HomeMy WebLinkAboutFile Documents.185 Forge Rd.0051.2018 (14).ARBKGenerated by REScheck-Web Software
Compliance Certificate
Project 0185 Forge Rd. #102
Energy Code:2009 IECC
Location:Aspen, Colorado
Construction Type:Multi-family
Project Type:Alteration
Climate Zone:7 (9922 HDD)
Permit Date:
Construction Site:
0185 Forge Road #102
Aspen, co 81611
Owner/Agent:
Jessica Baer
BSquared Staffing
0185 Forge Rd
Unit102
Aspen, co 81611
970 948 0692
jessbaer1@hotmail.com
Designer/Contractor:
Susanne Lovell
Lovell, Inc
po box 3914
Aspen, CO 81612
lovellsusanne@gmail.com
Permit Number:
Compliance: Passes
40.0% Better Than Code Maximum UA:5 Your UA:3
The % Better or Worse Than Code Index reflects how close to compliance the house is based on code trade-off rules.
It DOES NOT provide an estimate of energy use or cost relative to a minimum-code home.
Compliance:
Envelope Assemblies
Assembly
Gross Area
or
Perimeter
Cavity
R-Value
Cont.
R-Value U-Factor UA
Window: Vinyl Frame 6 0.170 1
Window: Vinyl Frame 8 0.200 2
Name - Title Signature Date
Compliance Statement: The proposed building design described here is consistent with the building plans, specifications, and other
calculations submitted with the permit application. The proposed building has been designed to meet the 2009 IECC requirements in
REScheck Version : REScheck-Web and to comply with the mandatory requirements listed in the REScheck Inspection Checklist.
Project Title: 0185 Forge Rd. #102
Data filename:Page 1 of 6
02/20/18Report date:
susanne lovell susanne lovell 02/22/2018
03/06/2018
Inspection Checklist
Requirements: 100.0% were addressed directly in the REScheck software
REScheck Software Version : REScheck-Web
Text in the "Comments/Assumptions" column is provided by the user in the REScheck Requirements screen. For each
requirement, the user certifies that a code requirement will be met and how that is documented, or that an exception
is being claimed. Where compliance is itemized in a separate table, a reference to that table is provided.
Energy Code: 2009 IECC
Section
#
& Req.ID
Pre-Inspection/Plan Review Plans Verified
Value
Field Verified
Value Complies?Comments/Assumptions
103.2
[PR1]1
Construction drawings and
documentation demonstrate
energy code compliance for the
building envelope.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
103.2,
403.7
[PR3]1
Construction drawings and
documentation demonstrate
energy code compliance for
lighting and mechanical systems.
Systems serving multiple
dwelling units must demonstrate
compliance with the commercial
code.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
403.6
[PR2]2
Heating and cooling equipment is
sized per ACCA Manual S based
on loads per ACCA Manual J or
other approved methods.
Heating:
Btu/hr_____
Cooling:
Btu/hr_____
Heating:
Btu/hr_____
Cooling:
Btu/hr_____
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
Additional Comments/Assumptions:
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title: 0185 Forge Rd. #102
Data filename:Page 2 of 6
02/20/18Report date:03/06/2018
Section
#
& Req.ID
Foundation Inspection Complies?Comments/Assumptions
303.2.1
[FO11]2
A protective covering is installed to
protect exposed exterior insulation
and extends a minimum of 6 in. below
grade.
Complies
Does Not
Not Observable
Not Applicable
Exception: Requirement is not applicable.
403.8
[FO12]2
Snow- and ice-melting system controls
installed.
Complies
Does Not
Not Observable
Not Applicable
Exception: Requirement is not applicable.
Additional Comments/Assumptions:
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title: 0185 Forge Rd. #102
Data filename:Page 3 of 6
02/20/18Report date:03/06/2018
Section
#
& Req.ID
Framing / Rough-In Inspection Plans Verified
Value
Field Verified
Value Complies?Comments/Assumptions
402.1.1,
402.3.1,
402.3.3,
402.5
[FR2]1
Glazing U-factor (area-weighted
average).
U-_____U-_____Complies
Does Not
Not Observable
Not Applicable
See the Envelope Assemblies
table for values.
