1.0 General
950sq.ft of interior space renovated.
Table of Contents
2.0 Project Introduction
2.1 Total project disturbance area roughly 950sq.ft
2.2 Project vicinity map is included
2.3 The project is located at 1039 E Cooper Ave, Chateau Roaring Fork Unit 24 facing the River.
Ii is a 2bedrooms/ 2bath apartment. The owners would like to update the unit by changing flooring,
plumbing fixtures and cabinets. We are also opening an existing closet towards Bedroom 2
3.0 Project Documentation
3.1 At the time of this CMP no permits have been issued.
3.2 Indicate project notification per CMP Manual for all properties within 300ft.
3.3 Project Sign will be placed on the unit windows .
3.4 Contact list included for: This information is also listed on A0.1 cover page of the plans
Owner
MILANO MARY J & MICHELANGELO A
315 RICHMOND RD
KENILWORTH, IL 60043
Contractor Lester Development – 970.424.1001
Site supervisor Tom Lester – 970.424-1001
Safety officer Elsa Lapeze – 970.424-1001
4.0 Project Implementation
4.1 Dates of construction ____________ fall 2017
4.2 Hours of construction __7:30 am to 5:00 pm Monday to Friday and Saturday 9am to 5pm
4.3 Construction schedule:
Demolition: _____ (10 days)
Inside remodel: _______ (180days)
4.6 Site map is provided
5.0 Project Management
5.2 Read Emergency vehicle access.
We, Lester Development (General Contractor) will maintain continuous emergency vehicle access, on
and around site, including but not limited to police, fire and ambulance services. This includes projects
adjacent to roads and alleys.
5.4 Map showing location of:
Staging ___on property ______
Trailer _______N/A_________
Materials ______inside ________
Waste management _____N/A_________
Recycling – Bear Proof for domestic – No commingle of trash
6.0 Traffic Control
6.4 Specify delivery vehicle:
Maximum number of deliveries at a time ___2_______
8/25/17
Hours of deliveries ____7:30 am to 5:00 pm__________
Exceptions to delivery schedule ___Holidays & high traffic times – Lester Development
will contact engineering if necessary.
8.0 Sediment and Erosion Control
9.0 Fugitive Dust Control
10.0 Emissions
10.1 Assure proper vehicle maintenance
10.2 Opacity – no darker than 40%
11.0 Noise Suppression
11.2 Read the Noise controls and reduction plan. This job site will require the use of excavator,
backhoe, and concrete pump. Lester Development will remind and require laborers and sub-contractor
about construction noise policy and requirements.
Hours: 9am to 5pm Monday to Friday for all activities exceeding 80 decibels.
8/25/17