HomeMy WebLinkAboutFile Documents.225 Cottonwood Ln.0013.2017.ARBKMarkup Summary
Subject: PlanCheck
Page: 17.2.22_225 Cottonwood_Permit Set A-1.2 Your note states window to be
replaced but the existing floor
plan shows this as a door.
Please clarify. Provide header
detail if this was actually a door
and the existing opening is
changing.
17.2.22_225 Cottonwood_Permit Set A-1.2 (2)
Subject: PlanCheck
Page: 17.2.22_225 Cottonwood_Permit Set A-1.2 Provide a cut sheet or schedule
for the new proposed egress
window as this was not existing
and is shown as a door on the
existing floor plans. Provide a
header detail stamped by a
structural engineer if this is
changing.
Subject: PlanCheck
Page: 17.2.22_225 Cottonwood_Permit Set A-7.2 Recessed luminaires installed in
the building thermal envelope
are required to be sealed and IC
rated (IECC 402.4.5). Provide
cut sheet on the proposed fixture
that demonstrates compliance.
17.2.22_225 Cottonwood_Permit Set A-7.2 (1)
Subject: PlanCheck
Page: 17.2.22_225 Cottonwood_Permit Set A-l.l Handrails required on at least
one side of stair where there are
4 or more risers IRC 311.7.7
17.2.22_225 Cottonwood_Permit Set A-l.l (2)
Subject: PlanCheck
Page: 17.2.22_225 Cottonwood_Permit Set A-l.l Egress windows must meet the
requirements of IRC
310.1.1-310.1.4. Provide specs
or a schedule for all windows
being replaced and identify
which windows will be used for
egress. Call out any applicable
safety glazing or egress
hardware and give sill height for
required egress windows.
Your note states
window to be replaced
but the existing floor
plan shows this as a
door. Please clarify.
Provide header detail
if this was actually a
door and the existing
opening is changing.
Provide a cut sheet or schedule for
the new proposed egress window
as this was not existing and is
shown as a door on the existing
floor plans. Provide a header
detail stamped by a structural
engineer if this is changing.
Recessed luminairesinstalled in the buildingthermal envelope arerequired to be sealedand IC rated (IECC402.4.5). Provide cutsheet on the proposedfixture thatdemonstratescompliance.
Handrails required on
at least one side of
stair where there are
4 or more risers IRC
311.7.7
Egress windows must
meet the requirements
of IRC
310.1.1-310.1.4.
Provide specs or a
schedule for all
windows being
replaced and identify
which windows will be
used for egress. Call
out any applicable
safety glazing or
egress hardware and
give sill height for
required egress
windows.
Egress windows were initially shown with a
'swing' to show operability. I updated dwgs
removing this confusion. All egress windows and
doors to remain as such, even if being replaced.
This is existing egress door to remain. I updated
dwgs and note to clarify.
IC Rated/Sealed housing cut sheet provided, as
well as updated noted on RCP dwgs.
Handrail and note added to stair in DWG.
Handrail to follow IRC 311.7.7
All replacement windows to meet IRC
310.1.1-310.1.4. Window sizes and sill heights
to remain. Window schedule sheet has also
been added (A-5.1) showing cut sheets from
window manufacturer with proper insulation and
sizing numbers.
City of Aspen
Received
4/24/17
Building Department