner's prior approval,such personnel will be paid based on actual hours devoted to the Project at the rates listed in the approved Burdened Hourly Rates schedule in Exhibit 3B. With the Owner's prior approval,reasonable travel and temporary living expenses are allowed for such employees. Salaried,exempt employees of Contractor will not be paid an overtime premium,and will not charge the Project for more than 40 hours in any week. Wages or salaries of officers of the company,Project Executives,Construction Executives,Senior Project Executives or above will not be reimbursed under any circumstances. §A.3.1.3.4 Costs paid or incurred by the Contractor for taxes,insurance,contributions,assessments and benefits required by law or collective bargaining agreements and,for personnel not covered by such agreements,customary benefits such as sick leave,medical and health benefits,holidays,vacations and pensions,provided such costs are based on wages and salaries included in the Cost of the Work under Sections A.3.1.3.1 through A.3.1.3.3 are included in the Burdened Hourly Rates identified on Exhibit 313,attached hereto,and will not be paid in addition to the Burdened Hourly Rates. §A.3.1.3.5 Intentionally deleted. §A.3.1.4 SUBCONTRACT COSTS Payments made by the Contractor to any Subcontractors in accordance with the requirements of the subcontracts on the Project will be considered a Cost of the Work and the Contractor will be entitled to no more than a 3%fee on Subcontract costs. Page 4 of 10 §A.3.1.5 COSTS OF MATERIALS AND EQUIPMENT INCORPORATED IN THE COMPLETED CONSTRUCTION §A.3.1.5.1 Costs,including transportation and storage,of materials and equipment incorporated or to be incorporated in the completed construction. §A.3.1.5.2 Costs of materials described in the preceding Section A.3.1.5.1 in excess of those actually installed to allow for reasonable waste and spoilage.Unused excess materials, if any, shall become the Owner's property at the completion of the Work or,at the Owner's option, shall be sold by the Contractor.Any amounts realized from such sales shall be credited to the Owner as a deduction from the Cost of the Work. §A.3.1.6 COSTS OF OTHER MATERIALS AND EQUIPMENT,TEMPORARY FACILITIES AND RELATED ITEMS §A.3.1.6.1 Costs of transportation,storage,installation,maintenance,dismantling and removal of materials,supplies, temporary facilities,machinery,equipment and hand tools not customarily owned by construction workers that are provided by the Contractor at the site and fully consumed in the performance of the Work.Costs of materials, supplies,temporary facilities,machinery,equipment and tools that are not fully consumed shall be based on the cost or value of the item at the time it is first used on the Project site less the value of the item when it is no longer used at the Project site. Costs for items not fully consumed by the Contractor shall mean fair market value. §A.3.1.6.2 Rental charges for temporary facilities,machinery,equipment and hand tools not customarily owned by construction workers that are provided by the Contractor at the site and costs of transportation,installation,minor repairs,dismantling and removal.The total rental cost of any Contractor-owned item may not exceed the purchase price of any comparable item. Rates of Contractor-owned equipment and quantities of equipment shall be subject to the Owner's prior approval. §A.3.1.6.3 Costs of removal of debris from the site of the Work and its proper and legal disposal. §A.3.1.6.4 Costs of document reproductions,facsimile transmissions and long-distance telephone calls,postage and parcel delivery charges,telephone service at the site and reasonable petty cash expenses of the site office. §A.3.1.6.5 Costs of materials and equipment suitably stored off the site at a mutually acceptable and insured location, subject to the Owner's prior approval. §A.3.1.7 MISCELLANEOUS COSTS §A.3.1.7.1 Premiums for that portion of insurance and bonds,at actual cost,required by the GMP Documents that can be directly attributed to this Contract. Estimates of the Guaranteed Maximum Price may be based on percentages,however payment to the Contractor will be based on actual cost. §A.3.1.7.2 Sales,use or similar taxes imposed by a governmental authority that are related to the Work and for which the Contractor is liable and which are not exempt under the City's Tax Exemption. §A.3.1.7.3 Fees and assessments for the building permit and for other permits,licenses and inspections for which the Contractor is required by the GMP Documents to pay. §A.3.1.7.4 Fees of laboratories for tests required by the GMP Documents,except those related to defective or nonconforming Work for which reimbursement is excluded by Section 12.4.3 of AIA Document A295TM-2008 or by other provisions of the GMP Documents,and which do not fall within the scope of Section A.3.1.8.3. §A.3.1.7.5-Royalties and license fees paid for the use of a particular design,process or product required by the GMP Documents;the cost of defending suits or claims for infringement of patent rights arising from such requirement of the GMP Documents;and payments made in accordance with legal judgments against the Contractor resulting from such suits or claims and payments of settlements made with the Owner's consent. However,such costs of legal defenses,judgments and settlements shall not be included in the calculation of the Contractor's Fee or subject to the Guaranteed Maximum Price.If such royalties,fees and costs are excluded by the last sentence of Section 9.17 of A295Tm -2008 or other provisions of the GMP Documents,then they