BRIKOR ASSOCIATES
20 Sunset Drive, Unit 1
Basalt, Colorado 81621
WWW.BRIKOR.COM
ASPEN CORE HOLDINGS, LLC.
135 EAST COOPER AVE
Construction Management Plan
May 29, 2019
05/30/2019
APPROVED
IFFR approval only. There is no site plan in the CMP. I spoke with Karl Schindler of Brikor about
this. He assured me that all storage and materials will be on private property. This permit also
includes a full demo of a garage structure. Karl said this will be by hand and no machinery involved.
Any work that does not fit this description was not approved in this CMP.
Patrick Harris 6/19/19
970 923 3088
BRIKOR ASSOCIATES
20 Sunset Drive, Unit 1
Basalt, Colorado 81621
WWW.BRIKOR.COM
TABLE OF CONTENTS
2.0 Project Introduction
2.1 Project Description
2.2 Project Disturbance Area
3.0 Project Documentation
3.1 Permitting
3.2 Public Notification
3.3 Project Sign
3.4 Contact List
4.0 Project Implementation
4.1 Dates of Construction
4.2 Hours of Construction
4.3 Construction Schedule
4.5 Project Fencing
4.6 Tree Protection
4.7 Parks
5.0 Project Management
5.1 ROW Management Plan
5.2 Emergency Access and Ordinance 35
5.3 Construction Parking
5.4 Staging Areas
5.5 Construction Trailer, Material Storage, and Waste Management
6.0 Traffic Control
6.2 Haul Routes
6.3 Weight and Size Limitations of Vehicles
6.4 Delivery Requirements
6.5 Traffic Control Plan
8.0 Sediment and Erosion Control
8.1 Storm Water Pollution Prevention Plan
8.2 BMP’s for Stormwater Pollution Prevention
8.3 Final Stabilization and Long Term Stormwater Quality
9.0 Fugitive Dust Control
9.1 Dust Control Plan
05/30/2019
970 923 3088
BRIKOR ASSOCIATES
20 Sunset Drive, Unit 1
Basalt, Colorado 81621
WWW.BRIKOR.COM
10.0 Emissions
10.1 Maintenance
10.2 Opacity
11.0 Noise Suppression
11.0 General
11.1 Noise Suppression Plan
11.2 Equipment and Method
APPENDICES
A – Required Project Sign
B – Parking Management Form
C – Haul Route Map
D – Noise Suppression Plan, Techniques and Equipment
E – Construction Schedule
G – Ordinance No. 35
H – Engine Idling
05/30/2019
970 923 3088
BRIKOR ASSOCIATES
20 Sunset Drive, Unit 1
Basalt, Colorado 81621
WWW.BRIKOR.COM
2.0 Project Introduction
2.1 Project Description
Installation of all required BMP and a six foot black screened chain link
fence with two gates for access. Demolition of all interior finishes and MEP from all four
existing structures. Installation of structural stabilization framing on three of the existing
structures in preparation to move the buildings. The rear Historic resource will be moved
off site and located temporarily at the Smuggler Racquet Club while the two forward
structures (including the Main Historic Resource) will be relocated on cribbing to the
rear of the property. The existing non historic garage will be demolished and debris
hauled off, as will the existing foundation structures. A temporary shoring system will be
installed till the new cast in place concrete foundation can be installed and the existing
buildings can be relocated atop their new structures. The existing structures will all be
remodeled according to the construction documents, as will the infrastructure for the
buildings (including MEP) as well as the landscaping.
2.2 Project Disturbance Area
6500 sq. ft.
2.3 Project Vicinity Map
See attached Appendix C – Project Vicinity and Haul Route Map
3.0 Project Documentation
3.1 Permitting
This CMP is being submitted as part of the application for a building
permit.
3.2 Public Notification
Public Notification will take place a minimum of 10 days prior to
commencement of work and will be distributed directly to neighbors within a 300 ft.
radius of the project. It will include an invitation to a pre-construction meeting, a
proposed schedule and description of impacts to the neighborhood.
05/30/2019
970 923 3088
BRIKOR ASSOCIATES
20 Sunset Drive, Unit 1
Basalt, Colorado 81621
WWW.BRIKOR.COM
A pre-construction meeting summarizing this CMP will be held five days
after the aforementioned public notification or five days prior to starting work.
