HomeMy WebLinkAboutFile Documents.601 E Hyman Ave.0022.2017 (13).ARBKG.F.Woods Construction
430 E Hyman Ave
Aspen, CO 81611
970-544-1833 office / 970-948-6483 cell
VICTORIAN SQUARE PENTHOUSE
601 E. Hyman Ave.
Aspen, CO 81611
Construction Management Plan_______________________________________
To:City of Aspen Building Department
130 South Galena
Aspen, Co 81611
From: Greg Woods, President
G.F. Woods Construction Inc.
430 E. Hyman Ave
Aspen, CO 81611
970-544-1833
Received
4/25/2017 2:45:26 PM
G.F.Woods Construction
430 E Hyman Ave
Aspen, CO 81611
970-544-1833 office / 970-948-6483 cell
TABLE OF CONTENTS
2.0 Project Introduction
2.1 Project Disturbance Area
2.2 Project Vicinity Map
2.3 Project Description
3.0 Project Documentation
3.1 Permits / Other Documentation
3.2 Public Notification
3.3 Project Sign
3.4 Contact List
4.0 Project Implementation
4.1 Dates of Construction
4.2 Hours of Construction
4.3 Construction Schedule
4.5 Project Fencing
4.6 Tree Protection
4.7 Parks
5.0 Project Management
5.1 Parking Management
5.2 Emergency Vehicle and Ordinance 35
5.3 Construction Parking Details
5.4 Staging Areas
5.5 Right of Way Limitations
5.6 Construction Trailer, Material Storage, And Waste Management
6.0 Traffic Control
6.2 Haul Routes
6.3 Weight and Size Limitations of Vehicles
6.4 Delivery Requirements
6.5 Traffic Control Plan
8.0 Sediment and Erosion Control
8.1 Storm Water Pollution Prevention Plan
8.2 BMPs for Stormwater Pollution Prevention
8.3 Final Stabilization and Long-Term Stormwater Quality
8.4 Inspection and Maintenance Procedures
9.0 Fugitive Dust Control
9.1 Dust Control Plan
Received
4/25/2017 2:45:26 PM
G.F.Woods Construction
430 E Hyman Ave
Aspen, CO 81611
970-544-1833 office / 970-948-6483 cell
10.0 Emissions
10.1 Maintenance
10.2 Opacity
11.0 Noise Suppression
11.1 General
11.2 Noise Suppression Plan
11.3 Equipment and Method
ATTACMENTS
A – Project Vicinity Map
B – Project Sign
C – CMP Site Plan
D – Ordinance No. 35
E – Construction Waste Management Plan
F – Haul Route Map
G – Engine Idling Policy
Received
4/25/2017 2:45:27 PM
G.F.Woods Construction
430 E Hyman Ave
Aspen, CO 81611
970-544-1833 office / 970-948-6483 cell
2.0 PROJECT INTRODUCTION
2.1 Project Disturbance Area
The area of disturbance for the scope of work on the Victorian Square
Penthouse project is limited to an interior build out focusing on a finish work scope and
minimal metal stud nonstructural framing, and will not require any ROW work. Vehicle
material and equipment staging will be necessary along Hunter St. and Hyman Ave.
2.2 Project Vicinity Map
See Attachment A – Project Vicinity Map
2.3 Project Description
The scope of construction will consist of a spec residential development
within the completed Victorian Square core and shell building. This affects the top
floor of the building, which is a total of 1,806SF of net livable space including deck
area making up the 3rd floor penthouse space. This will include metal stud framing,
minimal plumbing electrical and HVAC additions to the space, and an extensive finish
scope of work thorough out the penthouse space. This scope is limited to the 3rd floor
penthouse space, the basement storage space attached to the penthouse purchase,
and any coinciding work to the entire core and shell building to achieve a certificate of
occupancy for this residential space.
3.0 PROJECT DOCUMENTATION
3.1 Permits / Other Documents
This CMP is being submitted as part of the application for a building permit.
Asbestoses abatement will not be necessary as this is a new building with no existing
sheet rock on the 3rd floor. The plan sets being submitted for permit include all applicable
City of Aspen approvals.
