What structural welding is being
performed? Provide structural
plans and details and fully
signed special inspection
agreement form. Structural plans
should have special inspection
program.
IRC Building Description Form.pdf (1)
Page: 1.1
File Name: Permit Set_032817.pdf
Subject: PlanCheck
Author: nickt
Color:
Make your signature more
visible on your stamp on each
page.
Permit Set_032817.pdf (11)
Page: 1.1
File Name: Permit Set_032817.pdf
Subject: PlanCheck
Author: nickt
Color:
Provide the lab data from the
asbestos test as well as an
asbestos abatement clearance
report.
Page: 3.3
File Name: Permit Set_032817.pdf
Subject: PlanCheck
Author: nickt
Color:
Provide sheet 6.1. Must include
dimensioned stair details. Rise,
run, open riser opening size,
framing, handrails with returns,
and guards. If glass guards are
used, show method of support
that will resist 200 lb load.
Page: 3.6
File Name: Permit Set_032817.pdf
Subject: PlanCheck
Author: nickt
Color:
You are removing the drywall as
part of your asbestos abatement
and have details suggesting that
the new envelope tightness will
be increased. Provide exterior
air to the fireplace per 2009 IRC
R1006.
Unit #:
MC 2009 IPC 2009 IFGC 2009 IECC 2009 IFC 2011 NEC
___ YES NFPA _____
th Bolting ____Epoxy Anchors ____Structural Steel Welding
Micropiles _____Other (specify): ______________________ Table ____ResCheck Performace ____ResCheck UA Tradeoff
_sq ft Existing ______sq ft New Spa _____ Pool ____
Drive
ollwood Subdivision
her Kroeger
Drive
x
What structural
welding is being
performed? Provide
structural plans and
details and fully signed
special inspection
agreement form.
Structural plans should
have special
inspection program.
1.1
Make your signature
more visible on your
stamp on each page.
Provide the lab data from the asbestos
test as well as an asbestos abatement
clearance report.
CD
16.1
2 40'-7"
EXISTING TILETO REMAINNEW STAIR
15.1 15.1
14.1
Provide sheet 6.1.
Must include
dimensioned stair
details. Rise, run,
open riser opening
size, framing,
handrails with returns,
and guards. If glass
guards are used, show
method of support that
will resist 200 lb load.
B
C16'-51/2"1'-51/2"10'-8"51/2"4'-31/2"12'-2"NEW LINEARING HEARTH
EPURPOSED
OOD MANTEL
EXISTING WOOD
FIREPLACE
You are removing the
drywall as part of your
asbestos abatement
and have details
suggesting that the
new envelope
tightness will be
increased. Provide
exterior air to the
fireplace per 2009 IRC
R1006.
Signed attached inspection form and
signed structural drawings
All stamped images have been
replaced
All tests and results are attached
Sheet 6.1 updated and form attached for
guard support
Vent added
Received
6/6/17
Page: 3.6
File Name: Permit Set_032817.pdf
Subject: PlanCheck
Author: nickt
Color:
New hearth extension must
comply with manufacturer's
instructions if the fireplace is
factory built. If fireplace is site
built, it must be 20" deep and
extend to each side of the
opening at least 12" and it must
be supported entirely by
non-combustible structure and
materials all the way to grade.
2009 IRC R1001.9 and
R1001.10
Page: 3.6
File Name: Permit Set_032817.pdf
Subject: PlanCheck
Author: nickt
Color:
Door to washer/dryer closet
must have a minimum 100
square inch opening for makeup
air (2009 IMC 504.5).
Page: 3.9
File Name: Permit Set_032817.pdf
Subject: PlanCheck
Author: nickt
Color:
New cans in insulated ceiling
must be IC rated and sealed and
gasketed.
Page: 4.1
File Name: Permit Set_032817.pdf
Subject: PlanCheck
Author: nickt
Color:
New window at stairs must be
safety glazed (2009 IRC
R308.4).
Page: 5.2
File Name: Permit Set_032817.pdf
Subject: PlanCheck
Author: nickt
Color:
LED cans recessed into faux
beams must be listed for this
type of installation. Provide
specs. Non-IC type cans must
be 1/2" from combustible
materials; IC type cans may
contact combustibles (2014 NEC
410.116).