Work on project is tentatively scheduled to begin 5/27/2019. The pre-
construction meeting is therefore tentatively scheduled for 5/22/2019 at 10 am, or a date
to be determined by issuance of the building permit. Karl Schindler, Brikor Associates
Project Manager will act as the project representative and will notify all
parties listed above.
3.3 Project Sign
135 E. Cooper Ave Project Sign – APPENDIX A
3.4 Contact List
Owner: Aspen Core Holdings, LLC. c/o Cristof Eigelberger – 415-819-6284
Contractor: Brikor Associates – 970-923-3088
Site Supervisor: Karl Schindler - 970-618-6396
Safety Officer: Karl Schindler – 970-618-6396
Traffic Control Officer: Karl Schindler – 970-618-6396
Erosion Control Representative: Karl Schindler – 970-618-6396
Architect of Record: Cristof Eigelberger – 415-819-6284
City of Aspen Community Development – 970-920-5090
Pitkin County: 970-920-5200
Aspen Police Dept.: 970-925-5400
Aspen Fire Protection District – 970-925-2690
School District: 970-925-3760
RFTA: - 970-925-8484
Water Dept.: - 970-920-5110
Aspen Consolidated Waste: 970-925-3601
City of Aspen Electric: - 970-925-5491
Black Hills Energy: 888-890-5554
Aspen Valley Hospital: 970-925-1120
Emergency Services: - 911
05/30/2019
970 923 3088
BRIKOR ASSOCIATES
20 Sunset Drive, Unit 1
Basalt, Colorado 81621
WWW.BRIKOR.COM
4.0 Project Implementation
4.1 Dates of Construction
The current project start is scheduled for 12/1/2019. The estimated project duration
is 24 months putting the anticipated projected completion date at 12/1/2021. Start Date
is
dependent on permitting review and issuance timeframe. We do not anticipate to do any
work within the COA Right of Way.
4.2 Hours of Construction
Construction hours will be limited to 7:30am – 5:30pm Monday through Friday and
9:00am – 5:00pm on Saturday. Additional prohibited construction days are as follows:
• Sundays
• 4th of July
• Memorial day Weekend
• Labor day Weekend
• Thanksgiving day
• Christmas Day
• New Years Day
4.3 Construction Schedule
Please see attached – Appendix E – Construction Schedule
4.5 Project Fencing
A six foot black chain link fence and black screening will be installed along the
entire perimeter of the property along the limits of disturbance. Tree protection will be
installed around the drip line of the large willow in the front yard.
4.6 Public Health and Welfare
Brikor Associates will do the utmost to respect and protect public health and
welfare.
05/30/2019
Food and Wine
970 923 3088
BRIKOR ASSOCIATES
20 Sunset Drive, Unit 1
Basalt, Colorado 81621
WWW.BRIKOR.COM
4.7 Natural Environment
All of the surrounding natural environment will be respected and in the case of any
deliveries or operations that may affect the natural environment, protection of any
resource will be installed or implemented.
5.0 PROJECT MANAGEMENT
5.1 Right of Way Management Plan
At this point we do not anticipate the need to use the public ROW for anything
other than deliveries, and parking. Please see 5.3 below regarding construction parking
details.
5.2 Emergency Access and Ordinance 35
Brikor Associates will maintain continuous emergency vehicle access to the site,
including but not limited to police, fire, and ambulance services.
See Ordinance 35 – APPENDIX G
5.3 Construction Parking
See Parking Management Form – APPENDIX B. Applicant understands that the
COA Engineering Dept. does not review the Parking Management Form included in
Appendix B and Applicant shall submit said form to the COA Parking Dept. for review and
approval.
5.4 Staging Areas
All material handling and equipment staging will be accommodated on site, in the
garage, or inside the house. Under no circumstances will job materials be stored in the ROW,
unless rented from the COA for staging. Brikor Associates will keep trash containers and
portable restrooms within the limits of the project’s property.
05/30/2019
970 923 3088
BRIKOR ASSOCIATES
20 Sunset Drive, Unit 1
Basalt, Colorado 81621
WWW.BRIKOR.COM
5.5 Construction Trailer, Material Storage and Waste
Management
An 8X20’ construction trailer will be situated on site at the time
mobilization. The trailer will need to be located in different areas depending on
sequence of construction. Minimal storage will be required as all materials will be
delivered at time of use, and most materials will be stored in house or garage. No
loose materials will stored in any public right of way. Waste management will be
handled by bear proof containers placed on site. Construction related materials
will be sorted on site and placed in appropriate containers.
