520 E. HYMAN
STRUCTUAL REPAIR &
REROOFING
Construction Management Plan
04/23/18
05/08/2018
ATTACHMENT A
PROJECT VICINITY & HAUL ROUTE MAP
= DESIGNATED HAUL ROUTE
05/08/2018
520 E. HYMAN
PERMIT #(TBD).2018.XXXX
GENERAL CONTRACTOR:
HANSEN CONSTRUCTION, INC.
CONTACT: BRYCE OLSON
(970) 309-2518
24 HOUR EMERGENCY CONTACT #:
(970) 920-1558
05/08/2018
Attachment C – Contact List
520 E. HYMAN - CONTACT LIST
Owner: Salt Parks West LLC
Site Supervisor: Aaron Bevington – 970.618.4943
Project Manager: Bryce Olson – 970.309.1558
Safety Officer: Aaron Bevington – 970.618.4943
Traffic Control Officer: Aaron Bevington – 970.618.4943
Erosion Control Representative: Aaron Bevington – 970.618.4943
City of Aspen Community Development: 970.920.5090
City of Aspen Engineering: 970.920.5080
City of Aspen Parks & Recreation: 970.920.5120
Fire Department: Fire Marshal - 970.925.2690
Police Department: Non-Emergency - 970.920.5400
Roaring Fork Transit Authority: 970.920.1905
Aspen School District: 970.925.3760
Aspen Electric Department: 970.920.5148
Aspen Water Department: 970.920.5110
Aspen Sanitation District: 970.925.3601
Source Gas: 800-563-0012
Aspen Valley Hospital: 970.925.1120
Emergency: 911
05/08/2018
273 1017241 8 15222018Aug Sep OctID DescriptionOriginalDurationStart Finish10 Mobilization and Relocation of In-Use M 1 09/03/18 09/03/1820 Roof Removal 10 09/04/18 09/17/1830 Structual Steel Repairs 5 09/18/18 09/24/1840 Structual Decking Installation 5 09/25/18 10/01/1850 Permanent Roofing and Associated Flas10 10/02/18 10/15/1860 Demobilization 1 10/16/18 10/16/18Project StartProject FinishMobilization and Relocation of In-Use MechanicalRoof RemovalStructual Steel RepairsStructual Decking InstallationPermanent RoofDemobilizationStart Date: 09/03/18Finish Date: 10/16/18Data Date: 09/03/18Run Date: 04/23/18 Structural Roof Repair.ppx Page 1A520 E. Hyman Structural Roof Repair and Roofing Replacement05/08/2018
&UDQH4($&RQVWUXFWLRQ)HQFLQJ4/))DFLOLW\4($
)ODWEHG4($$WWDFKPHQW*&030DSGUDIWSGIRI6FDOH7DNHRIILQ$FWLYH$UHD$OO$UHDV5RRI5HSODFHPHQW2Q6FUHHQ30520 E. Hyman Structural Repair and Re-Roof CMP Site PlanHansen Construction, IncAlley Closed Signage05/08/2018
P 970.920.1558 F 970.920.3038 P.O. Box 10493 Aspen, CO 81612 - 2 -
1.0 TABLE OF CONTENTS
2.0 Project Introduction
2.1 Total Project Disturbance Area
2.2 Project Vicinity Map
2.3 Project Description
3.0 Project Documentation
3.1 Permitting
3.2 Public Notification
3.3 Project Sign
3.4 Contact List
4.0 Project Implementation
4.1 Dates of Construction
4.2 Hours of Construction
4.3 Construction Schedule
4.4 Project Fencing
4.5 Tree Protection
4.6 Parks Issues
5.0 Project Management
5.1 Parking Management Form
5.2 Emergency Access and Ordinance 35
5.3 Construction Parking Details
5.4 CMP Map – Staging, Trailer, Materials, Waste Management, Recycling
6.0 Traffic Control
6.2 Project Haul Routes
6.3 Weight and Size Limitations of Vehicles
6.4 Construction Vehicle Activities
6.5 Traffic Control Plan
8.0 Sediment and Erosion Control
9.0 Fugitive Dust Control
10.0 Emissions
10.1 General
10.2 Opacity
11.0 Noise Suppression
11.1 General
11.2 Noise Suppression
05/08/2018
P 970.920.1558 F 970.920.3038 P.O. Box 10493 Aspen, CO 81612 - 3 -
Attachments
A – Project Vicinity and Haul Route Map
B – Project Sign
C – Contact List
D – Construction Schedule
E – Parking Management Form
F – Ordinance No. 35
G – CMP Site Plan
H – Construction Waste Management Plan
J – 13.08.110 Engine Idling
05/08/2018
P 970.920.1558 F 970.920.3038 P.O. Box 10493 Aspen, CO 81612 - 4 -
2.0 PROJECT INTRODUCTION
2.1 Total Project Disturbance Area
The area of disturbance is approximately 3,000 SF which includes the existing roof.
