HomeMy WebLinkAboutFile Documents.800 S Mill St.0123.2018 (6).ARBKCONSTRUCTION MANAGEMENT PLAN 800 SOUTH MILLS STREET #7 ASPEN CO 81611 DAVID MILLER ASPEN CONSTRUCTION INC PO BOX 4446 ASPEN CO 81612 MARCH 1, 2018 CONTACT LIST: OWNER: 800 MILL 303 LLC CONTRACTOR: ASPEN CONSTRUCTION INC. 970 920-3960 PROJECT MANAGER: DAVID MILLER 970 379-9331 EMERGENCY ASSISTANCE 911 911 LOCAL HOSPITAL ASPEN VALLEY HOSPITAL 970 920-1120 ELECTRICITY: HOLY CROSS ELECTRIC 970 945-5491 WATER: CITY OF ASPEN WATER 970 920-5110 SEWER: ASPEN CONSOLIDATED 970 925-3601 NATURAL GAS: BLACK HILLS ENERGY 800 694-8989 POISON CONTROL AAPCC 800 222-1222 NON-EMERGENCY ASPEN COMMUNICATIONS 970 920-5400 UTILITY LOCATOR UNCC 811 04/26/2018 Aspen Construction, Inc. page 1 of 6 800 Mill 7 LLC CMP March 1, 2018 Construction Management Plan 800 S. MILL ST. #7 Aspen CO 81611 1.0 General 1.1 Disturbance 1.1.1 Total square footage of soil disturbance is 0 sf 1.1.2 Total square footage of building renovation is 1,072 sf 1.2 Table of Contents 1.2.1 Per Construction Management Plan Requirements Manual (April 2016) the total soil disturbance is less than 1,000 SF, however the building renovation is greater than 400 SF. Therefor a Construction Management Plan is required for this project. 2.0 Project Location 2.1 Disturbance area 2.1.1 Disturbed area shall be a total of 0 sf 2.1.2 No new structural elements to be incorporated into the existing building 2.1.3 No new exterior modifications to be incorporated into the existing building 2.2 Project Vicinity Map 04/26/2018 Aspen Construction, Inc. page 2 of 6 800 Mill 7 LLC CMP March 1, 2018 2.3 Description 2.3.1 The project scope of work consists of an interior remodel of existing bedrooms, bathrooms and Kitchen area. Minor interior partition wall renovation with the addition of new interior doors, fixtures and finishes. 2.3.2 No exterior walls are being moved. No new penetrations to the exterior walls or roofs. Two window sashes shall be replaced with operative openings for increased natural air flow. 3.0 Project Documentation 3.1 Permits 3.1.1 A #1 Building Permit is submitted. All trade permits will be submitted by licensed subcontractors. 3.1.2 No permits have been issued to date 3.1.3 Homeowner Association Compliance Policy has been signed by Owner 3.1.4 Zoning Compliance Verification Policy has been signed by General Contractor 3.2 Public Notification 3.2.1 Notification of neighbors within 300 feet shall be distributed via USPS by the design team/Owner 3.3 Project Sign 3.3.1 Project Signage shall comply with Appendix A: Required Construction Sign of the CMP Requirements Manual 2016 3.4 Contact Designation 3.4.1 Owner: 800 Mill 303 LLC 3.4.2 Contractor: Aspen Construction Inc: 970 920-3960 3.4.3 Project Manager: David Miller: 970 379-9331 4.0 Project Implementation 4.1 Dates of Construction Construction is estimated to begin April 15, 2018 and be completed June 30, 2018 4.2 Hours of Construction Hours of construction shall be limited to the hours allowable by the city of Aspen outside of the CRA and Central Core areas as defined in Appendix E: Core and Central Resort Area Map of the CMP Requirements Manual 2016. 4.3 Sequencing of Construction See attached Construction Schedule 04/26/2018 Aspen Construction, Inc. page 3 of 6 800 Mill 7 LLC CMP March 1, 2018 4.4 Adjoining Properties Project shall comply with the adjoining properties policy 4.5 Project Fencing No project fencing shall be installed as this is interior only renovation. Noise suppression fencing is not required 4.6 Public Health and Welfare Public health and welfare shall be maintained during the entire construction project 4.7 Natural Environment 4.7.1 Project shall comply as to protect the natural environment 5.0 Site and Right of Way Management 5.1 Right of Way Management Plan There is no anticipated encroachment into the Right-of-way. 5.2 Read Emergency Vehicle Access and Ordinance 35 The Project shall maintain continuous emergency vehicle access on and around the site. 5.3 Construction Parking Details According to the City of Aspen Traffic Impact Analysis Guidelines the level of TIA is EXEMPT and does not require a TDM and MMLOS. 