3 16'-51/2"28'-55/8"1'-51/2"10'-8"51/2"16'-0"40'-7"4'-31/2"15.1
34.2
HARDWOODROUGHOUT
BASEBOARDROUGHOUT
NEW LINEARFLOATING HEARTH
NEW REPURPOSEDWOOD MANTEL
EXISTING WOODFIREPLACE
GREAT ROOM
DECK
0
New hearth extension must comply with
manufacturer's instructions if the fireplace is
factory built. If fireplace is site built, it must be
20" deep and extend to each side of the
opening at least 12" and it must be supported
entirely by non-combustible structure and
materials all the way to grade. 2009 IRC
R1001.9 and R1001.10
XX
X
FW/D
51/2"11'-0"51/2"7'-1"31/2"2'-0"31/2"
NEW TILE FLOORING ANDNEW TILE AT SHOWERWALLS
E HEATER TO BEAND VENTED ATCLOSET BASE
NEW TILE FLOORIN AT KITCHE
NEW HARDWOODFLOORING
CENTER NEW WINDOWON STAIR OPENING
MASTER BEDROOM
MASTER CLOSET
WET BAR
MASTER BATH
W2
STAIRW2
51/2"5'-21/8"31/2"3'-11/4"NEW BATH PLAN
REFERNCE DRAWINGS BYACCENTS ON CABINETS
ETS REFERNCE
GS BY ACCENTSON CABINETS
Door to washer/dryer
closet must have a
minimum 100 square
inch opening for
makeup air (2009 IMC
504.5).
1
GENERAL LIGHTING NOTES:
1. ALL NEW LIGHT CANS INSTALLED TO BE HIGH EFFIC
New cans in insulated
ceiling must be IC
rated and sealed and
gasketed.
201
New window at stairs
must be safety glazed
(2009 IRC R308.4).
AB
X12 FAUX WOODMS W/ RECESSED
LED LIGHTS;SEE DETAIL 1/7.3
EXISTING WOOD BEAMWRAPPED W/ 8X24 NEW
FAUX WOOD BEAM;SEE DETAIL 1/7.3
LED cans recessed
into faux beams must
be listed for this type
of installation. Provide
specs. Non-IC type
cans must be 1/2"
from combustible
materials; IC type
cans may contact
combustibles (2014
NEC 410.116).
Structural details attached,
hearth revised
Vent added to door
Specs attached
Noted
Specs attached
Received
6/6/17
Page: 7.1
File Name: Permit Set_032817.pdf
Subject: PlanCheck
Author: nickt
Color:
Revise details on 7.1, 7.2 and
7.4 to indicate which elements
are existing and which are new.
Are these details here to show
proposed insulation after the
drywall is removed for the
asbestos abatement?
Page: 8.2
File Name: Permit Set_032817.pdf
Subject: PlanCheck
Author: nickt
Color:
Detail how the new hearth is
supported.
DESIGN CORPSALIUS
DESIGN CORPSALIUS
ASPEN, COKROEGER REMODELMTEN/A
ISSUE
PROJECT No:DRAWN BY:
DRAWING SET267 ROARING FORK DRIVECOPYRIGHT 2017 ALIUS DESIGNCORPS LLC. ALL RIGHTS RESERVED
FLOOR ASSEMBLIES &DETAILS
7.1
NOT FOR CONSTRUCTION
3/29/2017SCHEMATIC5/8"1'-2"3/4"3/4"5/8"1'-2"3/4"3/4"5/8"1'-2"3/4"3/4"1"6"2"4"5/8"1'-2"3/4"1 1/2"3/4"5/8"11 7/8"3/4"3/4"T&G WOOD FLOORING -SEE INTERIOR FINISHSCHEDULEFOR SPECIES AND FINISH
TILE FLOORING ANDSETTING BED - SEEINTERIOR FINISHSCHEDULE FOR TILE
¾" PLYWOOD SHEATHING
¾" PLYWOOD SHEATHING6" SOUND-ATTENUATIONBATTS @ LIVING SPACES
JOISTS RE: STRUCT.
5/8" GYP. BD. @ LIVINGSPACES
STAYSWASHED GRAVEL - MIN. 6"
UNDISTURBED SOILOR COMPACT FILL
4" CONC. SLAB
R-11 RIGID INSULATION
CARPET ATOP CARPETPAD-SEE INTERIOR FINISHSCHED.FOR CARPET TYPE
¾" PLYWOOD SHEATHING
1½" RADIANT SLABREINFORCED W/ W.W.M.
TILE FLOORING ANDSETTING BED - SEEINTERIOR FINISHSCHEDULE FOR TILE
6" SOUND-ATTENUATIONBATTS OVER LIVINGSPACE
JOISTS RE: STRUCT.