3.2 Public Notification
A project update will be provided to the neighboring business managers and
property owners periodically prior to relevant impacts of construction on the
surrounding properties. Neighboring property owners will be notified prior to any crane
mobilizations or traffic/ pedestrian encroachments.
Received
4/25/2017 2:45:27 PM
G.F.Woods Construction
430 E Hyman Ave
Aspen, CO 81611
970-544-1833 office / 970-948-6483 cell
3.3 Project Sign
See Attachment B – Project Sign
3.4 Contact List
Owner:
Contractor: GF Woods
Construction –
970.544.1833
Site Supervisor: Jim
Barnett –
970.379.9009
Safety Officer: Jim
Barnett –
970.379.9009
Traffic Control: GF Woods Construction – 970.544.1833
Erosion Control Representative: Eric
Wynne – 970.319.6938
City of Aspen: 970.920.5000
Pitkin County: 970.920.5200
Fire Department (Non-
Emergency):
970.925.2690 Roaring
Fork Transit Authority:
Aspen School District:
970.925.3760 Aspen
Water Department:
970.920.5110
Aspen Consolidated Sanitation
Department: 970.544.6823
Aspen Electric Department:
970.920.5148
Century Link
(Telephone Company):
877.781.7449 Comcast
(Cable TV):
800.934.6489
Aspen Valley Hospital: 970.925.1120
**********************For Emergencies Call
911**********************
Received
4/25/2017 2:45:27 PM
G.F.Woods Construction
430 E Hyman Ave
Aspen, CO 81611
970-544-1833 office / 970-948-6483 cell
4.0 PROJECT IMPLEMENTATION
4.1 Dates of Construction
The current project start date is scheduled for August 1, 2017. This date is
predicated on the core and shell receiving their certificate of occupancy before any work
can begin on the penthouse build out. The estimated project duration is 7 months (7)
putting the projected completion date at around March 1st, 2017. Any work within the City
of Aspen Right of Way will not commence prior to obtaining the appropriate permits from
the City of Aspen Engineering Department
4.2 Hours of Construction
GF Woods construction understands that construction hours are limited to
7:30am – 5:30pm Monday through Friday and 9am – 5pm on Saturday. GF Woods
further understands that no construction is permitted on Sundays, 4th of July day and/or
weekend if it falls on a Friday or Monday, Memorial Day and Labor Day weekends,
Thanksgiving Day, Christmas Day, and New Year’s Day. GF Woods further
acknowledges the following restrictions:
During Presidents Day:
Projects located in the Central Resort Area (CRA) are not permitted to work on
any exterior elements, however interior work may be permitted with prior
approval.
Projects outside the CRA will be permitted to work.
During the Christmas week
Projects located in the Central Resort Area (CRA) are not permitted to work on
any exterior elements, however interior work may be permitted with prior
approval.
Projects outside the CRA will be permitted to work.
During Holiday Season:
Holiday Season is defined as the days of the week leading up to Christmas until
New Year’s Day. Refer to Appendix J for Holiday Season dates.
Projects located in the Core are not permitted to work on any exterior
elements, however interior work will be permitted.
During the Food & Wine Festival in June (Friday thru Saturday):
Projects located in the Central Resort Area (CRA) are not permitted to work
projects outside the CRA will be permitted to work.
GF Woods understands that specific indoor activities during restricted periods
may be permitted with approval from the City of Aspen Engineering Department and that
specific conditions will be applied to each project separately. During the off-season 24
hour a day interior work may be permitted within the CRA. If GF Woods wishes to work
24 hours a day, GF Woods will present a work plan to the City of Aspen Engineering
Received
4/25/2017 2:45:27 PM
G.F.Woods Construction
430 E Hyman Ave
Aspen, CO 81611
970-544-1833 office / 970-948-6483 cell
Department and agrees not to work outside of the normal construction hours unless
approved by the city.
GF Woods understands that additional restrictions on construction hours and
encroachments may be necessary for Special Events such as the USA Pro Cycling
Challenge and the Farmer’s Market.
