HomeMy WebLinkAboutFile Documents.555 E Durant Ave.0017.2019 (15).ACBK  6/12/2017    Page 1 of 28    IBC Building Submittal Guide      A description of permit requirements for Commercial, Multifamily, and Mixed‐Use  Buildings under the International Building Code                  6/12/2017    Page 2 of 28    Table of Contents Documents Planning Approvals ___________________3   Permit Applications & Contact Sheet _____3  Valuation Guidance __________________3  Fees _______________________________4  HOA Certification ____________________4  IBC Building Description Form __________4  Asbestos Questionnaire, Reports________4  State Demolition Approval Notice _______4  Fireplace Registration & Specs__________4  Energy Code Compliance ______________5  Non‐Vented Roof Assembly Calculations__8  U‐factor Fenestration Docs_____________9  CREMP/RREMP Documents____________9  Line Grade Verification Form__________10  Verification of Structural Integrity______10  Soils Report________________________11  Special Inspection Agreement_________11  Photos____________________________11  Unit/Building Relationship____________12      Drawings Drawing Standards__________________13  Cover Sheet _______________________13  Survey ____________________________14  Excavation/Earth Retention Plans ______14  Site Plan __________________________14  Renewable Energy Mitigation plan _____15  Area Sheet________________________15  Occupancy/Means of Egress Plan______16  Fire Resistance Plans/Details __________16  Accessibility Plans/Details ____________17  Floor Plans ________________________17  Roof Plan _________________________18  Elevations ________________________18  Sections __________________________19  Details ___________________________19  Stairs ____________________________20  Ramps ___________________________20  Fireplace Details ____________________20  Schedules _________________________21  Reflected Ceiling Plans ______________21  Lighting Plans _____________________21  Electrical Plans_____________________21  Commercial Kitchen Plans____________21  Mechanical Plans ___________________22  Plumbing Plans_____________________22  Structural Plans ____________________23  Additional Information Adopted Codes _____________________24  Design Criteria_____________________24  Fire Sprinklers______________________25  Carbon Monoxide Detectors __________25  Inspections ________________________25  Final Inspections____________________25  Permit Process: What to Expect________26    6/12/2017    Page 3 of 28    Documents Planning Approvals (1 copy) Check with the Planning Department to see if your project requires land use review. Any of the following  that are specific to your project must be submitted:  □ Resolutions  □ Decisions  □ Ordinances  □ Development Orders  □ Other Land Use Approvals  Permit Application & Contact Sheet Fill out the entire upper portion of the form.   ‐ Existing Sqft: Provide the Gross Floor Area (See Area Sheet section for definition) of the entire  unit or building as it exists.  ‐ Sqft this Permit: Provide the Gross Floor Area of the area where the scope of work will take  place.  ‐ Contractor: The permit must be signed by a contractor who is licensed with the City of Aspen.   An unlimited contractor’s license is required to construct new type I or II buildings. A light  commercial contractor’s license is sufficient for all other work.  ‐ Valuation: Enter the project valuation in the appropriate line on the Permit Application Form.  Per City Policy, the permit valuation shall include the total value of the work for which a permit  is being issued. This includes materials and labor for the permanent structure and mechanical,  electrical, plumbing and gas, fire sprinkler and elevator systems and equipment. Permanent  systems such as audio visual, lighting and HVAC controls are included in the total as are  expenses directly related to construction such as equipment rental and contractor fees.   Costs such as architectural and engineering design fees, landscaping and planting, tap fees,  development mitigation fees, trash removal and cleaning are not included.  It is the applicant’s responsibility to provide the valuation (109.3)  The valuation is ultimately  determined by the building official and documentation presented to the building official. Per  City Policy, the permit valuation shall include the total value of the work for which a permit is  being issued. This includes materials and labor for the permanent structure and mechanical,  electrical, plumbing and gas, fire sprinkler and elevator systems and equipment. Permanent  systems such as audio visual, lighting and HVAC controls are included in the total as are  expenses directly related to construction such as equipment rental and contractor fees. Costs    6/12/2017    Page 4 of 28    such as architectural and engineering design fees, landscaping and planting, tap fees,  development mitigation fees, trash removal and cleaning are not included.    Fees Fees will be due at submittal and at issuance. Contact a permit coordinator for an estimate at (970)920‐ 5090.  HOA Certification (1 copy) Form must be filled out and signed by owner.  IBC Building Description Form (1 copy) Fill out the form completely. If you do not know the type of construction, we may have it on file at the  Building Department.  Asbestos Questionnaire (1 copy) This must be filled out for all projects, regardless of the age of the building.  Asbestos test and clearance reports (1  copy)  If ‘yes’ is checked on the Asbestos Questionnaire, you must provide an asbestos test report. This must  include the following:  1. Inspector’s narrative including sampling locations  2. Inspector’s certificate  3. Lab data  If Asbestos is found and you will be disturbing it, you must submit a final air clearance asbestos  abatement report.  State Asbestos Demolition Approval Notice (1 copy) This is required if you are demolishing an entire building. One is required for each separate building,  including outbuildings. You must submit the original license, not a copy. The Asbestos Questionnaire has  information on how to acquire one.  Fireplace Registration and Specs (1 copy)   6/12/2017    Page 5 of 28    Fill out the Fireplace Registration Form for all fireplaces and fire pits existing and proposed associated  with the unit.  Provide the Manufacturer’s Installation Instructions for each gas fireplace. The following must be  included:  □ Firebox clearances   □ Flue/termination clearances  □ Firebox construction  □ Hearth Extension requirements  □ Exterior air requirements  □ Tight‐fitting door information  □ Damper/Flue sentinel information  Energy Code Compliance (2 copies) Residential Buildings (R‐3 buildings, as well as R‐2 and R‐4 buildings three stories or less in height  above grade) and residential portions of mixed‐use buildings may use of one of the following five  methods to demonstrate energy code compliance of the thermal envelope. You must note on the plans  which approach you are taking.  