TRANSMITTAL
Project: 21811.00 – Foster Lot 2 (0081.2019.ARBK)
Subject: Change Order #2 Building Dept Comment Response
Date: 03 July 2019
To: Justin Hahn, Plans Examiner, City of Aspen
From: Amanda Christianson, AIA
CC: Phil Le Hue, Permit Coordinator, City of Aspen
Via: Email
Attachments: See Below
If you do not receive all attachments listed below please call immediately.
Dear Justin,
Per your instruction, we have compiled the requested revisions to address your comments received by
R+B on June 20, 2019. The sheets included are:
- M0.0
- M0.1
- M0.2
- M0.3
- M1.1
- M2.0
- M2.1
- M2.2
- M2.3
- M3.0
- M3.1
- P2.0
- P2.1
- P2.2
- P2.3
They resolve your comments in the following manner.
Comment 1:
- P2.1, P2.2 and P2.3 have had their snowmelt zones updated to match the architectural areas
on A1.2.
- You will be revising the REMP worksheet to be the 2009 version instead of the 2015 version
and reconciling all calculations to match our documents.
Comment 2:
- All sheets listed above have been stamped and signed by the engineer of record.
Please contact either Delvon Nemechek or me should you have questions about the submitted
content. We look forward to your review.
Sincerely,
Amanda Christianson, AIA
720-263-6748