6.0 TRAFFIC CONTROL
6.2 Haul Routes
See Haul Route Map – APPENDIX C
6.3 Onsite Vehicle Limitations
Vehicle weights and sizes will be in accordance with local limitations.
6.4 Deliver Requirements
Pickup and deliveries times will be coordinated so that only one large truck
will be on site at any given time. Delivery vehicles and all other on-site vehicles
will not be allowed to idle for more than five (5) minutes, with the exception of
generators or PTO type operations. Project subcontractor and suppliers will be
provided with written notification of Aspen’s vehicle idling regulations. See
Section 13.08.110 Engine Idling – APPENDIX H.
6.5 Traffic Control Plan
Brikor Associates does not anticipate that there will be any need to
interfere with traffic on any public right-of-way. If some unforeseen need arises, a
Traffic Control Plan (TCP) will be prepared by a
State Certified Traffic Control Supervisor. The plan will conform to the most
current edition of the Manual of Uniform Traffic Control Devices for Streets and
Highways (MUTCD) and be submitted to the City of Aspen Department of
Engineering for approval/permitting.
05/30/2019
970 923 3088
BRIKOR ASSOCIATES
20 Sunset Drive, Unit 1
Basalt, Colorado 81621
WWW.BRIKOR.COM
8.0 SEDIMENT AND EROSION CONTROL
8.1 Storm Water Pollution Prevention Plan
During all site disturbance, all recommended Best Management Practices
(BMP’s) will be in place and maintained in order to minimize dirt entering the
streets. Primary strategies are as follows:
Avoid unnecessary site disturbance.
Maintain grading; install silt fences and sediment traps prior to any soil disturbance.
The installation of a tracking pad will be impractical due to the limited space
available. Brikor will make sure that the short ramp into the excavation is kept as
mud free as possible by use of screened rock over geo-textile fabric and not using
the ramp in wet conditions.
The washout of concrete chutes will have to be done back into the concrete trucks
due to the lack of space on site. Brikor will do everything they can to make sure
that the concrete trucks do not wash out illegally offsite.
Hard plastic kiddie pools or concrete dumpsters will be used to protect the ground
below the concrete pump transfer points. Spills captured will be allowed to dry and
will be placed in the site trash receptacle.
Pathways around the house will be stabilized primarily through the use of screened
rock over geo-textile fabric.
8.2 BMPs for Stormwater Pollution Prevention
Best Management Practices (BMPs) will be employed for stormwater management as
indicated in the following sections. The construction sequence as indicated in 4.3 above
will
help minimize the total area of disturbance at any particular point in time.
a) Structural Practices:
a. Silt fences will be installed on the downhill sides of all areas of disturbance as
shown on the civil engineers drainage and erosion control plans.
b. All open excavations will include the temporary development of a low point
with a sump/pump for the removal of stormwater. The sump inlet will be
protected with straw bales or a Dandy Bag type sediment filtration measure.
Clear sump effluent will be discharged where it will not cause further erosion
(to be determined based on construction phasing and available outlet areas
at that time).
c. Temporary diversion ditches and swales will direct runoff from other site
05/30/2019
970 923 3088
BRIKOR ASSOCIATES
20 Sunset Drive, Unit 1
Basalt, Colorado 81621
WWW.BRIKOR.COM
areas through straw wattle and hay bale filtration prior to discharge off the
site. The exact location and alignment of these structures will be determined
in the field based on project phasing and the space needed for construction
staging.
d. Fugitive dust control will be achieved using a hose and spray nozzle.
e. Surface roughening will be conducted in newly excavated areas to provide
temporary stabilization when other temporary stabilization measures are not
feasible (such as gravel or temporary vegetation) or will not be provided
immediately.
f. If for any reason construction is delayed for a period of time exceeding 30
days, more permanent stabilization will be put into place including backfilling
open excavations and reestablishing vegetation with seed and mulch.
b) Non-Structural Practices: Pollution prevention will be stressed among all employees
and sub-contractors, including adequate training of personnel and frequent
monitoring of activities.
a. Proper facilities and procedures will be used for on-site waste storage and
disposal. Daily inspection and maintenance of waste disposal areas will be
conducted. Where possible, waste containers will be covered, and waste
storage areas will be fenced.
b. The contractor will ensure that good housekeeping will be employed during
construction, with all work, materials storage and waste storage areas kept in
a neat and orderly condition.
c. Existing trees and mature vegetation that are not to be removed will be
protected during construction to limit unnecessary disturbance of site soils
and maintain natural erosion control.