GF Woods understands that additional restrictions on construction hours may
also be necessary due to the project’s specific impacts on adjoining properties which
may include limiting work during sales events (for a maximum of two sales events per
year), maintaining site lines to adjoining businesses, and providing signage on the
construction site advertising the adjacent business.
4.3 Sequence (Phasing) of Construction
This project will run continuously for seven months and will be phased starting
with rough framing, transitioning into rough in work, followed by finish work, concluding
with detail and trim out work in the interior space and minor work to the exterior deck
space.
4.4 Adjoining Properties
GF Woods understands and agrees that no person shall excavate on land close
enough to a property line to endanger any adjacent public street, sidewalk, and alley,
other public or private property, or easement, without supporting and protecting the
property from any damage that might result from construction operations.
GF Woods will coordinate with businesses operating on adjoining properties
and will work with said businesses to help mitigate construction impacts. This will
include identifying adjacent businesses and understanding what events (such as sale
events) and programs that neighboring businesses have scheduled throughout the
year. GF Woods will work with the adjoining properties to mitigate impacts to their
events and programs. This will include maintaining sight lines to adjacent businesses
as necessary.
Adjacent businesses include:
Native Roots 429-4443
Zane’s Tavern 544-9263
Little Ollie’s 544-9888
Gonzo Gallery 510-0656
Received
4/25/2017 2:45:27 PM
G.F.Woods Construction
430 E Hyman Ave
Aspen, CO 81611
970-544-1833 office / 970-948-6483 cell
4.5 Project Fencing
During the duration of the project, the ROW access around the build will be kept
passable and will not require any construction fencing to be implemented on this project
for any extended period. If pedestrian traffic needs to be redirected, a moveable
construction fence could be erected to help contain the flow of pedestrian traffic for safety
purposes. The fence will be eight feet (8') in height and constructed out of chain-link
fence with mesh windscreens.
4.6 Public Health and Welfare
This construction management plan was devised to protect and respect the
public health and welfare.
4.6 Natural Environment
There will be newly planted trees along Hyman and hunter that will require
protection on an as need basis. Whenever there may be a risk to the trees, say during
temporary product staging or large material delivery and placement, a visible protection
fence will be erected to surround the tree at the drip line.
5.0 SITE AND RIGHT OF WAY MANAGEMENT
5.1 Right of Way Management Plan
See Attachment C – CMP Site Plan
5.2 Emergency Access and Ordinance 35
GF Woods will maintain continuous emergency vehicle access on and around
the site, including but not limited to police, fire, and ambulance services.
See attachment D; Ordinance # 35
5.3 Construction Parking Details
The Victorian Square project will minimize the number of vehicles traveling
to the site by taking the following measures:
Traffic Demand Management Plan:
1.Carpool Program – GF Woods will require its employees and
employees of its subcontractors to form carpool groups of two or more
adults to reach the worksite. These carpools will originate no further up
valley than the Brush Creek Intercept Lot. GF Woods will keep copies of
carpool passes issued to said carpools for inspection by the city.
2.One Company Vehicle per Subcontractor – GF Woods will include a
provisions in its subcontracts for this project requiring that each
subcontractor bring only one company vehicle per day into the City of
Aspen for work related to the Victorian Square project.
Received
4/25/2017 2:45:27 PM
G.F.Woods Construction
430 E Hyman Ave
Aspen, CO 81611
970-544-1833 office / 970-948-6483 cell
GF Woods understands that no construction parking will be permitted
within the free two-hour residential parking areas without a valid permit
5.4 Staging Areas
The Victorian Square project does not have an alleyway directly adjacent to the
property but GF Woods will try to use the alley south of Little Ollie’s for short term staging
whenever possible. On site staging of materials will be designated to certain staging
zones listed on the Site Plan Attachment; C
The number of truckloads expected to and from the site are
estimated as follows:
Residential Deck Assemblies 3
Framing Materials 10
Finish Materials 20
Miscellaneous trucks 30
Total Trucks 63
GF Woods does not plan to use a tower crane for this project and will be
requesting that parking permits and/or ROW encroachment permits be granted so that a
mobile crane can be active in the diagonal parking spots on Hyman Avenue directly
adjacent to the building site. Crane picks will be essential to stage any material that will
not be able to be brought through a staircase or elevator. GF Woods plans on multiple
crane mobilizations to transport material from the street level to the deck space on the 3rd
floor. GF Woods understands that ROW encroachments are to be minimized and used as
a last resort in all cases. GF Woods understands that it shall obtain ROW encroachment
permits from the City Engineering Department before proceeding with said
encroachments.
