Construction Management Plan
535 E. Hyman Ave. Unit 001
1. Project Introduction
1.1. Unit 001 located in the basement floor of the Core building located at 535 E. Hyman
Ave. will have demising walls added and individual switched lighting added to each
space. This space is 933 SF of floor area. Material staging will be located on the
south side of the building with in the alley access and long term storage will be in
the space itself.
1.2. Vicinity Map:
1.3. The property contains a mixed use building located in downtown Aspen on the SW
corner of Hyman and Hunter Ave. There is an existing occupied tenant space in the
basement of this building. The scope of this remodel will be completed in 1 phase.
We anticipate starting the project in the beginning of June with the expectation of
total project buildout taking no more than six weeks. This building is serviced by
public utilities. There are no plans for upgrading any of the utility services.
2. Project Documentation
2.1. Adjacent properties will be notified of work and provided contact information via
the posting of the project sign the immediate neighbor will be notified of this
construction and informed on an as need basis of possible construction impacts. This
sign will include a brief scope of work and list contractor’s contact information.
05/23/2018
Because impacts beyond the licensed ROW area are not anticipated, specific
notification and on-site meeting should not be necessary.
2.2. A project sign will be posted on the entry door of the building with the contractor's
contact information.
2.3. Contact List:
Owner: Mocking Bird Interests Aspen, LLC
General Contractor: G.F.Woods Construction, Greg Woods (970) 544-1833 / (970)
948-6483
Site Supervisor: Bryan Scott (970) 987-0048
Safety Officer: Bryan Scott (970) 987-0048
Traffic Officer: Bryan Scott (970) 987-0048
3. Project Implementation
3.1. Dates of Construction: Construction is expected to last 6 weeks (June 1, 2018 – July
15, 2018) and will only occur on approved dates Monday through Saturday.
3.2. Hours of Construction: Construction activity will only occur during the allowed
hours of 7:30AM and 5:30PM Mon - Friday and 9AM to 5PM on Saturdays.
3.3. Excavation will not occur or encroach within 5’ of the property line.
3.4. Project is all interior scope so no job site fencing will be installed.
3.5. Project shall uphold utmost respect for public health and welfare.
4. Project Management
4.1. Parking for subcontractors and GF Woods Construction employees will be limited to
street parking. Temporary material staging will be located on the south side of the
building in the alley as well.
4.2. Parking at the site is limited and is all metered. Carpooling and public transit will be
encouraged and utilized to the greatest extent practicable.
4.3. Map of Construction Management Plan is attached as Exhibit A.
5. Traffic Control
5.1. Traffic Control Supervisor will manage operations, if and when necessary.
5.2. Designated haul routes will be followed. Exhibit B
5.3. Maximum vehicle weight shall not exceed 10,000lbs.
5.4. Any traffic control required for deliveries will be coordinated with the City of Aspen
Engineering Department. Deliveries will not be scheduled outside of the approved
hours of construction. No more than one delivery truck can be accommodated at
any time. Deliveries will be unloaded via the entry doors on the Hyman Ave in
early morning hours or through the alleyway to the south of the building.
5.5. A Traffic Control Plan is not included as road blockages or traffic stoppages are not
scheduled or anticipated due to the limited scope and nature of the project.
6. Pedestrian Protection
6.1. Pedestrian safety will be maintained per City Code Section 21.04.060, MUTCD
Chapter 6D, the Americans with Disability Act, and IBC Chapter 33.
7. Sediment and Erosion Control – NA
8. Fugitive Dust Control – N/A.
05/23/2018
9. Emissions – All construction vehicles will be maintained and in good running order.
10. Noise Suppression
10.1. Construction noise will be limited to 80 decibels at the property line whenever
possible. And are not expected to be a concern with all construction activity
contained indoors.
10.2. Loud or obtrusive work will be completed during the approved hours of 9AM to
5PM (Monday through Friday only). Neighbors will be notified 3 days advance.
05/23/2018