shall not be included in the Cost of the Work. §A.3.1.7.6 Costs for electronic equipment,cell phones,computers and software,office furniture and office equipment directly related to the Work with the Owner's prior approval.The total rental cost of any rental item, excluding the cost of insurance,repairs and maintenance, whether a Contractor-owned item or otherwise,may not exceed the purchase price of any comparable item. Page 5 of 10 Contractor shall provide Owner with an equipment management plan which identifies the following: .1 All equipment to be used on the Project;and .2 Competitive market rental rates for the equipment,including whether the equipment can be rented on an hourly,weekly or monthly basis;and .3 A recommendation regarding whether it is in the Owner's best interest to purchase the equipment outright or to rent the equipment;and .4 Which equipment may be provided by the Contractor,at rates not to exceed the competitive market rates. §A.3.1.7.6.1 Equipment including,but not limited to,electronic equipment,machinery,cell phones,computers and software,office furniture,supplies and office equipment purchased and charged to the Project as a Cost of the Work shall become the property of the Owner.The Owner may require Contractor to turn these items over to the Owner at the end of the Project.Any lease/purchase rental arrangements must be disclosed to the Owner. If the Contractor purchases equipment under a lease/purchase arrangement whereby rental payments are charged to Owner as a Cost of the Work,an appropriate credit shall be given to the Owner for the fair market value of the equipment at the time it was last used on the Project. For Contractor-owned equipment,the Contractor shall maintain daily equipment usage reports. The Owner shall not be charged for equipment which is stored on the job site but not in regular use. The equipment use reports shall be used by the Contractor to determine the most economical billing rate(hourly, weekly,monthly)to the Owner. §A.3.1.7.7 Deposits lost for causes other than the Contractor's negligence or failure to fulfill a specific responsibility in the GMP Documents. §A.3.1.7.8 Legal,mediation and arbitration costs,including attorneys' fees,other than those arising from disputes between the Owner and Contractor,and other than those related to claims filed by subcontractors or material suppliers for non-payment on the Project,reasonably incurred by the Contractor after the execution of this Agreement in the performance of the Work and with the Owner's prior approval,which shall not be unreasonably withheld. §A.3.1.7.9 Subject to the Owner's prior approval,temporary living and subsistence expenses approved by Owner incurred for the Contractor's personnel identified in A.3.1.3.2 above and required for the Work on this Project. Meals will not considered temporary living expenses and will not be reimbursed.The Owner reserves the right to approve accommodations for Contractor's personnel in advance,and to find them alternate accommodations in the event that the Owner does not approve of their proposed accommodations. §A.3.1.7.10 That portion of the reasonable expenses of the Contractor's supervisory or administrative personnel identified in A.3.1.3.2 above,incurred while traveling in discharge of duties connected with the performance of the Work on this Project,at the rates on Exhibit 1 B which have been approved by the Owner in writing.Travel expenses of officers of the company,Project Executives,Construction Executives, Senior Project Executives or above will not be reimbursed under any circumstances. §A.3.1.7.11 General Conditions will be paid monthly, on the basis of actual costs incurred,but only when supported by evidence satisfactory to the Owner. §A.3.1.8 OTHER COSTS AND EMERGENCIES §A.3.1.8.1 Other costs incurred in the performance of the Work if,and to the extent,approved in advance in writing by the Owner. §A.3.1.8.2 Costs incurred in taking action to prevent threatened damage,injury or loss in case of an emergency affecting the safety of persons and property,as provided in Section 9.24.4 of A295-2008. §A.3.1.8.3 Costs of repairing or correcting damaged Work executed by the Contractor,Subcontractors or suppliers, provided that such damaged Work was not caused by negligence,failure to conform to the Contract Documents,or failure to fulfill a specific responsibility of the Contractor and only to the extent that the cost of repair or correction is not recovered by the Contractor from insurance,sureties,Subcontractors, suppliers,or others. §A.3.1.9 RELATED PARTY TRANSACTIONS §A.3.1.9.1 For purposes of this Section A.3.1.9,the term"related party"shall mean a parent, subsidiary,affiliate or other entity having common ownership or management with the Contractor; any entity in which any stockholder in, Page 6 of 10 or management employee of,the Contractor owns any interest in excess of ten percent in the aggregate;or any person or entity which has the right to control the business or affairs of the Contractor. The term"related party" includes any member of the immediate family of any person identified above. §A.3.1.9.2 If any of the costs to be reimbursed arise from a transaction between the Contractor and a related party, the Contractor shall notify the Owner of the specific nature of the contemplated transaction,including the identity of the related party and the anticipated cost to be incurred,before any such transaction is consummated or cost incurred. If the Owner,after such notification,authorizes the proposed transaction,then the cost incurred shall be included as a cost