5.4 Staging Areas 5.4.1 Staging areas are indicated on the graphical CMP 5.4.2 Timing of excavation is April 1 – June 30 5.4.3 No tower crane is anticipated for this project 5.4.4 There is no anticipated encroachment into the Right-of-way 5.5 Right of Way Limitations There are no Right-of-way encroachments anticipated for this Project 5.6 Site Plan 5.6.1 See graphical CMP provided by the design team 5.6.2 No construction trailer is anticipated for this minor project 5.6.3 Extents of excavation are indicated on the Landscape Plan 5.6.4 No tower crane is anticipated for this project 5.6.5 On-site separation and recycling shall be performed on this project 5.7 Waste Management 5.7.1 See attached Waste Management Plan 5.7.2 Co-mingled materials and cardboard shall be separated on-site 04/26/2018 Aspen Construction, Inc. page 4 of 6 800 Mill 7 LLC CMP March 1, 2018 5.7.3 Food waste shall be contained in a bear-proof container 5.7.4 Concrete shall be transported separately 5.7.5 All litter and debris shall not scatter to adjoining properties 5.7.6 An on-site hazardous material spill cleanup kit shall be maintained during the project 6.0 Traffic Control 6.1 General Traffic control coordination and supervision are not anticipated during this project 6.2 Haul Routes All hauling from/to project shall comply with the City of Aspen designated routes 6.3 Onsite Vehicle Limitations There will be no oversized vehicles on the project at any time 6.4 Delivery Requirements 6.4.1 Hours of deliveries shall be in accordance with the City of Aspen Construction Schedule and calendar specific for this location 6.4.2 Only one delivery vehicle shall be allowed on the site at one time 6.4.3 Delivery and Heavy Duty Vehicles must have a visible sign on the vehicle indicating the contractors name and phone number 6.4.4 No idling is allowed for more than 5 minutes at the project 6.5 Traffic Control Plan A Traffic Control Plan is not anticipated for this project 7.0 Pedestrian Protection This project will not interfere with sidewalks as there are currently no sidewalks in the area 8.0 Sediment and Erosion Control This project has no soil disturbance and is not subject to Sediment and Erosion Control measures 9.0 Fugitive Dust Control With the limited nature of the excavation on this project, fugitive dust is not a concern. Any dirt that is transported onto the right-of-way shall be immediately cleared via hand broom. 04/26/2018 Aspen Construction, Inc. page 5 of 6 800 Mill 7 LLC CMP March 1, 2018 10.0 Emissions 10.1 General All vehicles and equipment shall be properly maintained to within manufacturer’s specifications 10.2 Emissions from Diesel Powered Engines All emissions from diesel powered engines shall have a density of no more than 40%. 11.0 Noise Suppression 11.1 General All construction equipment shall be adequately muffled and maintained to minimize noise 11.2 Noise Suppression Plan All activities on-site shall be performed so as to limit noise and shall comply with Appendix C of the CMP Manual 2016 11.3 Noise Limits and Suppression Requirements Project shall comply with the required decibel limitations at the property line during construction. All work performed that may approach the sound producing limitations shall not occur on weekends nor before 9AM on weekdays. No radios or music devices shall be used prior to 8AM. 11.4 Noise Level Measurements Noise levels are not anticipated to be high enough to require measurements 11.5 Continued Noise Monitoring Noise levels are not anticipated to be high enough to require continued monitoring 11.6 Specific Restrictions Related to Manufacturing On-Site There will be no noise related on-site manufacturing at this project 12.0 Enforcement 12.1 City Construction Mitigation Officer A City Construction Mitigation Officer (CMO) shall be assigned to this project by the City of Aspen 12.2 Corrective Action The City of Aspen shall enforce construction mitigation corrections as applicable by current codes and adoptions 04/26/2018 Aspen Construction, Inc. page 6 of 6 800 Mill 7 LLC CMP March 1, 2018 12.3 Inspection Reports CMO shall complete construction inspection reports and shall keep as public at the City Engineering Department 13.0 Construction Mitigation Committee The Construction Mitigation committee shall review exemptions sought by projects and make determinations as deemed appropriate. 14.0 Appeal Process Appeals shall be forwarded to the City Manager for exemptions 04/26/2018