Ventilation Report –
Mountain Forge Tenant Relocation to 625 E Hyman Units 103 & 104
This report is intended to verify compliance of ventilation air requirements in the 625 E Hyman
Units 103 & 104 for the new tenant being relocated from the Mountain Forge building. The
information included is based on previous mechanical designs for units 103 & 104 and the
currently installed fan coils and planned outside air airflows. To verify compliance, actual
airflows should be tested in the field.
OUTDOOR AIR VENTILATION
ROOM
ROOM
SIZE
(SQ.FT.)
DENSITY
(# / 1000
SF)
#
PEOPLE
CFM/
PERSON
CFM/
SF
O.A
REQUIRED
(CFM)
O.A.
PROVIDED
(CFM)
UNIT 103
OFFICE 528 5 3 5 0.06 47
CONFERENCE
ROOM 114 50 6 5 0.06 37
HUDDLE 108 5 1 5 0.06 11
TOTAL (FROM EXISTING FC-12): 95 240**
UNIT 104
82 30 3 5 0.06 20
LOUNGE 71 30 3 5 0.06 19
MAIN OFFICE
SPACE 365 5 2 5 0.06 32
CONFERENCE 122 50 7 5 0.06 42
OFFICE 72 5 1 5 0.06 9
OFFICE 56 5 1 5 0.06 8
PHONE BOOTH 32 5 1 5 0.06 7
TOTAL (FROM EXISTING FC-13): 138 280
*AIR VOLUME REQUIREMENTS BASED UPON LARGEST REQUIREMENTS LISTED IN TABLE 403.3.1.1 OF 2015 IMC
**BASED ON 40% OF AIR FLOW FROM FC-12 SERVING THIS SPACE & 585 CFM TOTAL PREVIOUSLY PLANNED OUTSIDE AIR
TO THE UNIT