303.1.3
[FR4]1
U-factors of fenestration products
are determined in accordance
with the NFRC test procedure or
taken from the default table.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
Location on plans/spec:
A1.1
402.4.4
[FR20]1
Fenestration that is not site built
is listed and labeled as meeting
AAMA/WDMA/CSA 101/I.S.2/A440
or has infiltration rates per NFRC
400 that do not exceed code
limits.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
402.4.5
[FR16]2
IC-rated recessed lighting fixtures
sealed at housing/interior finish
and labeled to indicate ≤2.0 cfm
leakage at 75 Pa.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
Location on plans/spec:
See Specifications provided,
A1.1 Lighting Plan
403.2.1
[FR12]1
Supply ducts in attics are
insulated to ≥R-8. All other ducts
in unconditioned spaces or
outside the building envelope are
insulated to ≥R-6.
R-_____
R-_____
R-_____
R-_____
Complies
Does Not
Not Observable
Not Applicable
Exception: Ducts located
completely inside the
building envelope.
403.2.2
[FR13]1
All joints and seams of air ducts,
air handlers, filter boxes, and
building cavities used as return
ducts are sealed.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
403.2.3
[FR15]3
Building cavities are not used for
supply ducts.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
403.3
[FR17]2
HVAC piping conveying fluids
above 105 ºF or chilled fluids
below 55 ºF are insulated to ≥R-
3.
R-_____R-_____Complies
Does Not
Not Observable
Not Applicable
Exception: Requirement is
not applicable.
403.4
[FR18]2
Circulating service hot water
pipes are insulated to R-2.
R-_____R-_____Complies
Does Not
Not Observable
Not Applicable
Exception: Requirement is
not applicable.
403.5
[FR19]2
Automatic or gravity dampers are
installed on all outdoor air
intakes and exhausts.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
Additional Comments/Assumptions:
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title: 0185 Forge Rd. #102
Data filename:Page 4 of 6
02/20/18Report date:03/06/2018
Section
#
& Req.ID
Insulation Inspection Complies?Comments/Assumptions
303.1
[IN13]2
All installed insulation is labeled or the
installed R-values provided.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
Additional Comments/Assumptions:
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title: 0185 Forge Rd. #102
Data filename:Page 5 of 6
02/20/18Report date:03/06/2018
Section
#
& Req.ID
Final Inspection Provisions Plans Verified
Value
Field Verified
Value Complies?Comments/Assumptions
402.2.3
[FI3]1
Attic access hatch and door
insulation ≥R-value of the
adjacent assembly.
R-_____R-_____Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
402.4.2,
402.4.2.1
[FI17]1
Building envelope tightness
verified by blower door test result
of <7 ACH at 50 Pa. This
requirement may instead be met
via visual inspection, in which
case verification may need to
occur during Insulation
Inspection.
ACH 50 =_____ACH 50 =_____Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
403.2.2
[FI4]1
Post construction duct tightness
test result of ≤8 cfm to outdoors,
or ≤12 cfm across systems. Or,
rough-in test result of ≤6 cfm
across systems or ≤4 cfm
without air handler. Rough-in test
verification may need to occur
during Framing Inspection.
_____ cfm _____ cfm Complies
Does Not
Not Observable
Not Applicable
Exception: All ducts and air
handlers are located within
conditioned space.
403.1.1
[FI9]2
Programmable thermostats
installed on forced air furnaces.
Complies
Does Not
Not Observable
Not Applicable
Exception: Requirement is
not applicable.
403.1.2
[FI10]2
Heat pump thermostat installed
on heat pumps.
Complies
Does Not
Not Observable
Not Applicable
Exception: Requirement is
not applicable.
403.4
[FI11]2
Circulating service hot water
systems have automatic or
accessible manual controls.
Complies
Does Not
Not Observable
Not Applicable
Exception: Requirement is
not applicable.
404.1
[FI6]1
50% of lamps in permanent
fixtures are high efficacy lamps.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
Location on plans/spec:
A1.1, See Spcificitaions
401.3
[FI7]2
Compliance certificate posted.Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
303.3
[FI18]3
Manufacturer manuals for
mechanical and water heating
equipment have been provided.
Complies
Does Not
Not Observable
Not Applicable
Requirement will be met.
Additional Comments/Assumptions:
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title: 0185 Forge Rd. #102
Data filename:Page 6 of 6
02/20/18Report date:03/06/2018
2009 IECC Energy
Efficiency Certificate
Insulation Rating R-Value
0.00Above-Grade Wall
0.00Below-Grade Wall
0.00Floor
0.00Ceiling / Roof
_______Ductwork (unconditioned spaces):
Glass & Door Rating SHGCU-Factor
0.20Window
Door
Heating & Cooling Equipment Efficiency
_______Heating System:_________________________
_______Cooling System:_________________________
_______Water Heater:___________________________
Name:Date:
Comments
03/06/2018