5.5 Right of Way Limitations (Hunter an Orange Zone and Hyman a Yellow Zone)
GF Woods understands the Limitations for Encroachment Zones set forth in the CMP
Requirements Manual. GF Woods will adhere to said limitations as best as possible, however, since the
Victorian Square site doesn’t have direct access to an alleyway, we respectfully request that we be
allowed limited encroachment beyond what is provided by the guidelines and allowed safety closures of
Row zones periodically. Please refer to the attached CMP Site plan for the encroachments that are being
requested.
Received
4/25/2017 2:45:27 PM
G.F.Woods Construction
430 E Hyman Ave
Aspen, CO 81611
970-544-1833 office / 970-948-6483 cell
5.6 Construction Trailer, Materials Storage and Waste Management
A job trailer will not be mobilized for this project. The attached CMP Site
Plan shows the areas designated for job materials storage, portable restrooms, and
waste management and recycling containers.
GF Woods understands that loose job material storage is not allowed in ROW
under any circumstance. Temporary material staging and lay down may need
to take place in the parking spaces along Hunter St. and Hyman Ave.
GF Woods understands that it must submit a waste management plan to the
City prior to beginning demolition or construction. Due to space limitations it will not be
practical to sort materials for recycling on site. GF Woods will be relying on waste
receiving facilities and the companies receiving materials for recycling and salvaging
to uses their discretion and optimize recycling and reuse wherever possible.
See Attachment E – Construction Waste Management Plan
GF Woods further understands that:
1.Project must recycle co-mingled materials (plastics #1-#7, tin, aluminum, and glass).
2.Project must recycle cardboard.
3.GF Woods shall provide containers or bins for recycling these materials.
4.Project must comply with Colorado and Aspen landfill bans, i.e. no
disposal of electronic waste, fluorescent light bulbs, hazardous waste or
yard waste and that said banned materials shall not be disposed of in
the trash.
5.Any dumpster or other trash receptacle that is used for food refuse must be
constructed in such a manner as to render it bear proof and that all such
containers shall be adequately covered at all times until transferred to the
landfill.
6.It is unlawful to permit accumulated debris, litter, or trash on any
construction site to blow or scatter onto adjoining properties.
7.An onsite hazardous material spill cleanup kit is required, as specified by
the City Engineer, that contains, at a minimum, a 25 pound bag of Floor-
Dri (or equal), absorbent pads, and other spill kit materials.
Received
4/25/2017 2:45:27 PM
G.F.Woods Construction
430 E Hyman Ave
Aspen, CO 81611
970-544-1833 office / 970-948-6483 cell
6.0 TRAFFIC CONTROL
6.1 General
GF Woods understands that all traffic control operations shall be managed by
the designated certified traffic control supervisor and that traffic control plans are to be
submitted to and approved by the city prior to impacting auto or pedestrian traffic.
6.2 Haul Routes
See Attachment F - Haul Route Map
6.3 Onsite Vehicle Limitations
Since the proposed building covers most of the lot, there will be no “onsite”
vehicles. Acquisition of rental parking spaces on Hyman and Hunter will be necessary
for material delivery and essential construction vehicle parking. All vehicles bring
workers, materials and equipment to the site will comply with State of Colorado weight
restrictions.
6.4 Delivery Requirements
GF Woods Construction understands and agrees that:
1.Traffic control required for deliveries must be fully coordinated with the City of Aspen
Engineering Department.
2.Roads will not be closed under any circumstances, unless granted permission from the City
of Aspen Engineering Department.
3.Deliveries times will be coordinated so that only one large truck will be on site at any given
time.
4.Deliveries will only occur during permitted working hours which are 7:30am – 5:30pm Monday
through Friday and 9am – 5pm on Saturday.