1. Prescriptive Alternative: Use the values out of Table R402.1.2 for insulation and fenestration (printed  below). Your details, sections, and/or schedules must be noted with these R and U values.  2015 IECC Table R402.1.2 (as amended by City of Aspen Ordinance 40, 2016)  CLIMATE   ZONE  FENESTRATION   U‐FACTOR  SKYLIGHT   U‐FACTOR  CEILING   R‐VALUE  WOOD   FRAME  WALL   R‐VALUE  MASS  WALL   R‐VALUE  FLOOR   R‐VALUE  BASEMENT   WALL   R‐VALUE  SLAB   R‐VALUE   & DEPTH  CRAWL   SPACE  WALL   R‐VALUE  7 0.28 0.55 49 20 +5 or  13+10h 19/21i 38g 15/19c 10, 4 ftd 15/19c  Table Footnotes:  c. "15/19" means R‐15 continuous insulated sheathing on the interior or exterior of the home or R‐19 cavity insulation at the  interior of the basement wall. "15/19" shall be permitted to be met with R‐13 cavity insulation on the interior of the basement  wall plus R‐5 continuous insulated sheathing on the interior or exterior of the home. "10/13" means R‐10 continuous insulated  sheathing on the interior or exterior of the home or R‐13 cavity insulation at the interior of the basement wall.  d. R‐5 shall be added to the required slab edge R‐values for heated slabs. Insulation depth shall be the depth of the footing or 2  feet, whichever is less in Zones 1 through 3 for heated slabs.  g. Or insulation sufficient to fill the framing cavity, R‐19 minimum.  h. The first value is cavity insulation, the second value is continuous insulation, so “13+5” means R‐13 cavity insulation plus R‐5  continuous insulation.  i. The second R‐value applies when more than half the insulation is on the interior of the mass wall.    2. U‐factor Alternative: Use the values out of table R402.1.4 from the 2015 IECC as amended (see  below). You must demonstrate your calculations of the U‐factor of any assemblies using this alternative,  including the effects of thermal bridging of from framing materials. Your details, sections, and/or  schedules must be noted with these values. You may mix this approach with the prescriptive one above.    6/12/2017    Page 6 of 28    Fenestration  U‐Factor  Skylight  U‐Factor  Ceiling  U‐ Factor  Frame  Wall U‐ Factor  Mass  Wall U‐ Factor  Floor U‐ Factor  Basement  Wall U‐ Factor  Crawl  Space  U‐ Factor  0.28  .55  0.026  0.045  0.057  0.028  0.050  0.055    3. Total UA Alternative: Use Rescheck, downloadable for free at www.energycodes.gov. The proposed  design must be a minimum of 2% more efficient than the standard reference design in order to  accommodate for Aspen’s amended prescriptive fenestration U‐factor. Be sure to address the following  in your Rescheck:  □ Select 2015 IECC as the code   □ Under Options, choose Compliance Method: UA trade‐off  □ Fill out all info on the Project tab, including Project Details (not optional!)  □ Fill out the Envelope tab with all of your assemblies and fenestration. See the Help section  for guidance.  □ The makeup and area of all assemblies must EXACTLY match the plans.  □ Cavity insulation is insulation installed in the framing cavities between studs and joists.  Continuous insulation is installed beyond framing and runs past it.  □ Print out and sign the Rescheck. Two copies are required.  4. Simulated Performance Alternative: Use Rescheck, downloadable at www.energycodes.gov, or other   software approved by the building official. Be sure to address the following in your Rescheck:   □ Under Options, choose Compliance Method: Performance Alternative  □ All the requirements of the Total UA Alternative method above apply.  □ Using the performance alternative requires additional inputs including conditioned floor area,  orientation of the building, a minimum of four walls having unique orientations, and a minimum  of one roof and floor.  5. Simplified Equivalent Compliance Alternative:  Under this approach compliance is based on adhering  to a minimum size for the heating and cooling systems:  1. The ratio of the air conditioning capacity to conditioned space is less than or equal to 1 ton  per 1000 square feet.   2. The ratio of the space heating system capacity to floor area of conditioned space is less than  or equal to 32,000 Btu/h per 1000 square feet.  The design team must provide details, sections, and/or schedules with insulation and fenestration R or U  values, but any values are acceptable as long as the air conditioning and space heating capacity meets  the minimum.  The heating system size is only intended for space heating, so if the system also supplies  hot water and/or snowmelt, load calculations need to be provided to show what portion of the total  output is needed for each of its uses.   This path also has two additional requirements:    6/12/2017    Page 7 of 28    1) The distance from the hot water supply outlet to hot water pipe to the hot water entry to a  room where hot water is used shall be no more than 10ft. This shall apply to the kitchens,  bathrooms with showers or tub, and rooms with a clothes washer. Provide hot water piping  plans to illustrate compliance.   2) Lighting ‐ at least one of the following requirements shall be deemed in compliance: 1. Lamps  over 15 watts shall be CFL, LED, or have an efficacy not less than 90 lumens per watt. 2. At least  90% of the lamps or fixtures shall have an efficacy not less than 75 lumens per watt.  Provide  lighting plans to illustrate compliance.   Commercial Buildings (Any building or portion of a mixed‐use building not included in the  residential definition above)  must comply with either the 2015 IECC or ASHRAE Standard 90.1 (2013)  for Envelope, Lighting, and Mechanical.  You must choose one code and not mix and match.   Envelope:  You may use of one of the following methods to demonstrate envelope energy code compliance. You  must note on the plans which approach you are taking.  Prescriptive: Use the values out of Table C402.1.3 and C402.4 from the 2015 IECC for climate zone 7.  Your details, sections, and window/door/insulation schedules must be noted with these values.  U‐factor Alternative: Same as above, but use the values out of table C402.1.4 from the 2015 IECC for  climate zone 7. You must demonstrate your calculations of the U‐factor of any assemblies using this  alternative, including the effects of thermal bridging from framing materials. You may mix this approach  with the Prescriptive one above.  