5/8" TYPE 'X' GYP. BD.
STAYSFOUNDATION WALLPER STRUCTURAL
BITUMINOUSWATERPROOFMEMBRANE
2" POLYISORIGID INSULATION
WASHED GRAVEL -MIN. 6"
1½" RADIANT SLABREINFORCED W/ W.W.M.
FLOOR JOISTS PERSTRUCTURAL
3/4" PLYWOOD
4" CONCRETE SLAB W/RADIANT HEAT (PERPLAN) SLOPE TODRAIN
2x8 SILL PLATE W/ 1/2"DIA. ANCHOR BOLTS
2x6 SILL PLATE
3/4" PLYWOOD
2x FURRING
FINISH FLOOR - SEE PLANS
R-42 SPRAY-IN RIGIDCLOSED-CELLINSULATION @CRAWLSPACE (ACTS ASVAPOR BARRIER)
¾" PLYWOOD SHEATHING
6" SOUND-ATTENUATIONBATTS @ LIVING SPACES
JOISTS RE: STRUCT.
5/8" GYP. BD. @ LIVINGSPACES
STAYS
R-42 SPRAY-IN RIGIDCLOSED-CELLINSULATION @CRAWLSPACE (ACTS ASVAPOR BARRIER)
LIVING SPACECRAWL SPACE
LIVING SPACECRAWL SPACE
6" SOUND-ATTENUATIONBATTS @ LIVING SPACES
JOISTS RE: STRUCT.
5/8" GYP. BD. @ LIVINGSPACES
STAYS
R-42 SPRAY-IN RIGIDCLOSED-CELLINSULATION @CRAWLSPACE (ACTS ASVAPOR BARRIER)
LIVING SPACECRAWL SPACE
R-28 SPRAY-IN RIGIDCLOSED-CELLINSULATION (ACTS ASVAPOR BARRIER)
R-42 SPRAY-IN RIGIDCLOSED-CELLINSULATION (ACTS ASVAPOR BARRIER)
MAINTAIN R-28INSULATION @ RIMJOISTS
SEAL JOIST CAVITIES PER'09 IECC CHAPTER 4
R-28 SPRAY-IN RIGIDCLOSED-CELLINSULATION (ACTS ASVAPOR BARRIER)
1" THICK FAUX WOODBEAM; SEE PLAN FORSIZING AND LOCATION
4" RECESSED LED LIGHT
FRAMED FLOOR W/ TILE
FRAMED FLOOR W/ CARPET
1 ½" = 1'-0"
7.1
FRAMED FLOOR W/ WOOD
SLAB ON GRADE @ CRAWLSPACES
F1
F2
F3
F5 1 ½" = 1'-0"1 ½" = 1'-0"
1 ½" = 1'-0"
T. O. PLYWOOD88'-0" or 100'-0" or 111'-0"
1 ½" = 1'-0"F41 HOUR RATED FRAMED FLOOR W/ TILE OVER11/2" SLAB
DESIGN BASED ON GA FILE NO. FC 53101 HOUR RATING40 TO 44 STC RATINGFIRE TESTING: UL R 1319-47, 5-8-63 UL DESIGN L508
UL DESIGN L508
T. O. FIN. FLOOR88'-03/4" or 100'-03/4" or 111'-03/4"
T. O. PLYWOOD88'-0" or 100'-0" or 111'-0"
T. O. FIN. FLOOR88'-03/4" or 100'-03/4" or 111'-03/4"
T. O. PLYWOOD88'-0" or 100'-0"
T. O. FIN. FLOOR88'-03/4" or 100'-03/4"
T. O. SLAB93'-111/4"
T. O. FIN. FLOOR111'-2 1/4"
T. O. PLYWOOD111'-0"
1 ½" = 1'-0"THRESHOLD @ EXT. SLAB1
1 1/2" FLOOR DETAIL & ASSEMBLY TEMPLATE
T. O. PLYWOOD100'-0" or 111'-0"
2 INSULATION DETAIL @ RIM JOIST1 ½" = 1'-0"
3 LIGHTING DETAIL @ FAUX BEAM1 ½" = 1'-0"
Revise details on 7.1,7.2 and 7.4 to indicatewhich elements areexisting and which arenew. Are these detailshere to showproposed insulationafter the drywall isremoved for theasbestos abatement?
WOOD MANTEL, VERIFY
NEW FLOATING HEARTH
Detail how the new
hearth is supported.
Noted new and existing
Structural drawings signed and
attached
Received
6/6/17