to be reimbursed,and the Contractor shall procure the Work,equipment,goods or service from the related party,as a Subcontractor,according to the terms of Section A.3.4.If the Owner fails to authorize the transaction,the Contractor shall procure the Work,equipment,goods or service from some person or entity other than a related party according to the terms of Section A.3.4. §A.3.1.9.3 Self-Performed Work:The Contractor will be allowed to bid on self-performed Work on the Project under the following conditions: 1. The Contractor may provide a bid on any portion of the Work(the"Self Performed Work")that the Contractor requests to perform,subject to the terms and conditions set forth in this Section A.3.1.9.3. Contractor must disclose to the Owner the subcontractor bid tabulation results for all subcontracted Work, including Self Performed Work.Contractor shall prequalify all subcontractors for all subcontracted work including the Self Performed Work,and must disclose the prequalification results to the Owner.The prequalification process for subcontractors involves the Contractor's evaluation and determination that the subcontractors have the experience,financial strength,safety record and staffing sufficient to perform the work within the scheduled time. The prequalification process for Self Performed Work involves the Owner's evaluation and determination that the Contractor has the appropriate experience,qualifications and competence for the Bid Package. Contractor shall list in the bid tabulation results any firm it proposes to use as a sub-subcontractor. Contractor may not utilize any firm as a sub-subcontractor if such firm could have successfully prequalified to bid the Self Performed Work. If the Owner approves the award of Self Performed Work to the Contractor,then such Work shall be performed for the Contractor's bid amount on the basis of a Stipulated Lump Sum,and shall not be subject to further audit or adjustment. Owner agrees that Contractor's own forces, for Self Performed Work which complies with this Section A.3.1.9.3, shall be deemed to include Contractor's own employees,material suppliers and sub-subcontractors involved in the Self Performed Work. 2. At least 30 days prior to soliciting bids from the subcontracting community,the Contractor shall submit its proposed Bid Packages to the Owner for review and approval including a detailed,line item list of the scope of work proposed by the Contractor to be included in each Bid Package,accompanied by a list of subcontractors from whom the Contractor intends to request bids. If Contractor intends to request approval from the Owner to submit a bid for Self Performed Work,then the Contractor must be listed on the proposed list of bidders. The Owner will review the Bid Packages and Bid Lists proposed by the Contractor within 14 days and notify the Contractor of any revisions required to be made to the Bid Packages or any proposed bidders to whom the Owner has an objection. The Contractor shall revise the Bid Packages and Bid Lists accordingly. 3. The Contractor must obtain the Owner's written consent in advance of submitting a bid to self-perform any Work on the Project. The Owner may request information and references from the Contractor to determine Contractor's experience,qualifications and competence to perform the scope of work. Bid tab review and award for trade packages involving Self Performed Work will be subject to Owner review and approval of award in conjunction with the Contractor. 4. The Contractor must not move Work included in the General Conditions to subcontractor Bid Packages or Self Performed Work. 5. If approved in advance to submit a competitive bid,the Contractor must obtain a minimum of three other competitive bids for the same scope of work. If there are less than four competitive bids received on the scope of work(Contractor plus 3 others),then the Owner will not approve the Contractor's self-performed bid and the Contractor must proceed to perform the Work under the Contract in accordance with A.3.1.9.3.7 below. Page 7 of 10 6. Contractor shall submit its competitive sealed bid to the Owner at least 24 hours in advance of the published bid opening date. 7. For all work performed by the Contractor on a non-competitive basis,defined as less than four competitive bids received on the scope of work,then the Contractor will be compensated on the basis of the Cost of the Work plus a 3%fee in its role as the General Contractor using the same overhead,general conditions and supervisory and administrative staff identified in the General Conditions for the Project as a whole,unless agreed mutually by the Owner and Contractor. 8. For Self performed Work,when items 1 through 7 above have been satisfied,the Contractor may utilize any fee deemed appropriate to form part of Contractor's competitively submitted bid for such Self Performed Work(the"Self-Perform Fee"). The Self Performed Work Fee is separate and distinct from the Contractor's Fee defined in Subparagraph A1.1.1.2. Contractor shall furnish the Owner with sufficient information regarding the scope and all inclusions/exclusions in the bid so Owner can confirm the scope is consistent with the Bid Packages approved in item 2 above,and to the other submitted bids. 9. Contractor's fee will be no more than 3%of the Cost of the Work,including but not limited to Self Performed Work,work performed by the Contractor's own forces,employees or personnel,materials purchased or equipment rented in the role as General Contractor,General Conditions,and all Work performed by Subcontractors. §A.3.2 COSTS NOT