Total UA Alternative: Use Comcheck, downloadable at www.energycodes.gov. Be sure to address the  following in your Comcheck:  □ Select 2015 IECC or ASHRAE 90.1 (2013) Standard as the code (no mixing and matching)   □ Fill out all info on the Project tab, including Project Details (not optional!)  □ Fill out the Envelope tab with all of your assemblies and fenestration. See the Help section  for guidance.  □ The makeup and area of all assemblies must EXACTLY match the plans and insulation  schedule.  □ Cavity insulation is insulation that sits in the framing cavities between studs and joists.  Continuous insulation is insulation that sits beyond framing and runs past it.  □ Print out and sign the Comcheck. Two copies are required.  Performance: Comply with section C407 of the 2015 IECC.  Interior and Exterior Lighting:  Use Comcheck; follow the instructions above, as well as:  □ Create a labeling system to ease comparison between the comcheck, lighting plans, lighting  schedule, and specs. All must match exactly.  □ Provide spec sheets for all fixtures listing wattages    6/12/2017    Page 8 of 28    □ Only take exemptions and allowances as allowed by 2015 IECC sections C405.4.1, Table  C405.4.2C503.6, C504.2.     Mechanical:  Use Comcheck; follow the instructions above, as well as:  □ Create a labeling system to ease comparison between the comcheck, equipment schedule  and plans. All must match exactly.    As an alternative to the above methods, you may use the Total Building Performance Method. Refer to  2015 IECC section C407.   Non-Vented Roof Assembly Dew Point Calculations (2 copies) Roof assemblies that do not meet the roof ventilation requirements of currently adopted codes shall be  designed to avoid the likelihood of fungal growth or the accumulation of moisture on the linings and  other building elements. The applicant shall submit calculations and/or supporting proof that the  building systems will perform to avoid the accumulation of fungal growth and moisture in the roof  assembly. The proposed roof assembly will be reviewed and approved by the building official and  demonstrate compliance to the alternate method of roof ventilation.  The calculations must show that the temperature of the condensing surface (T interface) is greater than  41 degrees F at 35% relative humidity. You may use the following equation:  T(interface) = R(exterior) / R(total) x [T(inside) – T(outside)] + T(outside)    Where:  T(interface) = temperature at the sheathing/insulation interface or the temperature of  the first condensing surface. Must be great than 41 deg F.  R(exterior) = the R‐value of the exterior sheathing  R(total) = the total R‐value of the entire assembly  T(inside) = 70 deg F  T(outside) = 19.8 deg F (mean daily temp)    Example:  Thickness:      5/8”  4”    5 1/4"  5/8”  Component:  Outside air layer  Water‐proof membrane  Sheathing  Closed‐cell spray foam  ‐‐‐‐‐‐‐condensing surface‐‐‐‐‐‐  Fiberglass Batt (high density)  Gypsum board  Inside air layer  R‐Value:  0.17  0.21  0.77  28    21  0.56  0.65    6/12/2017    Page 9 of 28      R(exterior) = 0.17 + 0.21 + 0.77 + 28 = 29.15  R(total) = 29.15 + 21 + 0.56 + 0.65 = 51.36  T(inside) = 70 deg F  T(outside) = ‐16 deg F  T(interface) = R(exterior) / R(total) x [T(inside) – T(outside)] + T(outside)  T(interface) = 29.15 / 51.36 x [70 – 19.8] + 19.8)  T(interface) = 48.3    The temperature at the first condensing surface (closed‐cell spray foam insulation) is 48.3 degrees F.  Therefore, the resulting dew point temperature of 41 degrees F would occur within the spray foam,  which verifies compliance.        U-Factor Fenestration Documentation (2 copies) All new windows, skylights, and glazed doors must have a factory applied NFRC stickered label listing the  U‐factor of the entire assembly. This U‐factor must match what you selected in the Energy Code  Compliance section above. You must note on the plans that all new fenestration on the project will  comply with this.  If new windows, skylights, or doors do not come with a factory applied NFRC stickered label listing the U  value of the entire assembly, you must demonstrate the U value using one of the following options per  City policy. The calculations must be for the entire assembly, including the glazing and the frame.  NFRC CMA certificate (preferred): Component Modeling Approach. Uses CMA Software Tool (CMAST).  Speak with your window/door representative to see if this is an option. More info here:  http://cmast.nfrc.org   ASHRAE Calculations: Calculation methods from ASHRAE Fundamentals Handbook: “U‐Factor (Overall  Coefficient of Heat Transfer).” A calculation is required for each individual window assembly or you may  calculate the worst performing window and use that U factor for every window. Below is an example:  1. Determine U‐value for the three sections of window assembly. You must look these up in the  ASHRAE tables:   Center of Glass (Ucg)   Edge of Glass (Ueg)   Window Frame (Uf)  2. Determine Area for the three sections of window assembly. Follow the directions in ASHRAE:   Center of Glass (Acg)   Edge of Glass (Aeg)   Window Frame (Af)  3. Calculate the weighted average U factor, by area of the three sections:    6/12/2017    Page 10 of 28    U= (Ucg x Acg) + (Ueg x Aeg) + (Uf x Af)  (Acg + Aeg + Af)  Renewable Energy Mitigation Program documents (1 copy) Snowmelt, hot tubs, and outdoor pools are required to comply with the Renewable Energy Program  (REMP). Residential Renewable Energy Mitigation Program guidelines apply to R‐3 buildings, as well as  R‐2 and R‐4 buildings three stories or less in height above grade and residential portions of mixed‐use  buildings.  Commercial Renewable Energy Mitigation Program guidelines apply to all other types of  buildings and commercial portions of mixed‐use buildings.  For further information on the REMP  program, refer to Appendix A and Appendix B in the City of Aspen’s adoption of the 2015 IECC.  In addition to the full size REMP plan sheets mentioned later, you must submit the following to  demonstrate compliance:  All:  □ Completed RREMP/CREMP worksheet, available on the City of Aspen website.  □ Specs on boiler (the boiler/heating unit for the snowmelt, pool, and/or spa), showing AFUE.  (annual fuel utilization efficiency)If using solar renewable credits: The renewable credit will  be determined by the system kW capacity multiplied by the efficiency of the system as  calculated on the RREMP worksheet. Be sure to include this tab from the worksheet.    o Plans should show panel location, tilt, and aspect from true South.   o Provide specs on solar panels, showing dimensions, orientation, and, if Photovoltaic,  kW per panel.     □    Hot Tub:  □ If using a spa that is not CEC or APSP‐14 certified, you must include it in the RREMP/CREMP  worksheet and pay the RREMP option fee. For RREMP, the area is the area of the water  surface.  