MEMORANDUM
Project: 21833.00 – 0039-2019-ARBK
Subject: IFFR for 1001 E Cooper – Unit 2
Date: 11 April 2019
Demo Narrative
1001 E Cooper is undergoing an interior remodel of both levels. Full gut of kitchen and all bathrooms.
Some layout changes to upper level.
While we answer the comments from zoning and the building department, we would like to request an
IFFR to start some demo and investigation of the existing conditions beyond the drywall.
The remodel has structural and floor plan changes but we will only be removing interior finishes such
as drywall, existing flooring, plumbing fixtures, kitchen appliances and millwork.
NO STRUCTURAL MEMBERS OR STUDS WILL BE TOUCHED UNTIL FULL PERMIT IS ISSUED.
04/16/2019
04/
1
6
/
2
0
1
9
joh
n
b
Per City IFFR Policy:
- No studs or other structural material may
be altered as a part of this permit.
-Pre-work, mid-progess, and final
inspections are required.