2.2 2.2 Project Vicinity Map
Please refer to Attachment A – Project Vicinity and Haul Route Map
2.3 Project Description
The proposed project will consist of temporarily relocating existing in-use mechanical units,
cutting out and hauling off existing structural roof decking and associated concrete slab,
temporary weather protection, installation structural steel as required by the engineer of record,
installation of new decking, installation of roof insulation, installation of new roofing and
associated flashings.
3.0 PROJECT DOCUMENTATION
3.1 Permitting
All required permits will be obtained by Hansen Construction and their subcontractors
including Structural Repair, Reroofing, Building. Mechanical, Electrical, and Plumbing will be
obtained if required by code to complete the re-roofing.
3.2 Public Notification
Public notification will take place a minimum of 10 days prior to commencement of work and
will be distributed directly to neighbors within a 300 foot radius of the project. It will include an
invitation to a pre-construction meeting, a proposed schedule and description of impacts to the
neighborhood. A preconstruction meeting summarizing this CMP will be held five days after the
aforementioned public notification and held at the project location.
3.3 Project Sign
Please refer to Attachment B – Project Sign
3.3 Contact List
Please refer to Attachment C – Contact List
4.0 PROJECT IMPLEMENTATION
4.1 Dates of Construction
The demolition will commence September 3rd. Estimated completion is October 15th.
05/08/2018
P 970.920.1558 F 970.920.3038 P.O. Box 10493 Aspen, CO 81612 - 5 -
4.2 Hours of Construction
Construction hours shall be limited to 7:30am – 5:30pm Monday through Friday and
9am – 5pm on Saturday. No construction is permitted on Sundays, 4th of July day and/or
weekend if it falls on a Friday or Monday, Memorial Day and Labor Day weekends,
Thanksgiving Day, Christmas Day and New Year’s Day.
During Presidents Day projects located in the Central Resort Area (CRA) are not
permitted to work on any exterior elements, however interior work may be
permitted with prior approval.
During the Christmas week (12/26-12/31) projects located in the Central Resort
Area (CRA) are not permitted to work on any exterior elements, however interior
work may be permitted with prior approval.
During the Holiday Season as defined by Aspen’s CMP Requirements Manual,
projects located in the Core are not permitted to work on any exterior elements,
however interior work will be permitted.
During the Food & Wine Festival in June (Friday thru Saturday) projects located
in the Central Resort Area (CRA) are not permitted to work.
4.3 Construction Schedule
Mobilization and Relocation of In-Use Mechanical- September 3rd
Roof Removal- 2 weeks
Structural Steel Repairs- 1 week
Structural Decking Installation- 1 week
Permanent Roofing and Associated Flashings- 2 weeks
Demobilization- October 15th
4.5 Project Fencing
We will install safety rail fencing around the perimeter of the parapet as needed for fall
protection.
4.6 Tree Protection
Not applicable.
4.7 Parks Issues
Not applicable.
5.0 PROJECT MANAGEMENT
5.1 Parking Management Form
Hansen Construction will utilize the parking space located in the alleyway which is reserved
05/08/2018
P 970.920.1558 F 970.920.3038 P.O. Box 10493 Aspen, CO 81612 - 6 -
for the owners of Unit B. All other construction vehicles will utilize paid parking as needed.
Please refer to Attachment E – Parking Management Form
5.2 Emergency Access and Ordinance 35
Hansen Construction will maintain continuous emergency vehicle access on and around the
site, including but not limited to police, fire, and ambulance services.
Please refer to Attachment F – Ordinance 35
5.3 Construction Parking Details
Hansen Construction will utilize the two parking spaces located on the alley which are
reserved for the penthouse unit and Unit B.
Hansen will also reserve parking spaces in front of the building on an as needed basis
for material deliveries.
Contractor and Subcontractor personnel will be required to carpool in groups of two or
more adults to reach the worksite.
HCI will offer public transit passes to workers that will be on site regularly and have the
ability to take advantage of the public transportation system.
No construction parking will be permitted within the free two-hour residential parking
areas without a valid permit.
5.4 CMP Map - Staging, Trailer, Materials, Waste Management, Recycling
The alleyway will be used for staging and material haul-off exclusively.
Right-of-Way encroachments will be used as a last resort in all cases. In the case where a
ROW encroachment occurs, Hansen Construction will obtain a permit from the City
Engineering Department before encroaching in the Right-of-Way.