If installing a RREMP exempt spa, provide specs showing dimensions and CEC  (California Energy Commission) or APSP‐14 (Association of Pool and Spa Professionals)  certification. The CEC has a database of all compliant spas at  http://www.appliances.energy.ca.gov/QuickSearch.aspx.   □ Specs on a safety cover listed as ASTM F 1346 (unless an enclosure barrier is used per 2015  International Swimming Pool and Spa Code 305)   Outdoor Pool:  □ Must include it in the RREMP/CREMP worksheet and offset or pay a fee. For REMP, the area  is the area of the water surface.  □ Specs on a safety cover listed as ASTM F 1346 (unless an enclosure barrier is used per 2015  International Swimming Pool and Spa Code 305).  □ Specs on a vapor‐retardant pool cover (2015 IECC R403.10.3).      6/12/2017    Page 11 of 28    Line Grade Verification Form (1 copy) Fill out part A and show horizontal ties to property line on Site Plan.  Verification of Structural Integrity (2 copies) For alteration, demo and repair work minor in nature; if any walls, or other potentially structural  elements are being altered, whether bearing or non‐bearing, verification in one of the following forms  may be accepted in lieu of a structural plan prior to demo:  Stamped Letter Option: A letter stamped and signed by a structural engineer or architect stating that  they will be involved with the project and certifying the structural integrity of the proposed demolition  or other work. Once finishes have been removed, if it is determined that structural bearing components  will be altered, a structural plan will be required.  Original Framing Plans Option: Provide the original framing plans demonstrating that the elements you  are proposing to alter are non‐bearing and not part of the structural frame. If during construction it is  determined that the existing structure does not match the original plans, a new structural plan or  stamped letter will be required.  Soils Report (1 copy) Must comply with the City of Aspen Soils Report Requirements. Alternatively, a letter from a  geotechnical engineer committing to excavate and then confirm assumptions or a letter from a  geotechnical engineer to use a soils report from an adjacent property may be submitted if approved by  the building official.    Special Inspection and Testing Agreement (2 copies) Work that includes any of the following requires special inspection per 2015 IBC section 1705:   □ High strength bolting  □ Epoxy anchors  □ Structural steel welding  □ Pre and post stressed tendons  □ Permanent micropiles or helical piers  □ Sprayed fireresistant materials  □ Mastic and intumescent fireresistant coatings    6/12/2017    Page 12 of 28    The Special Inspection and Testing Agreement may be turned in later in the submittal process; it is not  required at submittal, but is required prior to sign off and issuance. The agreement must be signed by  the following entities:  □ Special Inspection Agency  □ Owner  □ Engineer/Architect  □ Contractor  □ Fabricator (either approved or inspected)*  *Approved fabricators may inspect their own shop fabrication, but must have their field work inspected by the special  inspector. Inspected fabricators must have all of their work inspected by the special inspector.  Photos (1 copy) Provide photographs of the proposed work areas. (optional: to aid plans examiner for better  understanding of existing conditions) Unit/building Relationship (1 copy) For alterations and additions to multi‐unit buildings only.  Provide an elevation, section, or photograph  clearly showing the relationship of the unit being remodeled to the remainder of the building. Highlight  your unit and show neighboring units. Note the occupancy type of the neighboring units (residential,  business, retail, restaurant, etc).    6/12/2017    Page 13 of 28    Construction Drawings Set Drawing Standards □ Submit two full sets of plans at 24” x 36” size sheets, as well as one reduced 11” x 17” set. Other  sizes are not accepted under any conditions. For electronic submittals, refer to the electronic  submittal standards.  □ Do not fold any of the plans.  □ All sheets in a drawing set must be the same size, sequentially labeled, dated and have a page  title/description.  □ Include North arrow and the scale [standard architectural or engineering scales (1/4”=1’, etc)].  □ 1/4”scale is preferred. Minimum scale is 3/16”.  □ Title block with project name, project address and legal description.  □ Include matching gridlines on all drawings.  □ All structural, mechanical, electrical, and plumbing plans, details and calculations must be  prepared, stamped, and signed by a professional engineer or architect licensed in the state of  Colorado (digital copy of seal and signature is sufficient).  □ Architectural drawings are required to be stamped unless they meet one of the following  exemptions: 1) One, two, three, and four unit family dwelling including accessory buildings  associated with such dwellings 2) Garages, industrial buildings, offices, farm buildings, and  buildings for the marketing, storage, or processing of farm products, and warehouses, which do  not exceed one story in height, exclusive of a one‐story basement, and which under applicable  building code, are not designed for occupancy by more than ten persons 3) Additions,  alterations or repairs to the foregoing buildings which do not cause the completed building to  exceed the applicable limitations 3) Nonstructural alterations of any nature to any building if  such alterations do not affect the life safety of the occupants of the building. (CO State Board of  Architect Examiners and State Board of Registration for Professional Engineers)  □ Existing/Demolition plans shall be printed on the same sheet as the proposed plans. Where  there is not enough room, the existing/demolition plans should be grouped prior to the  proposed plans.   □ All drawings must differentiate between existing and proposed construction.  □ Provide floor plans of the entire unit, not just the area of work.  □ The floor plans should be ordered from lowest floor to the highest floor (i.e. basement, first  floor, second floor).   □ All Change Orders shall highlight with clouds or bubbles all areas changed, and include a  bulleted list of the changes. All changes must be identified in this manner. Corrections made to  a permit during the review process shall not have clouds or bubbles, only change orders should  have revision clouds.    Note: Some items below are repeated on different sheets. It is not required to have these items  shown multiple times, just be sure to show in one of the listed locations.  