5.Delivery and Heavy Duty Vehicles must have a visible sign on the vehicle that specifies the
project contractors name and phone number.
6.Delivery vehicles and all other onsite vehicles are not allowed to idle for more than five (5)
minutes, with the exception of generators or PTO type operations.
7.GF Woods will adhere to the city’s idling policy which is attached hereto as Attachment – H
See Attachment G – Engine Idling Policy
6.5 Traffic Control Plan
GF Woods or applicable subcontractor will submit a Traffic Control Plan (TCP)
as required prior to interfering with traffic on any public right-of-way. Any TCP will be
prepared by a State Certified Traffic Control Supervisor. The plan will conform to the
most current edition of the Manual of Uniform Traffic Control Devices for Streets and
Highways (MUTCD) and be submitted to the City of Aspen Department of Engineering
for approval/permitting.
Received
4/25/2017 2:45:27 PM
G.F.Woods Construction
430 E Hyman Ave
Aspen, CO 81611
970-544-1833 office / 970-948-6483 cell
The project is not located in a school area and does not interfere with any school
bus stops or school walk routes.
7.0 PEDESTRIAN PROTECTION
7.1 General
GF Woods will comply with pedestrian safety per City code 21.04.060, MUTCD
Chapter 6D, the Americans with Disability Act, and IBC Chapter 33. GF Woods
understands that Sidewalk closures in the core will not be permitted. Pedestrians must be
accommodated without having to cross the street. Short duration closures in the core may
be considered during the off-season.
8.0 SEDIMENT AND EROSION CONTROL
8.1 Storm Water Pollution Prevention Plan
This project will not engage in any scope of work that will affect the storm water
system and consequentially will not need a specific storm water management plan. If
the need arises, all necessary Best Management Practices (BMP’s) will be in place and
maintained in order to minimize dirt entering the streets. Primary strategies are as
follows:
Avoid unnecessary site disturbance.
Maintain grading; install silt fences and sediment traps prior to any soil disturbance.
The installation of a tracking pad will be impractical due to the limited space
available. GF Woods will make sure that the short ramp into the excavation
is kept as mud free as possible by use of screened rock over geo-textile
fabric and not using the ramp in wet conditions.
The washout of concrete chutes will have to be done back into the concrete
trucks due to the lack of space on site. GF Woods will do everything they
can to make sure that the concrete trucks do not wash out illegally offsite.
Hard plastic kiddie pools will be used to protect the ground below the
concrete pump transfer points. Spills captured will be allowed to dry and will
be placed in the site trash receptacle.
Pathways around the building will be stabilized primarily through the use of
screened rock over geo-textile fabric.
8.2 BMPs for Stormwater Pollution Prevention
Not applicable- interior renovation
Received
4/25/2017 2:45:27 PM
G.F.Woods Construction
430 E Hyman Ave
Aspen, CO 81611
970-544-1833 office / 970-948-6483 cell
8.3 Final Stabilization and Long-Term Stormwater Quality
Not applicable – interior renovation
8.4 Inspection and Maintenance Procedures
Not applicable – interior renovation
9.0 FUGITIVE DUST CONTROL
9.1 Dust Control Plan
Not applicable – interior renovation
Received
4/25/2017 2:45:27 PM
G.F.Woods Construction
430 E Hyman Ave
Aspen, CO 81611
970-544-1833 office / 970-948-6483 cell
10.0 EMISSIONS
10.1 Maintenance
GF Woods understands that all vehicles and equipment used on site
will be properly maintained such that the engines will function within the
manufacture’s standards or parameters.
10.2 Opacity
GF Woods Understands that emissions from diesel engines operated within the
City of Aspen shall be of a shade or density no darker than 40% opacity, except for
starting motion no longer than 10 seconds or for stationary operation not exceeding 10
seconds.
11.0 NOISE SUPPRESSION
11.1 General
GF Woods understands that projects located in the Core are limited to 70 dB at
the property line during the summer and winter season and 80 dB at the property line
all other times of the year. All construction equipment shall be adequately muffled and
maintained to minimize project noise. The installation of noise barriers is the minimum
technique to suppress noise, especially when jack hammering of concrete occurs.
