1.0 General
Total Square Footage of soil disturbance = N/A
Internal Remodel Only.
Table of Contents :
1.0 GENERAL ................................................................................................. 2
2.0 PROJECT INTRODUCTION ........................................................................ 4
2.1 Project Location…….................................................................................. 4
2.2 Project Disturbance Area ........................................................................ 4
2.3 Project Description ................................................................................. 4
3.0 PROJECT DOCUMENTATION ................................................................... 5
3.1 Permitting................................................................................................ 5
3.2 Public Notification ................................................................................... 5
3.3 Project Sign .............................................................................................. 5
3.4 Contact List .............................................................................................. 6
4.0 PROJECT IMPLEMENTATION .................................................................... 7
4.1 Dates of Construction .............................................................................. 7
4.2 Hours of Construction.............................................................................. 7
4.3 Construction Schedule ............................................................................ 7
4.4 Adjoining Properties………........................................................................ 7
4.5 Project Fencing …………............................................................................ 7
4.6 Natural Environment .............................................................................. 7
4.7 Public Health and Welfare....................................................................... 7
5.0 PROJECT MANAGEMENT ………................................................................ 7
01/30/2019
3 | Page
5.1 Parking Management............................................................................... 7
5.3 Emergency Access…................................................................................... 7
5.4 Staging Areas ............................................................................................. 7
6.0 TRAFFIC CONTROL ......................................................................................8
6.1 General .......................................................................................................8
6.2 Haul Routes................................................................................................. 8
6.3 Weight and Size Limitations of Vehicles ..................................................... 8
6.4 Delivery Requirements................................................................................ 8
7.0 PEDESTRIAN PROTECTION - N/A................................................................ 8
8.0 SEDIMENT AND EROSION CONTROL .......................................................... 8
8.1 Requirements.............................................................................................. 8
9.0 FUGITVE DUST CONTROL............................................................................. 8
9.1 Dust Control Plan......................................................................................... 8
10.0 EMISSIONS.................................................................................................. 8
10.1 General....................................................................................................... 8
10.2 Emissions From Diesel Powered Engines ................................................... 8
11.0 NOISE SUPPRESSION................................................................................... 8
11.1 General........................................................................................................ 8
11.2 Noise Suppression Plan................................................................................ 8
01/30/2019
4 | Page
2.0 Project Introduction
2.1 Total Disturbance Area = N/A – Inside Remodel Only
2.2 Project Vicinity Map. 100 East Main Street, Aspen, CO 81611
2.3 Basic Remodel -
- The Project consists of demolition of One Internal Wall.
(NON-Structural).
- Building 3 Doctors Exam Rooms, Supply Closet and Break Room.
01/30/2019
5 | Page
3.0 Project Documentation
3.1 Permit Types we will be submitting :
Building Permit, Construction Parking Permit, Electrical Permit,
Mechanical Permit, Plumbing Permit.
3.2 A project update shall be provided to the public on a basis no less
than monthly, via website on-site notices, or other accepted means
of notification (per request of the City of Aspen). The first public
notification shall occur no later than 10 days prior to construction.
ALL properties within 300 Feet by letter. Sample Attached.
3.3 Project Sign will be constructed and posted within 30 days of
Construction. (Enlarged Print Out in CMP.)
01/30/2019
6 | Page
3.4 The currently planned Project Contacts and Construction Team is as
follows :
Owner : Hanover Aspen, LLC
PO Box 481
Woody Creek, CO 81656
Structural Engineer : Hein L Brutsaert Engineering
133 Prospector, Aspen, CO 81611
Phone : (970) 300-1003
Contractor : Rutgers Construction
256 Twining Flats Road, Aspen, CO 81611
Phone : (970) 925-8229
Project Manager : Chris Morrow
Phone : (970) 379-5810
email : chris@rutgersconstruction.com
Architect : Galambos Architects - Janet Leverson
314 AABC, Unit # D, Aspen, CO 81611
Phone : (970) 429-1286
jleverson@galambosarchitects.net
Site Supervisor : James Guest 970-379-1195
Safety & Traffic Control Officer : James Guest 970-379-1195
Erosion Control Representative : James Guest 970-379-1195
EMERGENCY : Dial 911
Police Department : (970) 920-5400
Fire Department : (970) 925-8484
Pitkin County : (970) 920-5526
City of Aspen : (970) 920-5000
RFTA : (970) 925-8484
Holy Cross : (970) 945-5491
Source Gas : (970) 928-0401
Aspen Consolidated Sanitation : (970) 925-3601
01/30/2019
7 | Page
4.0 Project Implementation
4.1 Dates of Construction : Permit Pending.
Currently, the work is scheduled to commence around the beginning
of February, 2019. It is estimated that the total duration will be 30
work days, with a desired completion March, 2019.
4.2 Hours of Construction :
Construction hours will be limited to 7:30am – 5:30pm, Monday
through Friday, and 9:00am – 5:00pm on Saturdays. Construction
activities will not be permitted on Sundays or federally designated
holidays.
NO Noise Suppression Plan is needed due to low noise level.
4.3 Construction Schedule: Jan 7th through Jan 29th 2019.
3 x Days Demo.
10 x Days Rough Carpentry.
5 x Days Plumbing.
6 x Days HVAC.
8 x Days Electrical.
10 x Days Finish Carpentry.
1 x Days Install Carpet Floor.
5 x Days Painting.
4.4 N/A
4.5 N/A
4.6 N/A
4.7 N/A
5.0 Project Management
5.1 Complete Parking Management Form
(In CMP Folder). Appendix A
5.2 Continuous access for emergency vehicles (police, fire, and
ambulance) will be maintained on and around the project site.
5.3 N/A
5.4 All Materials will be staged inside.
Waste and Trash will be put in Truck parked out front.
01/30/2019
8 | Page
6.0 Traffic Control
6.1 Safety & Traffic Control Officer : James Guest 970-379-1195
6.2 Project Haul Routes : N/A
6.3 Weight and Size Limitations of Vehicles. N/A
6.4 Construction Vehicles / Delivery Vehicles.
All deliveries will be made by Rutgers Construction.
6.5 Traffic Control Plan : N/A
7.0 PEDESTRIAN PROTECTION - N/A
8.0 Sediment and Erosion Control : N/A
9.0 Fugitive Dust Control : N/A
10.0 Emissions : N/A
11.0 Noise Suppression : N/A
01/30/2019