Cover Sheet □ List code editions (2015 IBC, 2015 IECC, 2015 IMC, 2015 IPC, 2015 IFGC, 2017 NEC, and City of  Aspen Municipal Code Title 8)    6/12/2017    Page 14 of 28    □ Note if a Fire Sprinkler system will be installed and whether it is NFPA 13, NFPA 13D or NFPA  13R.  □ Address and unit #  □ Parcel ID #  □ Owners Name  □ Permit Number: Provide a blank if this is not yet known. If submitting a change order, do not use  the original permit number.  □ #1 Permit Number: If submitting a change order, put the original permit’s number here.  □ Change Order Number: i.e. change order #2  □ Contact Info for all involved parties, Designer or Architect, Structural Engineer, Mechanical  Engineer, Civil Engineer, Contractor, Owner and if Owners Representative   □ Table of Contents, index of sheets in this order, cover sheet, survey, site plan, zoning sheets, civil  sheets, landscape sheets, architectural sheets, MEP’s, structural sheets, stabilization sheets   □ List required types of special inspections  □ Note which path of energy code compliance you are taking  □ Planning approvals. Print every page of every approval on the cover sheet.  Survey For new construction and additions. Must be drawn per the Compliant City of Aspen Survey Checklist.  Excavation/Earth Retention Plans (under  Chapter 18 of the 2015 IBC and City of Aspen Engineering Standards)  □ Plans for Temporary and/or Permanent Soil Nails and Micropiles (must be stamped by engineer)  or a site plan showing that there is adequate space on site for a one‐to‐one layback (the  proposed foundation walls are within a horizontal distance less that the vertical depth of  excavation of any existing travel way, structure, or property line.)    Site Plan For new construction, additions, and exterior alterations. Include the following: □ Property lines, building setbacks, building envelopes, and easements  □ Exterior walls, roof lines, and overhead building projections with dimensions that tie the  building to the property line and other buildings on the same lot.  □ Provide the equivalent grade to architectural 100’. (i.e. 100’ = 7495.5’)  □ All development, including: Structures, decks, patios, walls, retaining walls, fences, gates,  walkways, fire pits, water features, railings, pergolas, trellises, vehicular access, parking areas,  vehicular turn‐arounds, driveways, carports, condensers, equipment, etc  □ Fire truck access, including distance and width, and turnarounds  □ Adjacent streets, alleys, adjacent building properties  □ Existing and proposed grades including spot elevations  □ Locations of all utility meters and shutoffs     6/12/2017    Page 15 of 28    □ Design flood elevations, flood hazard areas, and floodways (if applicable)  Commercial and/or Residential Renewable Energy Mitigation Program (CREMP/RREMP) plan □ Show all snowmelt areas in plan, provide individual area square footages and the total square  footage.  □ R‐10 insulation detail under snowmelt. Must be rigid foam, no bubble wrap.  □ Solar panels shown on plan. Photovoltaic:  kW, orientation, slope, and height above roof.  Thermal: square footage, orientation, slope, and height above roof.  □ Spas and pools.   □ Enclosure barriers or listed covers for pools and spas  □ You may choose to put all of this on the Site Plan if it can be done clearly and legibly.  Area sheet Illustrate and calculate building gross floor area as defined by 2015 IBC section 202 for all structures.    FLOOR AREA, GROSS. The floor area within the inside perimeter of the  exterior walls of the building under consideration, exclusive of vent shafts  and courts, without deduction for corridors, stairways, closets, the thickness  of interior walls, columns or other features. The floor area of a building, or  portion thereof, not provided with surrounding exterior walls shall be the  usable area under the horizontal projection of the roof or floor above. The  gross floor area shall not include shafts with no openings or interior courts.     Commentary: Gross floor area is that area measured within the perimeter  formed by the inside surface of the exterior walls. The area of all occupiable  and nonoccupiable spaces, including mechanical and elevator shafts, toilets,  closets, mechanical equipment rooms, etc., is included in the gross floor  area. This area could also include any covered porches, carports or other  exterior space intended to be used as part of the building’s occupiable space.    Illustrate and calculate fire area as defined by 2015 IBC section 202. If the fire area is greater than  5000sqft, a fire sprinkler system is required per Ordinance 40, 2016.    FIRE AREA. The aggregate floor area enclosed and bounded by fire walls, fire  barriers, exterior walls or horizontal assemblies of a building. Areas of the  building not provided with surrounding walls shall be included in the fire  area if such areas are included within the horizontal projection of the roof or  floor next above.    6/12/2017    Page 16 of 28      Occupancy/Means of Egress Plan □ Type of construction (i.e. Type VA, VB, IIIA, etc) Find this in the building address file or provide a  calculation per 2015 IBC chapter 5.  □ Building height, stories, area  □ Note any increases or ‘buy downs’ used, such as sprinkler or frontage increases.  □ Note if there is an existing fire sprinkler system, the type, and its extent (entire building?  partial?).  □ All occupancies and incidental/accessory uses with square footages  □ Proposed method of occupancy separation/non‐separation  □ Occupant load calculations  □ Travel paths and distances  □ Common path of egress measured rectilinearly  □ Separation of exits  □ Exit enclosures, exit passageways, corridors, lobbies, discharges, etc. labeled  □ Exit illumination and signs, emergency power  □ Seating, furniture, fixture, and/or merchandise display layout if applicable  Fire Resistance Plans/Details □ Occupancy separations  □ Type of Construction separations  □ Means of Egress separations  □ Fire resistive (and STC/IIC) walls, floors, ceilings, roofs, and shafts  □ Dash/highlight all rated assemblies in plan view and section. Must show continuity (rating must  not start and stop).  □ Label all rated assemblies (walls, floor/ceilings, roof/ceilings, shafts, etc) to reference a detail  and a listed and tested assembly. Print out the full installation instructions of each listed and  tested assembly on the plans. Listed and tested assemblies can be from one of the following:  o UL Listings  o Gypsum Manual (GA‐600 Fire Resistance Design Manual)  o From a manufacturer if the assembly was tested to UL 263 or ASTM 119.  