Please refer to Attachment G – CMP Site Plan
Please refer to Attachment H – Construction Waste Management Plan
The number of truckloads expected to and from the site are estimated as follows:
Roof Demolition 5
Structural Steel & Deck 5
Concrete on Deck 5
Roof Assemblies 5
Miscellaneous 5
Total Truckloads Estimated 25
05/08/2018
P 970.920.1558 F 970.920.3038 P.O. Box 10493 Aspen, CO 81612 - 7 -
Hansen is anticipating the 90% of the scope of work can be done from the alley. Hansen
does not plan to use a tower crane for this project and will be requesting that parking
permits and/or ROW encroachment permits be granted so that pump trucks and mobile
cranes can be employed in the alley behind the building. For the remaining 10% of the
scope Hansen will be requesting parking permits and/or Row Encroachment permits be
granted for two parking spots on Hyman Avenue directly in front of the building site. Hansen
understands that ROW encroachments are to be minimized and used as a last resort in all
cases. Hansen understands that it shall obtain ROW encroachment permits from the City
Engineering Department before proceeding with said encroachments.
6.0 TRAFFIC CONTROL
6.1 General
All traffic control operations shall be managed by the designated certified traffic control
supervisor.
6.2 Project Haul Routes
Please refer to Attachment A – Project Vicinity and Haul Route Map
6.3 Weight and Size Limitations of Vehicles
Since the proposed building covers most of the lot, there will be no “onsite” vehicles. All
vehicles bring workmen, materials and equipment to the site will comply with State of Colorado
weight restrictions.
6.4 Construction Vehicle Activities
Hansen Construction understands and agrees that:
1. Traffic control required for deliveries must be fully coordinated with the City of Aspen
Engineering Department.
2. Roads will not be closed under any circumstances, unless granted permission from the
City of Aspen Engineering Department.
3. Deliveries times will be coordinated so that only one large truck will be on site at any
given time.
4. Deliveries will only occur during permitted working hours which are 7:30am – 5:30pm
Monday through Friday and 9am – 5pm on Saturday.
5. Delivery and Heavy Duty Vehicles must have a visible sign on the vehicle that specifies
the project contractors name and phone number.
05/08/2018
P 970.920.1558 F 970.920.3038 P.O. Box 10493 Aspen, CO 81612 - 8 -
6. Delivery vehicles and all other onsite vehicles are not allowed to idle for more than five
(5) minutes, with the exception of generators or PTO type operations.
7. 13.08.110 Engine Idling- Hansen will adhere to the city’s idling policy which is attached
hereto as Attachment J.
6.5 Traffic Control Plan
We anticipate that the alley way directly behind the building will be closed during
construction hours throughout the project. No through traffic ahead signs will be posted at the
entrance to the alley and alley closed signs will be posted at the crane. If some unique need
arises, a Traffic Control Plan (TCP) will be prepared by a State Certified Traffic Control
Supervisor. The plan will conform to the most current edition of the Manual of Uniform Traffic
Control Devices for Streets and Highways (MUTCD) and be submitted to the City of Aspen
Department of Engineering for approval/permitting.
8.0 SEDIMENT AND EROSION CONTROL
We do not anticipate that there will be any need for sediment and erosion control measures,
however, if we end up doing any unanticipated work that disturbs more than 1,000 square feet
of the sidewalk, street or alley, we will submit a Stormwater Management Plan as required.
9.0 FUGITIVE DUST CONTROL
We do not anticipate that there will be any need for fugitive dust control measures, however,
if we end up doing any unanticipated work that results in fugitive dust emissions, we will submit
a fugitive dust control plan and file an application for a construction permit with the Colorado
Department of Public Health and Environment as required.
10.0 EMISSIONS
10.1 General
All vehicles and equipment used on site will be properly maintained such that the engines
will function within the manufacture’s standards or parameters.
10.2 Opacity
Emissions from diesel engines operated within the City of Aspen shall be of a shade or
density no darker than 40% opacity, except for starting motion no longer than 10 seconds or for
stationary operation not exceeding 10 seconds.
05/08/2018
P 970.920.1558 F 970.920.3038 P.O. Box 10493 Aspen, CO 81612 - 9 -
11.0 NOISE SUPPRESSION
11.1 General
Hansen understands that projects located in the Core are limited to 75 dB at the property
line during the summer season and 80 dB at the property line all other times of the year. All
construction equipment shall be adequately muffled and maintained to minimize project noise.
The installation of noise barriers is the minimum technique to suppress noise, especially when
jack hammering of concrete occurs.
11.2 Noise Suppression
520 E. Hyman roof replacement and structural repair work will require the use the of
concrete saws, hammer drills, and a crane. It is our intention to cut the roof out in tiles weighing
less than 4,500 pounds for safe removal by a crane. Slabs will be loaded onto a flat bed and
hauled away. During saw cutting the use of movable barricades around cutting activity will be
utilized. When the crane is onsite the use of movable barricades around the crane will be
utilized.