HomeMy WebLinkAboutFile Documents.108 Maple Ln.0035.2017 (6).ARBK! Response letter to conversation with Engineering 1. The plans indicate the neighboring north and east properties are providing temporary easements for the construction of the wall. Please provide supporting documentation for review. Please see documents named; agreement Strobl.Curley Easement - Recorded and agreement HOA .2017.01 2. It does not appear the geotechnical report provides soil design parameters for the stabilization design. Please provide supporting documentation that shows the parameters in the temporary shoring plans meet those on the site or where they can be found in the report. See Response Letter Temporary Excavation Support by Rock Solid Solutions 3. Has the neighborhood HOA approved the encroachment into Maple Ln? Please see agreement HOA .2017.01 4. The drawings provided appear to show the micropile cap is below the adjacent finished grade, which could cause negative impacts to the neighboring properties. Please indicate why the cap isn’t at grade and how neighboring properties will be protected from negative impacts. Cap is below grade at the request of the neighbor. This is so finished grade or the concrete sidewalk can be restored over the top of the cap at completion of construction. 5. It appears the structure on the property to the west may be negatively impacted by the excavation. Please provide supporting documentation which shows excavation stabilization is not required in this area. See Response Letter Temporary Excavation Support by Rock Solid Solutions 6. Given the proximity of the south basement wall to the lot line please indicate how excavation will be done in this area and stay within the lot line boundary. It would appear excavation stabilization would also be required in this area. Please provide supporting documentation that demonstrates why it is not required. Encroachment into south greenbelt is allowed by the HOA. Please see agreement HOA .2017.01 and Response Letter Temporary Excavation Support by Rock Solid Solutions 7. The Applicant/Contractor shall pothole all utilities in close proximity and verify no conflicts are present before the installation of such systems. Contractor will pothole all utilities prior to commencement of construction. 970.927.7620 204 Park Ave., Suite 2F PO Box 4432 Basalt, CO 81621 brad@bearchitect.com www.BEArchitect.com 9/1/17 9/1/17 9/1/17