o 2015 IBC section 721  o 2015 IBC section 722  □ Label all fire rated doors, windows, and hatches with the minute fire rating (may show this on  the door/window schedule alternatively)  □  Show all penetrations through fire resistive assemblies and provide listed product specs (no  penetrations are permitted in exit enclosures). Note that all penetrations of fire rated  assemblies must comply with 2015 IBC 714  □ Note where fireblocking and draftstopping will be installed. Show in any details as necessary.    6/12/2017    Page 17 of 28    □ Provide the distance to property line of all exterior walls. If facing a street or alley, provide the  distance to the centerline of the street or alley.  □ Provide elevations of all exterior walls that are less than 30 feet from the property line or  centerline of street or alley. Show the following on the elevations:  o Hatch the area of each portion of wall in a single plane on a single floor. Label the  square footage.  o Hatch the aggregate area of all doors and windows (full frame size) on each wall portion  above. Label the square footage.  o Provide calculations demonstrating compliance with 2015 IBC 705.8.  □ Where interior finish materials are applied on walls, ceilings or structural elements required to  have a fire‐resistance rating or to be of noncombustible construction, clearly show the furred or  set out construction with materials and dimensions shown in details. (803.13)  Accessibility Plans & Details □ Show accessible entrances and routes from public way throughout site and facility   o Show door maneuvering clearances  o Include route to toilet/bathing facilities  □ Show accessible means of egress  □ If any of the following are provided, some or one must be accessible (see IBC chapter 11).  Show in plan and clearly show all required clearances and dimensions.  o Parking, Toilet or Bathing facility, Sinks, Dressing room, POS counter, workspace,  seating, dining, kitchen/kitchenette, drinking fountain, elevator, storage, controls,  switches and outlets  □ Show all required accessibility signage  □ If four or more dwelling units, they must all be Type B accessible.   o State whether using option A or B for bathrooms and show all required elements  with dimensions.  o Reach ranges for controls and outlets  o Door clear opening widths to all rooms  o Grab bar reinforcement in all bathrooms  □ Show travel route and distance to toilet facilities  □ Existing buildings: If modifying a space containing a primary function, then an accessible  route, accessible toilet facilities and drinking fountain must be provided.  □ Accessibility details  □ Details and elevations showing clearances and dimensions for all accessible elements  □ Toilet and bathing room fixture clearances  □ Grab bars, mirrors, dispensers  □ Point of sale counters  □ Counters for dining and work surfaces  Floor plans Required for all permits  □ Existing drawings preceding proposed drawings  □ Room uses labeled  □ Gridlines    6/12/2017    Page 18 of 28    □ Section, detail, and assembly callouts  □ Provide the equation comparing site (surveyed) elevation to structure/ architectural plan  elevation: (i.e., 100’ first floor elev = 7962.50’)  □ Floor finish material  □ Carbon monoxide and smoke detector locations  □ Door swings with floor levels shown on both sides including exterior landings  □ Stairs: direction of travel, handrails with extensions and returns, rise/run  □ Guard rail locations  □ All appliances and equipment labeled  □ Attic and crawlspace access, with dimensions  □ Emergency Escape and rescue openings with height of sill above finish floor  □ Window wells with dimensions, show ladder.  □ Dashed outline of roof overhangs above    Roof Plan Applicable to new construction and roof work  □ Existing drawings preceding proposed drawings  □ Drains and secondary drains/scuppers  □ Skylights with labels matching schedule  □ Flue, exhaust, and chimney terminations and outside air intakes with dimensions to property  lines and openings.  □ Roof pitches shown as x:12  □ Solar panels with orientation, slope, and height above roof  □ Roofing material and class (Class A in Wildfire Zone High Hazard, Class B all others)  □ Roof/attic ventilation  □ Show exterior walls below with dashed line.  □ Show parapets  □ Snow stop locations. These are required anywhere a roof could shed ice and snow onto  potentially occupied areas such as a walkway, stairway, alley, deck, pedestrian and vehicular exit  from buildings or areas where there is potential for personal injury or property damage and  areas directly above or in front of gas utility or electric utility meters. (Ordinance 40, 2016)  □ FYI (this does not need to be on plans but must be installed): Ice dam barrier of at least two  layers of underlayment cemented together or of a self‐adhering polymer modified bitumen  sheet shall extend from the roof eave edge at least six feet inside the exterior wall line as  measured along the roof surface, eighteen inches from the centerline of the valley and up  twenty‐four inches on the vertical wall at a roof and wall juncture. (Ordinance 40, 2016)    Elevations □ Existing drawings preceding proposed drawings  □ Show grade, underground structure and window wells  □ Windows and doors (show operable vs. fixed) label to match schedules    6/12/2017    Page 19 of 28    o In residential occupancies give dimensions showing whether widow openings are within  24” of finish floor and are located more than 72” above the surface below.  In such cases  glazing needs to be fixed or have an opening limitation device. (1015.8)  □ Interior finish floor levels as dashed lines, including stairs  □ Dimension all guard heights  □ Egress windows labeled, bottom of opening heights dimensioned  □ Safety glazing labeled on windows  □ Vents, intakes, and exhausts with distances to openings and property lines  □ Chimneys and flues with heights 3’ at roof penetrations and 2’ above building elements within  10’  □ Finish materials, exterior walls, roofs  □ Protection from decay, wood to earth separations 6” min above grade  □ Landings at doors and stairways  □ Electric service and gas and water meter locations  □ Snow stops (see requirements in Roof Plan section)    Sections □ Detail and assembly callouts  □ Headroom height, including at dropped ductwork.  □ Show the thermal envelope continuity. Must be continuous or you must account for  gaps/thermal bridges using the UA trade off in Comcheck.  □ Skylights with dimension above finish floor  □ Roof and crawlspace ventilation  □ Separations and all fire rated assemblies  o Fire resistive (and STC/IIC) walls, floors, ceilings, roofs, and shafts  o Extents clearly shown  o Callouts referencing details  □ Fire rated openings, doors, windows.  □ Show all penetrations and transfer openings through fire resistive assemblies and provide listed  product specs.   □ Note where fireblocking and draftstopping will be installed. Show in any details as necessary.  □ Clearly show all furred or set out construction with materials and dimensions shown in details.  □ Note exterior projections and/or concealed construction requiring sprinkler protection.  □ Set out construction over fire rated or required non‐combustible assemblies per 2015 IBC  803.13.  □ Concealed combustible spaces in sprinklered buildings  o Concealed spaces of combustible construction require fire sprinklers unless filled with  non‐combustible insulation or are less than 6” deep. See NFPA 13‐8.15.1 for additional  exceptions.    Details □ All wall, floor, ceiling, roof assemblies  □ Fire resistive assemblies and firestop penetration details    6/12/2017    Page 20 of 28    o Include the full listing installation instructions on the plans. If options are presented  note specific option  □ All assembly, wall, floor, roof, parapet, eave, and ceiling intersections. Demonstrate continuity  of fire assemblies.  □ All intersections of dissimilar materials, corners and ends  □ Control joints  □ All insulation (rim joists, slab edge, etc.). No thermal breaks or cold bridges.  □ Air barrier and vapor barrier continuity  □ Air sealing locations (2015 IECC R402.4.1.1):   All joints, seams and penetrations   Site built windows, doors and skylights   Openings between window and door assemblies and their respective jambs and framing   Utility penetrations   Dropped ceilings or chases adjacent to the thermal envelope   Knee walls   Walls and ceilings separating a garage from conditioned spaces   Behind tubs and showers on exterior walls   Common walls between dwelling units   Attic access openings   Rim joist junction   Other sources of infiltration  □ Waterproofing, flashing, means of drainage  □ Details around openings such as windows and doors  □ Door thresholds (level floor on each side with ½” max up to threshold)  □ Finishes with schedule of flame spread index and smoke‐development index  □ Fire blocking and draft stopping  □ Fire resistive assemblies and STC/IIC assemblies (at occupancy separations) including a copy of  the listing and installation instructions printed on the plans. You must choose a listed and tested  assembly or use a preapproved assembly.  □ Masonry veneer assembly, support and weep holes.  □ Protection of foam plastic  □ Note where fireblocking and draftstopping will be installed. Show in any details as necessary.  □ Clearly show all furred or set out construction with materials and dimensions shown in details    Stairs □ Rise and run  □ Vertical rise  □ Headroom  □ Fire protection for enclosed usable space under stairs  □ Handrails, returns, extensions  □ Guards  □ Landings  Ramps   6/12/2017    Page 21 of 28    □ Slope and cross slope in % or 1:12  □ Vertical rise  □ Handrails, returns, extensions  □ Guards  □ Edge protection  □ Landings  Fireplace Details   □ Note type of appliance (ie: gas log, direct‐vent)  □ Dimensions, including firebox opening  □ Firebox and chimney/flue clearances to combustibles  □ Hearth extension dimensions, construction, and support  □ Firebox and hearth extension support  □ Exterior air supply  □ Gas log fireplaces must have tight‐fitting flue dampers or doors, and outdoor combustion  □ air. (2015 IECC R402.4.2, IBC 21)    Schedules □ Window: size, U factor, emergency escape, safety glazing, fire rating  □ Skylight: glazing materials, laminates, interlayer thickness, curb height, U factor, fire rating  □ Door: size, clear opening width, U factor, fire rating  □ Finishes – include flame spread index and smoke‐development index    Reflected Ceiling Plans □ Permanently installed light fixtures  □ Skylights  □ Soffits and furred/dropped ceilings  □ Attic access with dimensions    Lighting Plans (under the 2014 NEC, 2015 IECC) □ Permanently installed light fixtures  □ Lighting Schedule, note IC rated cans  □ Labeling on plan must match the COMcheck, lighting schedule, and specs.     Electrical Plans □ All lighting with key notes matching schedule and cut sheets  □ Note IC rated cans  □ Receptacles, switches, circuits  □ Panel schedule    6/12/2017    Page 22 of 28    □ Location and size of all panel boards, electric service, service disconnect, and transformers with  clearances  □ Grounding and bonding  □ Electrical load calculations per 2017 NEC  □ Emergency power lighting  □ Height AFF of all controls, switches and outlets required to be accessible  □ Any fixtures projecting into a means of egress must be dimensioned  □ Meter Location    Commercial Kitchen Plans □ Commercial kitchen layout, equipment, and schedules  □ Kitchen hoods with clearances  □ Washable surfaces    Mechanical Plans  □ Basic one‐line schematic drawing of the HVAC system  □ Show all equipment, ductwork, and venting  □ Show all intake, exhaust, flue, and vent outlets with dimensions to openings and property lines  □ Equipment layout with access, working space, and clearances  □ Equipment schedule with equipment sizes, efficiency, btus, cfm, etc  □ Description of all systems and sequence of operation  □ Winter/summer indoor and outdoor design temperatures listed on the plan. Must fit within the  following parameters:  o Winter indoor temp may not be above 72 deg F (2015 IECC R302.1)  o Winter indoor temp may not be below 68 deg F (2015 IRC R303.8)  o Summer indoor temp may not be below 75 deg F (2015 IECC R302.1)  o Summer outdoor design temp: 82 deg F (Ordinance 40, 2016)  o Winter outdoor design temp: ‐15 deg F (Ordinance 40, 2016)  □ Show calculations used to provide ventilation per 2015 IMC 403 as amended in Ordinance 40,  2016.  **Group R‐2, R‐3, and R‐4 occupancies require balanced ventilation systems. The minimum  continuous outdoor airflow rate shall be determined in accordance with the following equation:  Qr = ((0.01 x Afloor) + [7.5 x (Nbr + 1)]) x Sc   where:   Qr = ventilation flow rate, cubic feet per minute (cfm)   Afloor = floor area in square feet (ft2)   Nbr = number of bedrooms, not less than one   Sc = 0.75 (system coefficient for balanced systems)   Exception: The outdoor air ventilation system is not required to operate continuously where the system has controls  that enable operation for not less than 1 hour of each 4‐hour period. The average outdoor air flow rate over the 4‐ hour period shall be not less than that prescribed by the equation.    □ All fireplaces, sizes, types, exterior/combustion air, and venting  □ Fire/smoke dampers, radiation dampers  □ Height AFF of all controls required to be accessible  □ Radiant floor piping – show R5 insulation  □ Snowmelted areas – show R10 insulation    6/12/2017    Page 23 of 28    □ Commercial kitchen layout, equipment, and schedules  □ Kitchen hoods with clearances and cfm  □ Make up air  □ Dryer duct length, CFMs and makeup air  □ Note fuel type and combustion air requirements for existing equipment to remain.    