INCLUDED IN THE COST OF THE WORK §A.3.2.1 The Cost of the Work shall not include the items listed below: .1 Salaries and other compensation of the Contractor's personnel stationed at the Contractor's principal office or offices other than the site office,of officers of the company,Project Executives, Construction Executives,Senior Project Executives or above,except as specifically provided in Section A.3.1.3. or as may otherwise be provided; .2 Expenses of the Contractor's principal office and offices other than the site office; .3 Entertainment,business development meals,meals delivered to the job site,or similar expenses; .3 Overhead and general expenses,except as may be expressly included in Section A.3.1; .4 The Contractor's capital expenses,including interest on the Contractor's capital employed for the Work; .5 Except as provided in Section A.3.1.8.3 of this Agreement,costs to correct defective,non-conforming work,or work damaged due to the negligence or failure of the Contractor for self-performed work awarded on a competitive basis, Subcontractors and suppliers or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable to fulfill a specific responsibility of the Contract; .6 Any cost not specifically and expressly described in Section A.3.1; .7 Costs,other than costs included in Change Orders approved by the Owner,that would cause the Guaranteed Maximum Price to be exceeded; .8 Bonuses,profit sharing,incentive compensation and any other discretionary payments paid to anyone hired by the Contractor or paid to any Subcontractor or vendor,without the Owner's prior approval; and .9 Travel expenses of any kind,including aviation related expenses,of officers of the company,Project Executives,Construction Executives, Senior Project Executives or above. §A.3.3 DISCOUNTS,REBATES AND REFUNDS §A.3.3.1 Cash discounts obtained on payments made by the Contractor shall accrue to the Owner if(1)before making the payment,the Contractor included them in an Application for Payment and received payment from the Owner,or(2)the Owner has deposited funds with the Contractor with which to make payments;otherwise,cash discounts shall accrue to the Contractor.Trade discounts,rebates,refunds and amounts received from sales of surplus materials and equipment shall accrue to the Owner,and the Contractor shall make provisions so that they can be obtained. §A.3.3.2 Amounts that accrue to the Owner in accordance with the provisions of Section A.3.3.1 shall be credited to the Owner as a deduction from the Cost of the Work. Page 8 of 10 §A.3.4 SUBCONTRACTS AND OTHER AGREEMENTS §A.3.4.1 Those portions of the Work that the Contractor does not customarily perform with the Contractor's own forces,defined as the Contractor's own personnel or employees, shall be performed under subcontracts or purchase agreements with the Contractor.There will be no distinction made for different subcontract or supplier tiers other than for Self Performed Work defined in Section A.3.1.9.3.The Owner may designate specific persons from whom, or entities from which,the Contractor shall obtain bids.The Contractor shall obtain bids from Subcontractors and from suppliers of materials or equipment fabricated especially for the Work and shall deliver such bids to the other Project Participants.The Project Participants shall then determine which bids will be accepted.The Contractor shall not be required to contract with anyone to whom the Contractor has reasonable objection. §A.3.4.2 When a specific bidder(1)is recommended to the Owner by the Contractor;(2)is qualified to perform that portion of the Work;and(3)has submitted a bid that conforms to the requirements of the GMP Documents without reservations or exceptions,but the Owner requires that another bid be accepted,after the GMP has been established, then the Contractor may require that a Change Order be issued to adjust the Guaranteed Maximum Price by the difference between the bid of the person or entity recommended to the Owner by the Contractor and the amount of the subcontract or other agreement actually signed with the person or entity designated by the Owner. §A.3.4.3 Subcontracts,purchase orders or other agreements shall conform to the applicable payment provisions of this Agreement,and shall not be awarded on the basis of cost plus a fee without a guaranteed maximum price or lump sum price.If a Subcontract or purchase order is awarded on the basis of the cost-plus a fee with a guaranteed maximum price,the Contractor shall provide in the Subcontract or purchase order for the Owner to receive the same audit rights with regard to the Subcontractor or supplier as the Owner receives with regard to the Contractor in Section A.3.5,below. §A.3.5 ACCOUNTING RECORDS The Contractor shall keep full and detailed records and accounts related to the cost of the Work and exercise such controls as may be necessary for proper financial management under this Contract and to substantiate all costs incurred.The accounting and control systems shall be satisfactory to the Owner. The Owner and the Owner's auditors shall,during regular business hours and on at least a monthly basis,upon reasonable notice,be afforded access to,and shall be permitted to audit and copy,the Contractor's records and accounts, including complete documentation supporting accounting entries,books,correspondence,instructions,drawings,receipts,subcontracts, Subcontractor's proposals,purchase orders, vouchers,memoranda and other data relating to this Contract.The Contractor shall preserve these records for a period of three years after final payment,or for such longer