HomeMy WebLinkAboutFile Documents.710 E Durant Ave.0015.2019.ACBKWe are getting ready to begin a service upgrade project for Unit W-10 at Durant Mall in Aspen and will need to
get a 3" core drill approved in order to run new conduit closer to the unit. Eric Pekkala is GC for the project and
will also be performing the core drill - given that the core and location are approved. Attached are photos of
the proposed location for the core drill.
Could you please review this and provide approval if possible. (There is only one core - these are descriptions
A 3" core drilled hole 45" away from the existing supply hole reference directly under the electrical box.
the cabinet.
03/15/2019
03/15/2019
03/15/2019
03/15/2019
03/15/2019
03/15/2019
03/15/2019
03/15/2019
03/15/2019
We are getting ready to begin a service upgrade project for Unit W-10 at Durant Mall in Aspen and will need to
get a 3" core drill approved in order to run new conduit closer to the unit. Craig Smith is GC for the project and
will also be performing the core drill - given that the core and location are approved. Attached are photos of
the proposed location for the core drill.
Could you please review this and provide approval if possible. (There is only one core - these are descriptions
from the dierent angles of photo).
A 3" core drilled hole 6" o of the West wall and 45" away from the existing supply hole reference
A 3" core drilled hole 45" away from the existing supply hole reference directly under the electrical box.
A 3" core drilled hole 6" o of the West wall and 45" away from the existing supply hole reference directly above
the cabinet.
03/15/2019
03/15/2019
03/15/2019
03/15/2019