Plumbing Plans □ DWV, water piping, storm water  □ Roof drains, overflow drains or scuppers  □ Discharge location for overflow drains  □ Protection from freezing  □ Below grade ejectors  □ Condensate disposal method and termination location  □ Gas piping  □ Gas meter location (including protection from falling snow)  □ Grease interceptors, sand and oil interceptors    Structural Plans (under the 2015 IBC, Ordinance 40, 2016)  Required for new construction, additions, and structural alterations.  □ Reference to soils report or soils bearing capacity assumption signed letter from structural  engineer  □ Design load criteria, wind speed & exp. category, ground snow load, and seismic category.  All to  match City’s amended design criteria (See additional information below  □ Foundation plan: footing, pad and foundation wall sizes, steps, and elevations; cross sections  showing reinforcement  □ Frost protection depth  □ Roof and floor framing plans  □ Locations and sizes of all framing components  □ Hangers  □ Header sizing  □ Fasteners and welds  □ Shear walls/bracing locations and nailing requirements  □ Material types, grades and species identified  □ Details referenced in plans  □ Masonry and stone veneer Support   □ Special inspections program, list the elements and periodic or continuous inspections required       6/12/2017    Page 24 of 28      6/12/2017    Page 25 of 28    Additional Information Adopted Codes & Standards The following codes as amended by Ordinance 40, 2016  □ 2015 IRC (International Residential Code) Chapters 1‐10   □ 2015 IRC appendixes:  E: Manufactured homes, F: Radon, J: Existing Buildings & Structures, H:  Patio Covers, K:  Sound Transmission.  □ 2015 IPC (International Plumbing Code)  □ 2015 IMC (International Mechanical Code)  □ 2015 IFGC (International Fuel Gas Code)  □ 2015 IECC (International Energy Conservation Code)  □ 2015 IFC (International Fire Code)  □ 2015 IEBC (International Existing Building Code)  □ 2015 ISPSC (International Swimming Pool and Spa Code)  □ 2015 ISEP (International Solar Energy Provisions)  □ 2014 NEC (National Electrical Code) (Will adopt 2017 when State of Colorado adopts)  Design Criteria As adopted by Ordinance 40, 2016  □ Ground snow load: 100 psf  □ Wind speed: 89 mph, exposure category B  □ Seismic design category: C  □ Weathering: Severe  □ Frost line depth: 36”  □ Termite/Decay: none to slight  □ Winter design temperature: ‐15 deg F  □ Ice shield underlayment required: yes, 6’ up from eave  □ Flood Hazards: FEMA MAP 6/4/1987  □ Air Freezing Index: 1694  □ Mean Annual Temp: 40 deg F  □ Site Class: determined by soils report, or by structural engineer’s assumption statement.   Per City Policy:  □ Summer outdoor design temp: 82 deg F  □ Indoor design relative humidity: 35%      6/12/2017    Page 26 of 28    Fire Sprinklers As adopted by Ordinance 40, 2016:   Automatic fire sprinkler systems are required in all structures 5,000 square feet or greater as  defined by fire area and in structures 2 stories or more in height and in structures containing 4  or more dwelling units.   Carbon Monoxide Detectors All owners of existing residential occupancies shall come into compliance with the requirements of  Chapter 8.15 Carbon Monoxide Detectors. The ordinance became effective on March 2, 2009 and  applies to all existing, new and altered dwelling units.    Inspections See the City of Aspen Inspection Checklist for a list of potential inspections your project may require.   Final Inspection Expectations Prior to Final inspection, you must have/complete the following:  1. Have final signoffs from each applicable review agency, including:  a. Zoning  b. HPC  c. Engineering  d. Fire  e. Water  f. Sanitation  g. Parks  h. Environmental Health  2. For new commercial construction equal or greater than 9000 sf, you must conduct a blower  door test 2015 IECC C402.5.1.2 (as amended in Ordinance 40, 2016).  3. Manuals for all appliances and equipment must be compiled together in one location for the  owner.  4. In residential construction, a certificate must be permanently affixed on or in the electric panel  with the following information per 2015 IECC R401.3  a. List all insulation R values and fenestration U factors.  b. List types and efficiencies of all heating, cooling, and service water heating equipment.  5. Submit a complete set of as‐built drawings for the project.            6/12/2017    Page 27 of 28            Permit Process: What to Expect Schedule a Submittal Meeting  Once you have assembled all the drawings and documents required by the checklist, call to schedule a  Submittal Meeting. You will sit down with a Permit Coordinator who will go through the checklist with  you to make sure you application is complete. If it is not, you will be asked to come back another time  with the complete package. It is recommended to have a Pre‐Submittal Meeting prior to submittal with  a Permit Coordinator and a Plans Examiner so that you have a clear understanding of what you will need  to submit.  Permit Review  Once submitted, your permit will sit in the queue waiting for the various Review Agencies to look at it.  The Permit Coordinator will let you know which agencies will be reviewing and will be your point of  contact for status inquiries.   Receive Comment Letter  You will receive comments from review agencies as they review your permit.  You must wait until you  have received comments or a sign off from all relevant review agencies prior to submitting your  responses.  Create Response and Schedule a Re‐Submittal Meeting   Schedule a Re‐Submittal Meeting with the Permit Coordinator once you have addressed all of the  comments. Bring a copy of the comments along with your written response to each comment in both  physical (8 ½ x 11) and digital format (word doc). Each response should include a description of how the  comment has been resolved and which drawing or document has been revised. The Permit Coordinator  will go through this list item by item with you to ensure everything has been addressed before accepting  the revisions.  Permit Review  The Permit now goes back in the queue and the process continues until all Review Agencies have signed  off. You will then be contacted to pick up and pay for your permit.  Changes During Construction  If changes are made to the design such that the drawings no longer match the proposed work, contact a  permit coordinator. Depending on the scope of the change, a Change Order permit may be required; if  the changes are insignificant enough, it may be sufficient to simply submit as a clarification.      6/12/2017    Page 28 of 28