period as may be required by law. ARTICLE 4 MISCELLANOUS PROVISIONS §A.4.1 The Owner's program for the Project described in Section 1.2.1 of the AIA A295-2008 has been revised,as follows: Burlingame Ranch Phase II will be constructed in multiple Phases over a period of several years. Construction of Civil Infrastructure began in 2012 and will be completed in 2013. Construction commencement of Buildings 1,2,3 and 4 is anticipated in 2013. Construction commencement of Building 5,6 and 7 is anticipated in 2014,subject to Aspen City Council approval. Award by the Owner to the Contractor of any particular Phase will not be construed to be a guarantee of award of subsequent Phases. Owner reserves the right to terminate the Agreement for the Owner's convenience,as well as the right to competitively bid subsequent Phases. The Preconstruction Services and Implementation Documents Phase Services as defined in the Agreement have been fully completed.The terms for performance for any additional preconstruction services in the future shall be mutually agreed upon between Owner and Contractor. §A.4.2 Sections 7.1.5.1 and 7.2.4.1.1 in the A195-2008 Agreement are deleted and replaced with the following provision: §7.2.4.1.1 Notwithstanding the above,in the event the City Council for the City of Aspen does not approve the Guaranteed Maximum Price for Phase II,Vertical Construction,or any subsequent Phase of the Work,this Agreement will be terminated for the Owner's convenience and no subsequent Suspension or Termination Expenses or fees will be due or will accrue from the Owner to the Contractor after such termination. Approval of the Guaranteed Maximum Price for Phase II,or any subsequent Phase,by City Council creates no obligation on the part of the Owner to approve subsequent Amendments to the Agreement for subsequent Phases of the Work. Page 9 of 10 §A.4.3 Interest on amounts ultimately determined to be due to a contractor or the City shall be payable at the statutory rate applicable to judgments from the date the claim arose through the date of decision or judgment, whichever is later.Aspen Municipal Code Sec.4.16.070.Interest. §AAA Sections 11.1.10 and 11.3.1.3 of the AIA A295-2008 are deleted and replaced with the following. §11.1.10 Deductible: The Contractor shall pay any amounts not covered because of a deductible under the OCIP general liability policy up to$10,000 per claim. §113.1.3 If the property insurance requires deductibles,the Contractor shall pay costs not covered because of such deductibles up to$10,000 per claim. §A.4.5 Section 9.22.2.8.7 of the AIA A295-2008,the Schedule of Liquidated Damages applies to each date of Substantial Completion in Section A.2.1 for each building,separately,but shall not exceed$2,000 per day. §A.4.6 Section 10.1.2 of the AIA A295-2008 is amended to add the following sentence to the end of the Section: "In order for the Owner to occupy and utilize the Work for its intended purpose,consisting of the sale of condominium units to private individuals,the building must have official approval for occupancy from each Authority having jurisdiction,and the interior punch lists on the individual units must be completed to an extent to allow a condominium owner to move-in and occupy any unit in a particular building." §A.4.7 Section 9.23.3.4 of the AIA A295-2008 is amended to add the following sentence to the end of the Section: "The Contractor shall submit the updated Construction Schedule each month in electronic.pdf format,and shall also submit the corresponding base or raw schedule file in Primavera P6 format" §A.4.8 Section 9.23.3.4 of the AIA A295-2008 is replaced with the following Section: "Retainage of five percent(5%)will be withheld from the completed Construction Phase of the Work.This retainage will accumulate throughout 100%of the Construction Phase(s). §A.4.9 Section 11.4 of the AIA A295-2008 is revised as follows: Section 11.4,Performance and Payment Bonds, is revised to remove the language requiring a Performance and Payment Bond on the amount of preconstruction services. §A.4.10 Section 9.21.3.5 of the AIA A295-2008,add the following sentence to the end: The Contractor shall submit a Change Order Request to the Architect and the Owner which includes the proposed adjustment in the Contract Sum and Contract Time as a result of the Construction Change Directive within 21 days of receipt of the Construction Change Directive. This Agreement entered into as of January 2013. CITY OF ASPEN HASELDE CO CTIO PLC By: OWNER(Signature) TOR gnature) Michael C.Ireland,Mayor Byron Haselden,President /am Page 10 of 10 Exhibit 1B 100% Implementation Documents Guaranteed Maximum Price 48 Unit — Revision 8 January 3. 2013 tot BURLINGAME< $e e ti e x RANCH Page 1 �������� |��N� 0V^����������� CONSTRUCTION January J, 20|3 Chris Everson Affordable Housing Project Manager City ofAspen |30 South Galena Street Aspen. C{} 8\G| | Rc�ur�in�� B�udin�umoc Ranch Phase ||-4QUnit Guaranteed Maximum Price—revision 5 Dear Chris, We are p|uasod to submit for your review our Revised Guaranteed Maximum Price, for the vertical construction o[8udiuoumneRanch Phase lL1n provide all necessary |abur, materials. and equipment to construct the project. This proposal also includes all of the cost trends the team has been working on the several months. Our Proposal is as b`}|*`vs: Site(remaining n/wrk)— ...... [arpod»— .... ----- .........----------- ........ -------------- ...$809`0U| 8uiidingo--------------------....... -----------------S10`489,j78 Trend Log Summary........ -------------....... ----------..-----.