HomeMy WebLinkAboutFile Documents.1039 E Cooper Ave.0226.2017 (7).ARBK
ELEMENT ENVIRONMENTAL | Lester 042717 CRF
1
Client Job Name
Chateau Roaring Fork
Property Address
1039 E. Cooper #24
Aspen, CO 81611
TABLE OF CONTENTS
1.0 - Scope of Work
2.0 - Sampling Requirements
3.0 - Sampling Methodology
4.0 - Laboratory
5.0 - Suspect Materials Sampled
6.0 - Table of Results
7.0 - Description of Sampling Area
8.0 - Conclusion
- Lab Report
- Certifications
TOTAL SAMPLES ANALYZED: 7
SAMPLES >1% ASBESTOS: 4
Asbestos Sampling Report
Date: 05/04/2017
Date of Inspection: 04/27/2017
Client:
Lester Development
PO Box 11347
Aspen, CO 81612
Attn:
Tom Lester
Building Inspector:
Joshua Johnson
CDPHE #18401
189 County Rd. 135
Glenwood Springs, CO 81601
josh@elementenv.co
(970)274-3139
8/25/17
ELEMENT ENVIRONMENTAL | Lester 042717 CRF
2
_____________________________________________
1.0- This was an inspection for suspect ACM (Asbestos Containing Material) for a remodel.
Element Environmental conducted a visible inspection for visible materials that would
be impacted during the remodel. This inspection was limited to the areas found in the
Description of the Sampling Area 7.0. Although sampling is destructive in nature, this
was a non-invasive inspection. It was of materials that were accessible. If other suspect
materials become visible/apparent during demolition or construction activities, work in
that area should be halted and more sampling/testing must take place, per Colorado
regulations. Any suspect materials that were not tested are to be assumed to contain
asbestos.
2.0- A limited bulk sampling of from all suspect materials was conducted in accordance with
Colorado State Requirements. The minimum number of samples per homogenous areas
are as follows:
2.1- Surfacing Materials- >1,000 sq.ft.- Minimum of 3 samples
1,000 sq.ft.- 5,000sq.ft.- Minimum of 5 samples
>5,000 sq.ft. Minimum of 7 samples
2.2- Miscellaneous materials- Minimum of 1 sample
2.3- Thermal Systems Insulation (TSI)- Minimum of 3 samples
3.0- The purpose of the inspection is to identify materials that are homogenous. A
homogeneous area is defined as one which shares suspect material, texture, color,
location, and/or apparent time of construction. The materials are segregated into
separate homogenous areas. The size is determined and then samples are taken. The
samples are taken in a random numerical sequence.
4.0- Josh Johnson, a Colorado Department of Public Health & Environment certified building
inspector, certification number: 18401, performed the inspection. Samples taken were
sent to CEI Labs in Cary, North Carolina. The samples were analyzed by PLM (Polarized
Light Microscopy) analysis. Per the CDPHE Regulation any sample that is found by a lab
to be trace, or <1% asbestos, is considered to be ACM material. This material would still
be a regulated material by CDPHE. The sample most have an additional “point count”
performed to be considered less than 1% and not be regulated by the CDPHE. The lab’s
documents with analyses and findings are found below.
8/25/17
ELEMENT ENVIRONMENTAL | Lester 042717 CRF
3
5.0- SUSPECT MATERIALS SAMPLED
• Texture
• Drywall
• Tape
• Joint Compound
6.0- TABLE OF RESULTS
HOMOGENOUS
AREA
DESCRIPTION OF AREA CATEGORY
&
FRIABILITY
NUMBER OF
SAMPLES
APPROXIMATE
SQ.FT.
% AND TYPE OF
ASBESTOS FOUND
(A) Stomp Texture throughout
the unit
S /Y 5 ~2,500 sq.ft. 3% Chrysotile in 4 of 5
samples
(B) Vinyl Flooring in the Kitchen M /N/A 2 ~100 sq.ft. No Asbestos detected
Key:
S- Surfacing
M- Miscellaneous
T- Thermal Systems Insulation
N- No
Y- Yes
N/A- Not Applicable
7.0- DESCRIPTION OF SAMPLING AREA
• The interior of the unit would be undergoing a complete remodel
8/25/17
ELEMENT ENVIRONMENTAL | Lester 042717 CRF
4
8.0- CONCLUSION
• The Texture throughout the unit was found to contain asbestos.
This material become friable when it is removed. If this material is to be disturbed or removed, the
material MUST be remediated in accordance with the CDPHE Regulation No. 8 by a licensed abatement
contractor. For residential projects over 32 sq.ft. of surfacing material, 50 linear feet of pipe insulation, or
55 gallon drum of waste, and for commercial project with 160 sq.ft. of surfacing material, 260 lineal feet
of pipe insulation, or a 55 gallon drum of waste a permit is required. The permit is through the CDPHE.
Along with the permit a final air clearance is required by a certified Air Monitoring Specialist. For projects
over 3,000 sq.ft a Project Design and Project Manager is required. Element Environmental is certified and
can perform Final Clearances, Project Design, and Project Management if required. All work performed
MUST follow all EPA, State Regulation 8, and OSHA regulations to protect the general public, the client,
and the workers.
Josh Johnson,
8/25/17
ELEMENT ENVIRONMENTAL | Lester 042717 CRF
5
8/25/17
ELEMENT ENVIRONMENTAL | Lester 042717 CRF
6
8/25/17
ELEMENT ENVIRONMENTAL | Lester 042717 CRF
7
8/25/17
ELEMENT ENVIRONMENTAL | Lester 042717 CRF
8
8/25/17