HomeMy WebLinkAboutFile Documents.1419 Crystal Lake Rd.0267.2018 (2).ARBK1419 Crystal Lake Change Order #2
(a) 300 S. Spring Street, Suite 201 Aspen, CO 81611 (c) Ryan 970.274.1421 & Matthew 970.618.1645 (w) www.thunderbowlarchitects.com
Scope of Work- This Change Order has the following components associated with it:
Sheet A-101:
-Interior wall located between gridlines 3.5 and 4, and gridlines B and C has been added 12BBB inches
to the South of existing partition.
Sheet A-102:
-Interior kitchen window 10 located between gridlines 4 and 5, and on gridline B has shifted to the
south 2’’ feet 6 inches.
-Interior kitchen wall located between gridlines 3.5 and 4, and gridlines B and D has been added,
entire kitchen has shifted 16B inches to the South.
-Doors in Mud Room closet located between gridlines 2 and 3, and gridlines C and D have been
removed.
-Stairs in garage located between gridlines 1.5 and 3, and gridlines A.75 and B have been altered to
be a straight run stair, and adjacent partial height wall has been added.
-Directional swing for interior door 112 leading from garage to mud room has been flipped.
-Dining room built-in framing located between gridlines 3.5 and 4.5, and gridlines E and E.5 has
been adjusted.
-Dining room built-in framing located between gridlines 3.5 and 4.5, and gridlines F and G has been
adjusted and a full-height wall separating the living room and dining room has bee added.
-Dining room slider door 105 size has been adjusted.
-Interior wall located in powder room on gridline 3 between gridlines F and G has been added 12
inches from existing partition.
-Fireplace surround located in living room between gridlines 3 and 4, and gridlines G and H has
been adjusted.
-Finish floor elevations of both living room and exterior covered patio have been revised to show
existing site conditions.
-Step has been added to bottom of spa area south of gridline 6 located on gridline G.
Sheet A-103:
-Window 32 between gridlines 1.5 and 2 and on gridline A.75 has been adjusted to fit existing
opening.
-Interior corner wall condition has been added to her closet between gridlines 1.5 and 2, and
gridlines D and E.
-Master bedroom fireplace surround framing between gridlines 3 and 4, and gridlines E.5 and F has
been adjusted.
- Size of master bath sliding doors and individual window unit has been adjusted, rough opening
matches existing.
-Closet in bedroom 4 between gridlines 4.5 and 5, and gridlines B and C has been revised.
Sheet A-201:
-Living room top of finish floor elevation markers have been revised to reflect site conditions.
Sheet A-202:
-Living room top of finish floor elevation marker has been revised
-Drawing 2 West elevation, size of window 32 between gridlines 1.5 and 2 has been revised.
-Drawing 2 West elevation, location of window 10 between gridlines 4 and 5 has been revised.
10/31/2018
1419 Crystal Lake Change Order #2
(a) 300 S. Spring Street, Suite 201 Aspen, CO 81611 (c) Ryan 970.274.1421 & Matthew 970.618.1645 (w) www.thunderbowlarchitects.com
Sheet A-301:
-Living room top of finish floor elevation marker has been revised.
-Drawing 1 section 1 between gridlines A7.5 and A.5, interior partial height wall has been added
Sheet A-303:
-Living room top of finish floor elevation marker has been revised.
Sheet A-501:
-Drawing F-2 has been updated to reflect proposed floor build-up.
Sheet A-701:
-New lighting layout
Sheet A-702:
-New lighting layout.
Sheet A-703:
New lighting layout.
10/31/2018
11/15/2018