(S'8|9`|5O) General Cmndhiono---- ..... ----------------------------- �|_3078�] Construction Contingency—..... S3 0 8 3 1 Bidding and Award &Uowance ------------ ...... |0,O00 Insurance, fecs 0ond-------------------- ....... ------ ....... ---S734.I|5 1[O1[A8. ESTIMATED CONSTRUCTION COSI. ..................................................S16,779 7 /�mcuxuchcJsummu��hcuhx*ddibkmo| inhvmukv ) ()ur [;MP is based on 14j month duration with construction starting April \. IO|]' see attached mUesiooeschcdo\c� lhia(3K-1P is based ou Hascideu Construction being, issued u notice ou proceed bYFebruary }, 20 1 S, i[ the NTP is not issued by this date wcv/i|| need to reevaluate the Gh1P for -cost ondschcdu|e impacts, DESIGN DOCUMENTS Our Proposal is based on Jocunncni^ prepared b\ Oz Architecture as [o||oss: Page lanuar x. 1-01 Pac-- '~of 2 • BurlinLannc Ranch Phase; 11 ._lt W-0 Implementation Documents Project -Manual. dated ugu:�t )I, 20i-) • BurlinLa e Ranch Phase II - 100% Implementation Documents For Construction Drawings, dated August 3 1. 20 1 • Burlinayame Ranch Phase 11 --- Pry:-Bid Addendum #101.. dated September 20. '012 We believe that this proposal properly reflects the entire cast and scope of the project. If you have any questions regarding the data submitted or should require additional information, please do not hesitate to contact us. Sincerely, F-IASELDEN CONSTRUCTION. L,L,C Christian Ekstrom Preconstruction `vianatLer cc: IPD Team —COA. RLB. OZ Page 3 HASELDEN BURLINGAME RANCH AFFORDABLE HOUSING PHASE 11 48 Unit Vertical Construction January 3,2013 Precc,i Team- Cnfi5fvar Ekstrom Revision 6 48 UNIT GMP COST DESCRIPTION TOTALS BUILDING NUMBER I 52,776.637 BUILDING NUMBER 2 $3.132.145 BUILDING NUMBER 3 $1,784,329 BUILDING NUMBER 4 $2,796,467 COVERED PARKING STRUCTURES $809,001 COVERED WALKWAYS AT BUILDING CONNECTORS w/Building Est SITE DEVELOPMENT 51464,280 MEDIUM VOLTAGE LINE-ALLOWANCE $175.000 6 R.O.HOMES Excluded DIRECT COST TOTAL $14,937,859 COST TRENDS: Cost trends carried forward from sheet 2 ($819,150) TOTAL COST TRENDS ($819,150) GENERAL CONDITIONS S 1,384,260 GENERAL CONDITIONS-Al SCOPE OVERLAP CREDIT S (76,427) DIRECT COST W/GC SUBTOTAL Is 15,426,642 INDIRECT COSTS: DESIGN&PROFESSIONAL SERVICES BY OWNER MATERIALS&SOILS TESTING BY OWNER TRAFFIC STUDY BY OWNER PERMITS&FEES BY OWNER LEED DOCUMENTATION NOT INCLUDED DEVELOPMENT FEES BY OWNER SALES TAXES AS APPLICABLE INDIRECT COST TOTAL is DIRECT&INDIRECT COST TOTAL Is 15,426,6421 CONSTRUCTION FEES: CMIGC PRE-CONSTRUCTION FEE IN OWNER BUDGET CM/GC CONSTRUCTION FEE S 15,426,542 3,00% S 462,736 CONSTRUCTION FEES COST TOTAL I $ 462,7961 CONTINGENCIES&ALLOWANCES: CONSTRUCTION CONTINGENCY S 15,426 542 200% S 308,531 PERMIT REVIEW COMMENT CONTINGENCY BY OWNER BIDDING AND AWARD ALLOWANCE $ 310,000 CONTINGENCY COST TOTAL $ 61$,631 COST OF CONSTRUCTION SUBTOTAL INSURANCE&BOND COSTS: QUALITY CONTROL-3RD PART Y ILA JOLLA PACIFICj S 53,865 GENERAL LIABILITY INSURANCE OR PROJECT INS• RAN""'E. OCIP BY OWNER DIFFERENCE IN COVERAGE INSURANCE 0,448% S 74,270 BUILDER'S RISK OCIP BY OWNER PERFORMANCE&PAYMENT BO,ND 0,861"Y"i S 143,283 INSURANCE&BOND COST TOTAL $ 2711,4118 148 UNIT GMP TOTAL COST $ 16,779,287 Note-All"re3I(OUt Vak!e'S afe 3pPrOXiMate if sc-ee is femoved re-verification of the costs,will be required Page 4 Exhibit 2B Burlingame Ranch Phase 11—48 Unit GMP r Clarifications/Assumptions & January 3,2013 RS HASELDEN CONSTRUCTION General items inclusions 1) The Guaranteed Maximum Price is based on 100%implementation Documents For Construction issued by Oz Architecture dated August 31,2012 and Addendum 1 dated September 20,2012, 2) This GMP proposal expires on February 1,2013. 3) GMP is based on construction of buildings 1-4 with associated site work/carports only. Buildings 5 thru 7 will be priced at a later date,the price included within the alternates section is for budget purposes only. 4) The GMP is based on receiving a written notice to proceed/letter of authorization by February 1,2013. S) The GMP is based on a construction start of April 1,2013. 6) On the award recommendation if the selected subcontractor column states"scope completion subcontractor"this means that the work can be awarded to another subcontractor to complete this scope or Haselden will complete this scope on a time and material basis at our fixed wage rates. 7) Per the Addendum,2 units are included as Type A(ADA)at building 2. The breakout is as follows:(1)1 BR Type A Unit, (1)2 BR Type A Unit. Exclusions 1) Importing of fill,assumed that a mining process will be established onsite to use the existing soils. 2) Building permits,grading permits,construction mitigation permits and plan check fees are by Owner. 3) We have not included any costs for permit review comments that may affect the GMP.This will be issued as a Construction Change Directive to the Contract. 4) Fees associated with permit transfers are by Owner. S) Utility tap fees are by owner 6) Temporary construction power consumption cost is by the Owner. 7) Service expansion fees are by owner 8) All City of Aspen taxes on material permanently installed into the project are excluded. 9) Telecom Communications,Electrical,Cable,Gas service fees are by Owner. 10) Road cut/closure permits and fees are by Owner 11) Platting and recording fees are by Owner 12) Registered survey is by Owner 13) Architectural and consultant fee are by Owner 14) Cost of testing and inspections services are by Owner 15) Offsite improvements not indicated on the plans are not included 16) Geotechnical and material testing are by Owner. 17) We have not included any costs for on-site security services during off-hours. 