11.2 Noise Suppression Plan
The Victorian Square Penthouse project will not require a specific noise
suppression plan due to the nature of the interior build out scope. The surround core and
shell building is expected to be adequate to suppress any excessive construction noise
and contain this within the property line. If the need arises noise suppression blanketing
will be implemented to contain noise to the required levels.
11.3 Continued Noise Monitoring
GF Woods will provide incremental as needed noise monitoring to assure we are
within the required decibel levels.
Received
4/25/2017 2:45:27 PM
9,027
1,504.5
Legend
1:
WGS_1984_Web_Mercator_Auxiliary_Sphere
Feet01,504.5752.25
Notes
Pitkin Maps & More
THIS MAP IS FOR INFORMATIONAL PURPOSES.
Pitkin County GIS makes no warranty or guarantee
concerning the completeness, accuracy, or reliability
of the content represented.
Map Created on 5:31 PM 08/27/15 at http://www.pitkinmapsandmore.com
State Highway
Road Centerline 9K
Primary Road
Secondary Road
Service Road
Rivers and Creeks
Continuous
Intermittent
River, Lake or Pond
Town Boundary601 E. HYMAN AVE.
ATTACHMENT A - VICINITY MAP
Received
4/25/2017 2:45:27 PM
Attachment B - Vic Square Jobsite SignPenthouse
Received
4/25/2017 2:45:27 PM
VICTORIAN SQUARE - 601 E. HYMAN - CMP SITE PLAN
ROLL OFF
DIAGONAL PARKING SPACES ON HYMAN AVE. IN FRONT OF BUILDING TO BE USED
PERIODICALLY FOR DELIVERY TRUCKS, MOBILE CRANES, AND TEMPORAY STAGING
PARELLEL SPACES ALONG HUNTER TOBE USE PERIODICALY FOR DELIVERYTRUCKS AND ROLL OFF PLACEMENTMaterial staging on
deck
Temporary staging
and crane landing
deck
Received
4/25/2017 2:45:27 PM
ATTACHMENT D - ORDINANCE 35
Received
4/25/2017 2:45:27 PM
Received
4/25/2017 2:45:27 PM
Received
4/25/2017 2:45:27 PM
Received
4/25/2017 2:45:27 PM
1
ATTACHMENT E - WASTE MANAGEMENT PLAN
CONSTRUCTION WASTE MANAGEMENT PLAN
Company Name:
GF Woods Construction
Contact Person: Greg Woods
Address:
P.O. Box 10493 Aspen, CO 81612
Telephone #: 948-6483
Project Location: 601 E. Hyman Ave.
Contractor:
GF Woods Construction
Contact Person: Greg Woods
Telephone #: 948-6483
Recycling Coordinators:
Contact Person:
Telephone #
Project Description:
GF Woods Construction
Jim Barnett
379‐9009
Tennant finish of the 3rd floor penthouse space of the Victorian Square building.
Waste Management Goals:
This project will recycle or salvage for reuse a minimum of 5 % by weight of the waste
generated on-site. This will be new construction focusing on finishes and we will be
conscientious in conserving materials.
Waste reduction will be achieved through building design, and reuse and recycling efforts will be
maintained throughout the construction process.
Waste Prevention Planning:
Compliance with Chittenden Solid Waste District’s (C.S.W.D.) mandatory recycling
requirements for businesses. C.S.W.D. mandatory recyclables include:
o newspaper
o corrugated cardboard
o white and colored office paper
o plastic and glass bottles and jars
o metal cans
Received
4/25/2017 2:45:27 PM
2
Compliance with C.S.W.D. and Pitkin County’s Landfill Bans, i.e. no disposal of tires,
appliances, yard waste, mandatory recyclables, hazardous waste, batteries, fluorescent tubes,
electronic waste and large metal items.
Project Construction Documents – Requirements for waste management which will be included
in all work. The General Contractor will contractually require all subcontractors to comply with
the C.S.W.D. mandatory recycling requirements.
The Construction Waste Reduction Plan shall be implemented and executed as follows and as
on the chart:
o Salvageable materials will be diverted from disposal where feasible.
o There will be a designated area on the construction site reserved for a row of
dumpsters each specifically labeled for respective materials to be received.
o Hazardous waste will be managed by a licensed hazardous waste vendor.