c) Materials Handling:
a. All potentially hazardous materials will be stored off site. In the event that
any such materials are stored on site, toxic materials and petroleum products
will be enclosed and contained in an impervious elevated basin sized large
enough to hold the volume of the hazardous materials being contained.
b. Any spill or discharge or construction related materials will be cleaned up
immediately and disposed of accordingly.
c. Any spill not properly contained and cleaned-up will be reported to the proper
authorities.
i. Aspen Fire Department, Fire Marshal: 925-2690
ii. Colorado Department of Public Health and Environment, Emergency
Response: 303-756-4455.
iii. City of Aspen Engineering Department: 920-5080
iv. City of Aspen Environmental Health Department: 920-5039.
v. National Response Center: 800-424-8802
05/30/2019
970 923 3088
BRIKOR ASSOCIATES
20 Sunset Drive, Unit 1
Basalt, Colorado 81621
WWW.BRIKOR.COM
8.3 Final Stabilization and Long-Term Stormwater Quality
All temporary BMPs will remain in place until construction is complete and revegetation has
been verified to have taken hold. Final stabilization and long term stormwater quality are
addressed by the civil and landscape drawings submitted as part of the building permit submittal
package.
8.4 Inspection and Maintenance Procedures
a) A thorough inspection of the stormwater management system will be performed at
least every 14 days, and after any precipitation event that causes run off. The
inspection will include the observation of the construction site perimeter and
discharge points, all disturbed areas, and material storage areas exposed to
precipitation. All erosion and sediment control measures will be inspected for
integrity and functionality (e.g., sediment fences, hay bales, straw wattles, temporary
swales and ditches).
b) Damaged or ineffective BMPs will be fixed and/or replaced. Removed sediment will
be placed where it will not become an additional pollution source.
c) When necessary, BMPs will be added, removed or replaced with more effective
measures. All such actions will be documented and the SWMP will be updated to
reflect those changes.
9.0 FUGITIVE DUST CONTROL
9.1 Dust Control Plan
Since this is an interior remodel, we do not anticipate that fugitive dust will be
much of an issue. If there is any site disturbance, the project’s Dust Prevention and
Control Plans are as follows:
Avoid unnecessary site disturbance.
During construction a hose and spray nozzle will be used on exposed soils as
necessary
to mitigate air born dust.
Exported soils and other debris will be hauled off via covered dump trucks. All areas
05/30/2019
970 923 3088
BRIKOR ASSOCIATES
20 Sunset Drive, Unit 1
Basalt, Colorado 81621
WWW.BRIKOR.COM
directly surrounding the site will be maintained daily with thorough cleanings taking
place
every Friday afternoon.
24 Hour Contact: Karl Schindler – 970.618.6396
P 970.923-3088 – 30 Sunset Dr, Basalt CO 81627
10.0 EMISSIONS
10.1 Maintenance
All vehicles and equipment used on site will be properly maintained such that the
engines will function within the manufacture’s standards or parameters.
10.2 Opacity
Emissions from diesel engines operated within the City of Aspen shall be of a shade or
density no darker than 40% opacity, except for starting motion no longer than 10
seconds or for
stationary operation not exceeding 10 seconds.
11.0 NOISE SUPPRESSION
11.0 General
The allowable noise limit at this location is 70db during the summer season (June
1 – Labor Day). The noise limit at all other times is 80db. All activities generating noise
in excess of the aforementioned limits will require a noise suppression plan and be
restricted to operating between 9:00am – 5:00pm Monday through Friday. All
construction equipment shall be adequately muffled and maintained to minimize project
noise. The installation of noise barriers is the minimum technique to suppress noise,
especially when jack hammering of concrete occurs.
11.1 Noise Suppression Plan
Since this is an interior remodel, we do not anticipate that noise will be much of
an issues. We understand that any activity that generates noise in excess of the limits
mentioned in 11.0 above will require a noise suppression plan and is restricted to
operating between the hours of 9am and 5pm Monday through Friday. Please refer to
Appendix D – Noise Suppression Plan.
05/30/2019
970 923 3088
BRIKOR ASSOCIATES
20 Sunset Drive, Unit 1
Basalt, Colorado 81621
WWW.BRIKOR.COM
11.2 Equipment and Methods
In addition to the standard practices agreed to within the signed Noise
Suppression Plan, the table below from the City of Aspen’s complete packet has been
included for quick contractor/subcontractor reference.