18) Procurement of all easements is the responsibility of the owner. 19) We have not included any costs to maintain the site after substantial completion. 20) We have not included any costs to maintain the site over the 2012/2013 winter season. 21) We have not included any costs for LEED documentation. 22) Costs associated for the relocation of the overhead power lines. Pagel Burlingame Ranch Phase it—48 Unit GMP Clarifications/Assumptions January 3,2013 R5 NA$ELDEN CONSTRUCTION 02B Earthwork Inclusions 1) We have included an allowance for the Earthwork scope of work.Once the At work is completed,the existing conditions are surveyed and coordinated with the construction documents,and the OAC team has discussed and come to agreement on the scope of work and pricing,the allowance will be reconciled. • The earthwork allowance is based on the provided drawings and AutoCAD files, not actual site conditions. • The earthwork allowance assumes that no excess structural fill will be available from the At package.This assumption is based on information provided by Gould Construction.Due to this information,buildings 1-7 require a substantial import. 2) We have included costs to process all fill on-site. 3) We have included costs to crush rock on-site for fills below building slabs that require over- excavation and will do so in order to meet the noise requirements as set by the City of Aspen. 4) We have included all boulder retaining walls as utilizing on-site rock. No additional costs have been included to import and place new rock. We believe that we should have a sufficient amount of boulders on-site for this scope but if for some reason there is a shortage of quantity we will borrow from the existing stockpiled boulders left from Phase I. 5) We have included trenching,backfilling,and conduit only for Aspen Electric service. Wiring by others. 6) We have included trenching and backfilling of the gas service. installation of line is by others. 7) We have included trenching,backfilling,and conduit for the joint phone/cable line. Wiring by others. Exclusions 1) We have not included any temporary shoring. 2) We have not included any costs for re-spreading topsoil at the 12" depth as specified in the Western Ecological Report,we have included re-spreading at a 6"depth. 02G Site Concrete Exclusions 1) We have not included any colored or stamped concrete. 02J Site Furnishing Inclusions 1) We included an allowance for two transit benches.A question was asked,but the answer did not provide us with specific enough information to procure. 2) We have included 4 mailboxes with 16 cluster boxes by Salsbury Industries.This should provide enough mailbox units for 64 tenants.While there are not additional mailboxes shown for buildings 6&7,we believe that two more units are required to provide enough mailboxes for 82 tenants. Because of this,the alternate for buildings 6&7 includes two additional mailboxes to ensure all 82 units have mailbox space. Page 2 Burlingame Ranch Phase II—48 Unit GMP Clarifications/Assumptions January 3,2013 R5 NASELDEN CONSTRUCTION Exclusions 1) We have not included installation of bike racks per the plan note for snow removal purposes. 2) Precast window wells. 02L Landscaping/irrigation Inclusions 1) It is our understanding that the completion or additional scope in the"Park Areas"will be paid for from a different fund. Temp seeding of these areas has been included for erosion control purposes. 2) We have included grading only for the community gardens. It is our understanding that the gardens will be by others. Exclusions 1) We have not included any costs for importing topsoil. We have assumed all topsoil on-site will be screened and properly amended for use. 03B Gypsum Concrete Inclusions 1) We have included gypsum concrete at 1.5"thick.The 0.75-1.("thickness listed in the specifications does not meet the minimum required by the manufacturers. Exclusions 1) We have not included any costs gypsum crack filler,acoustical sealant or 6mil plastic sheeting vapor barrier.These products are not part of this system,but listed in the specification. 05B Miscellaneous Metals Inclusions 1) Detail 2/A6.11 calls for the mesh to be"powder coated". No color is specified. We have included black powder coating on all mesh. Exclusions 1) Proposal excludes"U"Shape Perimeter steel frame between posts at Mesh as described in the description of mesh in detail 2/A6.11. The detail shows the mesh being sandwiched between 2x4 cedar pieces,not a"U"channel,so that is how we have included it. 2) Bollards are not included based on response#23 in Addendum#1. 3) Proposal excludes Building S,as there are no handrails or balcony assemblies at this building. 06A Rough Carpentry Exclusions 1) We have not included FSC certified dimensional lumber. Page 3 Burlingame Ranch Phase If—48 Unit GMP Clarifications/Assumptions J January 3,2013 RS NASELDEN CONSTRUCTION 06B Architectural Woodwork Inclusions 1) Casework is by custom manufacturer equal to all specification requirements. Exclusions 1) Specification section 06200-7 calls for exterior benches. The exterior site benches are included with the site furnishings package. No benches are included using plastic lumber. 07E Roofing&Sheet Metal Inclusions 1) We have included an allowance for snow fencing and snow clips. 2) We have included corrugated metal roofing.The specifications call for standing seam metal, but the plans and details show corrugated metal. Exclusions 1) We have not included any gutters or downspouts. 2) We have not included any heat tape or Bylin as none are shown. 