HomeMy WebLinkAboutFile Documents.58 Pitkin Way.0158.2019 (5).ARBKCONSTRUCTION MANAGEMENT PLAN Wing Residence 58 Pitkin Way, Aspen, CO 81611 Parcel ID: 273501407003 1.0 Background This Construction Management Plan (CMP) outlines and details the construction management measures that will be employed throughout the construction process located at 58 Pitkin Way, Aspen, CO 81611. This CMP is intended to address all items that are applicable to the scope of work in said project. Where items are not applicable to the scope of work, the CMP will note this. The provided CMP will outline supplemental information along with its location when addressed in the attached appendices. 2.0 Project Introduction 2.1 Project Location- Project is located at 59 Pitkin Way, Pitkin Reserve Lot #3 Plus 1/3 Interest in Lot #7, City of Aspen, County of Pitkin, State of Colorado. See Appendix A for a Detailed Project Vicinity Map. 2.2 Disturbance Area- 2,712 sq ft or .062 acres 2.3 Description of work- The scope of work will include all that is necessary for the replacement of the existing snowmelted driveway. Project duration is estimated at five weeks from acceptance of Building Permit until Close-out. No utility connections will be added or altered through this scope of work. Construction waste will be hauled off via Haul/Emergency Access Map to the Landfill for disposal and recycling. See Appendix B. 3.0 Project Documentation 3.1 Permits- A. Building Permit- Please reference the permit application B. MEP Permits- Please reference the permit application 3.2 Public Notification- A letter shall be sent to all neighbors within 300 feet of the Project no less than ten days prior to construction. Due to the short duration of the project, no additional updates shall be required prior to Project completion. Notice is to identify any traffic/pedestrian concerns and to outline hauling/staging operations. A pre-construction meeting between the Site Supervisor and all Sub-Contractors shall occur ten days prior to construction with all impacted stakeholders to be notified as well. 3.3 Project Sign- See Proposed Sign - Appendix C 3.4 Project Contacts- Contractor: Structural Associates Co. 4185 County Rd. 154 Glenwood Springs, CO 81601 Project Manager: Brian Hanlen (970) 945-0147 Office 06/20/2019 I spoke with Greg Cissell, site supervisor, about a few issues. He is aware of work hours. Concrete demo to not start before 9 AM due to noise. Notify neighbors before concrete pour for traffic issues. PH 7/5/19 APPROVED WING RESIDENCE CONSTRUCTION MANAGEMENT PLAN Site Supervisor: Greg Cissell Structural Associates Co. 4185 County Rd. 154 Glenwood Springs, CO 81601 (970) 379.6574 Mobile Safety Officer: N/A (Contact Site Supervisor) Traffic Officer: N/A (Contact Site Supervisor) Erosion Control: N/A (Contact Site Supervisor) 4.0 Project Implementation: 4.1 Dates of Construction- Currently anticipating construction duration from July 22nd, 2019 to August 26th, 2019. 4.2 Hours of Construction- Will be limited to Monday through Friday 7:30 a.m. to 7:00 p.m. 9:00 a.m. through 5:00 p.m. Saturdays, with no work permitted on Sundays and federally designated holidays and other construction limitations set by the City of Aspen. Constructions activities producing noise greater than 80 decibels are limited to the following days and times: Monday thru Friday 9:00 am to 5:00 pm. 4.3 Sequence of Construction- See Appendix D- Project Schedule 4.4 Adjoining Property Owners- Adjacent properties will be protected from onsite runoff by silt fencing and straw waddles. Notification of all foreseen disturbances will be communicated to adjacent neighbors by the Site Supervisor. All notices will be made prior to the initiation of any such disturbances; this includes but is not limited to: noise disturbances, hauling/staging, Right of Way limitations/disruptions. 4.5 Project Fencing- Construction boundary fencing and silt protection to be installed in accordance with details contained within civil drawings and layout as shown on Construction Site Management Plan in Appendix E. 4.6 Natural Environment- No adverse effects on the nearby, natural environment are anticipated. Any unforeseen environmental impacts will be promptly mitigated by Structural Associates’ management team and controlled in accordance with the City of Aspen’s building regulations. No trees shall be removed and any that are adjacent to disturbance area(s) to be protected / fenced. 5.0 Project Management: 5.1 Parking Management- All parking to be contained on site as designated in Appendix E. 5.2 Emergency Vehicle Access- Emergency vehicle access will not be affected by the scope of work identified in this CMP. See Appendix B- Haul/Emergency Access Map 06/20/2019 Allowable work hours are 730-530 M-F. WING RESIDENCE CONSTRUCTION MANAGEMENT PLAN 5.3 Parking Details- Public transportation and carpooling efforts will be made to reduce the amount of onsite parking required for construction. See Appendix E. 5.4 Staging Areas- Designated staging area(s) will be located within property boundary. 5.5 Construction Trailer, Materials Storage, and Waste Management- Due to the small nature of this project, no jobsite office will be required on-site. Material storage will be reserved to on-site. A small dumpster will be located on-site. Due to the scope and short duration the existing recycling and bear proof (home owner’s) trash receptacles will be utilized for any food waste. One portable restroom will be available for workers. See Appendix E. 6.0 Traffic Control 6.1 General- All required traffic control shall be performed by on-site supervisory staff. Professional Traffic Control Companies will be contracted as required. 6.2 Haul Routes- See Appendix B- Haul/Emergency Access Map 6.3 Delivery requirements- No affect on any public roads will occur as a result of the scope of work identified in this CMP. Due to staging limitations, only (1) delivery will be permitted at any one time. Delivery schedule shall fall within the general project hours of 7:30 to 5:30 Monday through Friday. No idling of delivery vehicles will be permitted for longer than five minutes. 6.4 Traffic Control Plan- All construction related traffic shall be controlled and maintained by the on-site Supervisor as outlined in the Haul/Emergency Access Map. See Appendix B 7.0 Pedestrian Protection 7.1 General- All construction activity will comply with safety per MUTCD chapter 6D, the Americans with Disability Act, and IBC Chapter 33. 8.0 Sediment and Erosion Control 8.1 See protections as described in Appendix E with details provided in the civil drawings. 9.0 Fugitive Dust Control 9.1 Fugitive Dust Control Plan- All fugitive dust will be controlled by watering as required. 10.0 Emissions 10.1 General- All onsite vehicles/equipment will be maintained to manufacturer’s specifications. 10.2 Diesel Engines- Emissions from diesel powered engines shall have an opacity of no darker than 40% except for ten seconds during start up. 11.0 Noise Suppression 11.1 General- All construction activity shall comply with the City of Aspen’s noise limitations. 06/20/2019 WING RESIDENCE CONSTRUCTION MANAGEMENT PLAN Appendices: Appendix A: Project Vicinity Map Appendix B: Haul/Emergency Access Map Appendix C: Project Sign Appendix D: Project Schedule Appendix E: Construction Site Management Plan 06/20/2019