WORK SESSION MEMORANDUM
TO:Mayor and City Council
FROM:Jack Danneberg, Project Manager
THRU:Pete Rice, P.E., Senior Project Manager
Trish Aragon, P.E., City Engineer
DATE OF MEMO:November 4th, 2019
MEETING DATE:November 11th, 2019
RE:Castle and Maroon Creek Road Traffic Improvements
SUMMARY: Staff seeks input on the Castle and Maroon Creek Road Traffic Improvement project
that is scheduled for consent at a future Council meeting. The goals for this work session include the
following:
Background on this project
Purpose of the project and scope
Describe pieces of the project that are not included in the scope
Gain Council input
The primary goal of the project is to obtain traffic data including movements and generation rates to
assess the existing conditions that lead to congestion on Maroon Creek and Castle Creek roads. The
secondary goal of this project is to identify ways to improve traffic flow during peak periods on Castle
and Maroon Creek roads due to the interaction at the Highway 82 roundabout near Aspen (Aspen
Roundabout) with non-infrastructure modifications.
BACKGROUND:The City receives a significant amount of complaints for the congestion on
Maroon and Castle Creek Roads throughout several city departments. During peak traffic periods,
vehicle backups consistently occur at the 20-year-old roundabout during peak periods on State
Highway 82 (Aspen Roundabout) that intersects Maroon Creek and Castle Creek Roads. This vehicle
congestion from Highway 82 in the roundabout negatively impacts the function of the roundabout and
vehicles using Castle and Maroon Creek Roads. This congestion continually frustrates tourists, skiers
and citizens.
DISCUSSION:Concrete resurfacing for the roundabout is planned for the year 2022 as a separate
project. That project will be a collaboration between CDOT and the City of Aspen. While there have
been side studies done at locations like the Aspen Recreation Center and School, there is insufficient
data counts at the roundabout because these past projects focused only on information pertaining to
their site. Obtaining wholistic data on traffic congesting in the roundabout will lead to better decisions
for any modifications that can be made during the 2022 concrete replacement project.
2
The project scope will include organizing existing data and conferring with stakeholders on Maroon
Creek and Castle Creek roadways. Stakeholders could include USFS, the school officials, RFTA,
CDOT and Aspen Skico. By gaining missing traffic data, staff and the consultant will be able to
coordinate modifications that can be made based on counts and not antidotal information.
The project scope will not address the “Entrance to Aspen Record of Decision” that was done in the
1994 The project will not address adjusting the entry through Marolt Open Space or an additional
bridge. The project will organize all existing data, coordinate with the stakeholders and present minor
modifications to Council for any decisions based on the roundabout. Understanding the limits, the data
and Council’s direction will help direct staff coordinate with CDOT for the 2022 concrete replacement
project.
FINANCIAL IMPLICATIONS: This is a planning project to better understand the traffic challenges
that impact the local legs of the Aspen Roundabout. During this project the City of Aspen will
determine traffic challenges based on the data obtained in the project. These deliverables will cost the
city $97,010.00.
3
Castle and Maroon Creek Road Traffic Improvements
Trish Aragon, P.E.
Pete Rice, P.E.
Jack Danneberg, E.I.T. November 11th, 2019
4
Background
5
•Understand Issues
•Quick and Cheap Fixes
Goals
6
What this project is not:
7
Where are we?
8