3) We have not included any standing seam roofing. 4) Asphalt roofing at meter banks.This is shown in select details/notes,but Addendum#1 said that these areas were fenced. 071 Joint Sealants Exclusions 1) We have not included joint sealants per detail G/C5.01. 08B Door/Frame/Hardware Supply Inclusions 1) The interior Masonite pre-hung doors as specified will not meet the urea-formaldehyde free requirements. Exclusions 1) We have not included any glass sliding doors. 2) We have not included any screen doors at unit entries that have fiberglass insulated doors. 08i Shower Enclosures&Mirrors Inclusions 1) Specification section 10186,for Glass Shower Doors,doesn't list any specific products. Therefore,we have included an allowance of$800 per door. 096 Gypsum Board Systems Inclusions 1) We have included the following gypsum board assemblies: - 0 1 layer of standard gypsum board at each side of interior partitions and at the interior side of exterior walls. o 1 layer of gypsum board at demising walls(2nd layer of sheathing with 06A). o We have included 2 layers of gypsum board on RC channel at all lower level ceilings. o We have included 1 layer of drywall on all top level ceilings with no RC channel. Page 4 Burlingame Ranch Phase II—48 Unit GMP Clarifications/Assumptions January 3,2013 R5 NASELDEN CONSTRUCTION o Gypsum board, metal studs and metal roof framing at carport trash rooms per the drawings. 09G Flooring Systems Inclusions 1) A.375"thick,Class 1 carpet pad is included at all carpet locations. 2) We have included an Anti-Fracture membrane at all on-grade floor tile locations and a fluid applied membrane at above grade floor the locations. 3) Specification section 09300 calls for the wall the to be installed per TCA Method W244. This requires a water resistive barrier to be installed underneath the tile. Therefore,we have included a Laticrete Hydro Barrier membrane that will be installed directly beneath the tile. Exclusions 1) Tile base,as indicated in specification section 09300 is excluded. All base is indicated to be M DF. 2) Proposal excludes all moisture mitigation at the slabs prior to flooring placement,as none is indicated in the specifications. 3) Proposal excludes Chloroloy Waterproof Shower Liner. This is not needed based on the response in Addendum#1 which stated that all shower pans are preformed units. 091 Painting Systems Exclusions 1) We have not included any paint at misc metal that receives powder coating,including site railings. JOB Toilet Compartments&Accessories Inclusions 1) Larsen's 2.5LB Multi-Purpose Fire Extinguisher on Bracket is included at each unit,to be installed under the sink. Exclusions 1) We have not included any shower curtains. 2) We have not included any architectural louvers—specification section 10202,none shown. 3) All fire extinguisher cabinets&10 lb extinguishers that fit inside them are excluded based on response to Question#18 in Addendum#1. 10F Identifying Devices Inclusions 1) We have included 2 (ea)identification signs per building. 2) We have included 1 (ea)identification sign per unit. 3) We have included 1 (ea)sign at each water entry room. 4) We have included 1 (ea)sign at each carport storage room. 5) We have included 2 (ea)signs per covered stair. Page 5 Burlingame Ranch Phase 11—48 Unit GMP Clarifications/Assumptions January 3,2013 R5 HASELDEN CONSTRUCTION 11E Appliances Inclusions 1) We have included ADA accessible appliances at two(2)ADA units in Building 2 as indicated in Addendum 1. 2) Sheet A7.01 lists that the Microwave Range Hood is at ADA units. It also lists the Under Cabinet Hood and Countertop Microwave at ADA Units. We have included Microwave Range Hoods at Non-ADA units only. 3) Many of the appliance models listed on sheet A7.01 are no longer available,therefore, comparable products have been included. Exclusions 1) We have not included the following appliances: o Recycling Center 12B Window Treatments Exclusions 1) We have not included any window treatments. 15A Mechanical Systems Exclusions 1) Gas service by others,our cost includes taking the gas from the meter into the building 2) Sump pumps 4/P002, none shown on the documents. 3) Elkay fixtures,line is not available. 15B Fire Protection Exclusions 1) The following items are not included within the budget o Standpipe systems o Fire pumps and controls,we are assuming that the current water pressures are sufficient. o Fire protection at closets less than 24 sf o Fire protection at bathrooms less than 55 sf o Exterior decks,carports, attics, interstitial spaces or exterior stairways. o Anit-freeze or dry pipe system,assumed dry heads only off of the wet.This may cause some additional soffits. o Nicet level stamp on plans,engineering stamp excluded. 16A Electrical Inclusions 1) Romex has been included for all wiring within the buildings 2) Medium voltage is included as an Allowance until a bid can be secured. Exclusions 1) lightning protection and surge protectors are not included. 2) Incoming television and telephone service cable from pedestals to units are by Others. 3) Television and telephone pedestals are by Others. 4) Radio amplification is not included. Page 6 Burlingame Ranch Phase II—48 Unit OMP Clarifications/Assumptions January 3,2013 Rs HASELDEN -- - - - CONSTRUCTION S) Cell amplification is not included. 6) Electrical meters by Others. 7) Pre-wiring for security is not included. 8) Temporary construction power consumption cost is by the Owner. Page 7 Exhibit 3B 40 �������� Equipment Rates # A CONSTRUCTION January Ranch Phase ti January 3,2013 Detail upon request from City Attorney Page 1