Received
4/25/2017 2:45:27 PM
3 1. Salvage YesNoDo you plan to salvage materials from this project prior to demolition or construction? X If YES, list the materials that will be salvaged (e.g., doors, windows, casing, toilets, sinks, fixtures, wood siding, tiles, etc.) Facility or Salvage company receiving material Receipt attached Y/N ? 1. 2. 3. 4. 5. 2. Source Separation YesNoDo you plan to source separate any materials for delivery to a recycling facility (e.g. separation of material such as wood, concrete, metal into separate bins) Materials HaulerFacilityWood Intermountain Waste & RecycleGlenwood Springs Metal Same Commingled Recyclables Same 3. On-Site Use YesNo XReceived 4/25/2017 2:45:27 PM
4 Do you plan any on-site reuse activities for this project (e.g. reuse of wood forms for concrete, on-site crushing of concrete for on-site use, use of reusable containers or pallets for material deliveries, etc.)? (please provide photos of locations these items were reused) If yes, please describe: 4. Disposal at landfill Will any materials be disposed of (not recycled or salvaged) at the landfill? Yes XNoEstimate the number of tons of material to be taken to the landfill for disposal: 1 ton of construction waste Received 4/25/2017 2:45:27 PM
E MAIN
S
T
W MAI
N
S
T
E DURA
N
T
A
V
E
E HOP
K
I
N
S
A
V
E
GI
B
S
O
N
A
V
E
E COO
P
E
R
A
V
E
W HAL
L
A
M
S
T
W BLE
E
K
E
R
S
T N THIRD STS ASPEN STW FRA
N
C
I
S
S
T
N FIFTH STW HOP
K
I
N
S
A
V
E N MILL STNORTH
S
T
N SIXTH STW SMU
G
G
L
E
R
S
T
N FOURTH STS MONARCH STPARK AVES MILL STR
E
D
M
T
N
R
D
N FIRST STS ORIGINAL STLAKE AVEN SECOND STS GARMISCH STLO
N
E
P
I
N
E
R
D
O
A
K
L
N
S HUNTER STS WEST END STE BLEE
K
E
R
S
T N SPRING STNEALE AVEVINE ST
S FIRST STSHADY LNMIDLAND AVEE HYM
A
N
A
V
E
S GALENA STGILLESPIE AVE
W HYM
A
N
A
V
E
DEAN
S
T
KIN
G
S
T
RI
O
G
R
A
N
D
E
P
LN EIGHTH STS SPRUCE STMA
P
L
E
L
N
PARK CIRN GARMISCH STRACE STE HALL
A
M
S
T
WATER
S
A
V
EN ASPEN STS THIRD STN SPRUCE ST
TEAL CTA
J
A
X
A
V
ENICHOLAS
LN
W COO
P
E
R
A
V
E
JUAN S
T WILLIAMS WYASPEN MTN
R
DPUPPY SM
ITH
ST
QUEEN ST
CLEVELAND STLACET LN
FOUN
D
E
R
S
P
L
A
C
E
C
O
T
T
O
NW
O
O
D
L
N
S RIVERSIDE AVEN SEVENTH STPEARL CT
SOUTH AVE
SUMMI
T
S
T
GILBE
R
T
S
TS FIFTH STS SIXTH STW NO
R
T
H
S
T
S FOURTH STS SPRING STN RIVERSIDE AVES SPRING STDEAN S
T S GALENA STN SEVENTH STP
A
R
K
C
I
R
DEAN S
TS MILL STASPEN MTN RDMap prepared by Engineering and GIS Department
City of Aspen, CO 81611 May 4,2007
0 600300
Feet
Legend
Designated Heavy Haul Route
Roads
Parcels
City Boundary
OFFICIAL HEAVY HAUL ROUTE MAP
601 E. Hyman Ave
ATTACHMENT G - HAUL ROUTE MAP
Received
4/25/2017 2:45:27 PM
ATTACHMENT H - ENGINE IDLING
Received
4/25/2017 2:45:27 PM