ID Task Name Duration Start 1 Asbestos Abatement 12 days Mon 2/5/18 2 Permit Issued 1 day Wed 2/21/18 3 Demo - Interior 5 days Thu 2/22/18 4 New Framing 5 days Thu 3/1/18 8 Rough MEP 10 days Tue 3/6/18 7 Install Pocket Door Tracks 4 days Thu 3/8/18 5 Rough in Fireplace 2 days Fri 3/16/18 9 Inspections 1 day Tue 3/20/18 10 Insulation 2 days Wed 3/21/18 12 Inspections 1 day Fri 3/23/18 13 Hang & Tape Drywall 5 days Fri 3/23/18 6 Tile on Fireplace Wall 7 days Fri 3/30/18 20 Drywall Texture 10 days Fri 3/30/18 21 Tile Main Level 5 days Fri 4/13/18 15 Tile Master Bath 7 days Wed 4/18/18 14 Cabinets 4 days Fri 4/27/18 16 Tile Bath 2 4 days Fri 4/27/18 17 Counter Tops 10 days Thu 5/3/18 27 Base & Case 2 days Thu 5/3/18 11 Prime & 1st Coat 2 days Mon 5/7/18 19 Wood Floors 4 days Wed 5/9/18 18 Appliances 2 days Tue 5/15/18 28 Final MEP 3 days Tue 5/15/18 29 Carpet 2 days Fri 5/18/18 22 Touch-up Paint 2 days Tue 5/22/18 23 Construction Clean 1 day Thu 5/24/18 24 Work List 3 days Fri 5/25/18 25 Final Inspection 1 day Wed 5/30/18 26 Powder Puff Clean 1 day Thu 5/31/18 Asbestos Abatement 2/20 Permit Issued 2/21 Demo - Interior 2/28 New Framing 3/7 Rough MEP 3/19 Install Pocket Door Tracks 3/13 Rough in Fireplace 3/19 Inspections 3/20 Insulation 3/22 Inspections 3/23 Hang & Tape Drywall 3/29 Tile on Fireplace Wall 4/9 Drywall Texture 4/12 Tile Main Level 4/19 Tile Master Bath 4/26 Cabinets 5/2 Tile Bath 2 5/2 Counter Tops 5/16 Base & Case 5/4 Prime & 1st Coat 5/8 Wood Floors 5/14 Appliances 5/16 Final MEP 5/17 Carpet 5/21 Touch-up Paint 5/23 Construction Clean 5/24 Work List 5/29 Final Inspection 5/30 Powder Puff Clean 5/31 14 17 20 23 26 29 1 4 7 10 13 16 19 22 25 28 3 6 9 12 15 18 21 24 27 30 2 5 8 11 14 17 20 23 26 29 2 5 8 11 14 17 20 23 26 29 1 4 February 2018 March 2018 April 2018 May 2018 June 2018 Unit 3G (DRAFT) Page 1 10/12/1712/14/17