HomeMy WebLinkAboutFile Documents.216 S Monarch St.0040.2018 (3).ACBKCottage
Construction Management Plan
1.0 General
1.1 Total Disturbance Area
NONE Interior Only (560 SF Leasable Space)
1.2 Table of contents
This List is a table of Contents
2.0 Project Introduction
2.1 Total Project Disturbance area
NONE
2.2 Project Vicinity Map
301 E Hopkins Street
Site Location
2.3 Description that includes:
2.3.1 Background information
Interior Only.
This construction project is the cottage building on the corner of
Hopkins and Monarch. We are just removing some internal walls that
are not structural. We will have an engineer look at them before
removing. The space is to be white boxed with existing finishes
2.3.2 Proposed Development Type
Commercial___________ Interior Only
3.0 Project Documentation
3.1 Describe the Permit Type, List Permit #’s and Include Copies of all Permits
04/17/2018
We are Applying for a “Interior Finish and Fixture Removal Permit” and a
“General Building Permit”
We do not have Permit Numbers because we are applying for a permit
We do not have copies of the permits because we are applying for permit.
3.2 Indicate project notification per CMP Manual
Will notify owners and business in 300 ft area
We have walked around with Notice to people on the Block and the
Block across from us and will do again 10 days before construction starts
3.3 Project Sign is Constructed and Posted
See Below
3.4 Contact List included for
3.4.1 Owner
Building – Katie Reed LLC Lex Tarumianz 970-618-5648
Lease Holder – Rob Ittner 970-948-7976
3.4.2 Contractor
Tim McMann – 970-948-9760
3.4.3 Site Supervisor
Tim McMann – 970-948-9760
4.0 Project Implementation
4.1 Dates of Construction
April 2018 to June 10 2018 (hope to be done before)
4.2 Hours of Construction
Under Guidelines of CMP Manual and City of Aspen Code
4.3 Construction Schedule
Will Know Better When we get Permits
Demo – End of April 2018
Light Electrical – May 2018
Mechanical – None
Wall and minor Construction – None
Finishes – May 2018
4.4 Describe Project Fencing
None N/A Interior Only
4.5 Site Map for Tree Protection Fencing/Tree Drip Line
None N/A Interior Only
4.6 Parks Issues – Driplines, Permits, Demo
None N/A Interior Only
5.0 Site Management
5.1 Right of Way Management Plan
None N/A Interior Only
5.2 Emergency Vehicle Access and Ordinance
None N/A Interior Only
5.3 Construction Parking Detail
None N/A Limited small vehicle street parking
5.4 Map Showing Locations (Staging Areas)
04/17/2018
Stage will happen mostly in the Space.
There will only be light car use and that will be
street parking for contractors like electricians
and builders (they will be encouraged to use
the Garage when possible)
We are trying to contract with the Crystal
Palace building for one of their parking spaces
Dumpster will only be used for one day pickups.
We are staging the light amount of waste in the
space until dumpster is dropped off and picked
up in a 24 hour permit. If we need to add a
street spot with the parking department we will
do that as needed for a day here or there. (see
Map)
6.0 Traffic Control
6.1 General
Project takes place inside in controlled Space so no traffic impacts.
6.2 Project Haul Routes
Per the CMP Manual
6.3 Weight and Size Limitations of Vehicles
Standard Vehicles
6.4 Construction vehicles Activities Defined
6.4.1 Specify Delivery Vehicle
None N/A
6.4.2 Maximum number of deliveries at a time
10
6.4.2.1 Hours of Delivery
Working hours of 7:30am to 5:30pm Monday through Friday and 9am
to 5pm on Saturdays
6.4.2.2 Exceptions to delivery schedule
None
6.5 Include Traffic Control Plan Prepared by a Certified Traffic Control Supervisor
None N/A
6.5.1 Site Access Location
6.5.2 Street/site signage control
6.5.3 Traffic control related to peak traffic hours and special event
6.5.4 Traffic flagging areas and hours
7.0 Pedestrian Protection
None N/A
04/17/2018
8.0 Sediment and Erosion Control
None N/A
8.1 Storm Water Pollution Prevention Plan
8.1.1 Erosion Control Measures
8.1.2 Mud Track Location
8.1.3 Tire Washing Location
8.1.4 Concreter Washing Location
9.0 Fugitive Dust Control
None N/A
9.1 Complete a fugitive dust control Plan
9.1.1 Sediment Tracking techniques
9.1.2 Water Trucks
9.1.3 24 hour Contact
10.0 Emissions
None N/A
10.1 Assure Proper Vehicle Maintenance
10.2 Opacity – no darker than 40%
11.0 Noise Suppression
Per City Code
11.1 Specify Noise equipment/methods used per CMP Manual
11.2 Noise modeling by noise engineer
11.3 Continued noise monitoring location and information
04/17/2018
The Cottage
Cooking School of Aspen
Rustique LLC
Building Permit #
____________________
General Contactor
Tim McMann
970-948-9760
Contact
Rob Ittner
970-948-7976
Emergency Phone
970-948-7976
In the event of an emergency call 911
04/17/2018