HomeMy WebLinkAboutFile Documents.729 W Francis St.0090.2019 (3).ARBK
John Walker Builder
G&B LLC UNIT 1 Residence Remodel
729 Francis Street, Aspen, CO 81611
Construction Management Plan
To: City of Aspen Building Department
130 South Galena St
Aspen, CO 81611
From: John Walker Builder
PO Box 10255
Aspen, CO 81612
(970) 379-7598
jwalk22401@aol.com
1.0 General:
1.1 Approximately One Thousand Three Hundred Seventy One (1371) square
feet of interior space. This work includes demo/removal of existing interior
finishes and a half wall, new kitchen and bathrooms cabinets/countertops
New flooring including hardwoods, carpet and tile.
1.2 Table of Contents:
http://www.aspenpitkin.com/Portals/0/docs/businessnav/GradeExcavateRO
W/Construction%20Management%20Checklist.pdf
04/26/2019
2.0 Project Introduction:
2.1 Approximately One Thousand Three Hundred Seventy One (1371) square
feet of interior space.
2.2 Project vicinity map
2.3 Interior remodel of private residence at 729 W Francis Street Unit 1. Interior
spaces per plans attached. New kitchen and bathroom cabinets/countertops.
New flooring/carpet/tile. Remove 1/2 wall. Scope of this remodel will take
approximately 2 months to complete starting demo upon receipt of demo
permit, and interior remodel upon receipt of building permit. Proposed
Development is a complete remodel.
3.0 Project Documentation:
3.1 Permit Types: none have been issued thus far. Anticipated permits to
include demo, construction, plumbing and electrical will be applied for as
needed.
3.2 Neighbors within 300 feet will be notified of the construction per City of
Aspen CMP Manual guidelines with the first public notification occurring no
later than 10 days prior to the start of construction with a project sign
readable from street or driveway and shall meet criteria in City Municipal
Code 26.510.030B4. The project sign will include public notification of
description of work to be performed within construction phase, list any traffic
and/or pedestrian concerns, and describe hauling/staging operations. The
project sign will also include information of the kinds of equipment, expected
noise levels and durations of loud work per City of Aspen CMP Manual
guidelines.
3.3 Project sign will be constructed and posted with contractors contact
information and other required project information. Appendix A: Required
Construction Sign.
3.4 Contact List
Owner: G&B LLC N Hernandez 970-379-5401
General Contractor: John Walker Builder (970) 379-7598
Site Supervisor: John Walker (970) 379-7598
Safety Officer: John Walker (970) 379-7598
Traffic Officer: John Walker (970) 379-7598
Erosion Control: John Walker (970) 379-7598
04/26/2019
4.0 Project Implementation:
4.1 Dates of Construction: Construction is expected to last approximately 2
months (June 1 – Aug 1 2019) but may adjust depending on timing of Demo
& Building permit issuance and receipt. Construction will occur on approved
dates Monday through Saturday.
4.2 Hours of Construction: Construction activity will only occur during the
allowed hours of 7:30AM and 5:30PM Monday – Friday and 9:00AM –
5:00PM on Saturdays. No construction will occur on non-approved dates
during project duration.
4.3 Construction Schedule: Anticipate approximately 2 months of construction.
Please refer to attached Appendix B: Construction Phasing Plan.
4.4 Adjoining Properties: Excavation N/A
4.5 Project Fencing N/A Please refer to Site Plan sheet in attached Project
Plans.
4.6 Project Fencing N/A. Please refer to Site Plan sheet in attached Project
Plans.
4.7 Parks Issuances N/A. Project shall be oriented to minimize harm to all
aspects of the City of Aspen’s natural environment, including tree protection
as needed.
5.0 Project Management:
5.1 Parking Management (Appendix C: Site Plan): Parking for John Walker
Building employees and subcontractors will utilize the on-property parking
spaces. Any potential Right of Way (ROW) encroachments for parking will
be avoided, and will submit for approval with the Engineering Department if
needed.
5.2 Emergency vehicle access Ordinance 35: Project shall maintain continuous
emergency vehicle access, on and around site, including but not limited to
police, fire, and ambulance services
.
5.3 N/A
5.4 Site Map showing location of Staging, Material, Portable Toilet, Waste
Management, and Recycling (no trailer needed): Appendix C: Site Plan
04/26/2019
6.0 Traffic Control:
6.1 N/A
6.2 Designated haul routes will be followed. Appendix D: Designated Haul
Routes
6.3 Weight and Size limitations: maximum vehicle weight will not exceed
10,000lbs.
6.4 Any traffic control required for deliveries will be coordinated with the City of
Aspen Engineering Department. Deliveries will not be scheduled outside of
approved hours of construction. No more than one delivery truck can be
accommodated at any time. Deliveries will be unloaded via the driveway into
either garage or front door/bridge way during early morning hours, except
when deliveries required outside of early morning hours but within approved
hours of construction.
6.5 A Traffic Control Plan is not included as road blockages or traffic stoppages
are not scheduled or anticipated due to the limited scope and nature of this
interior remodel project.
8.0 Sediment and Erosion Control: N/A
9.0 Fugitive Dust Control: N/A
10.0 Emissions:
10.1 All vehicles and equipment used on site will be properly maintained such
that the engines will function within manufacturer’s standards or parameters/
10.2 Emissions from diesel engines shall be of a shade or density no darker
than 40% opacity.
11.0 Noise Suppression: per code
11.1 Construction noise will be limited to 70 decibels at the property line
whenever possible. Construction noise not expected to be an issue for
activity contained indoors.
11.2 Any loud or obtrusive work will be completed during the approved hours
of 9AM to 5PM (Monday through Friday only). Neighbors will be notified 3
days in advance when applicable.
Appendices & Attachments:
Project Plans
Appendix A: Required Construction Sign
Appendix B: Construction Phasing Plan
Appendix C: Site Plan
Appendix D: Designated Haul Routes
04/26/2019
APPENDIX A: REQUIRED CONSTRUCTION SIGN
24 in
18 in
PROJECT: 729 FRANCIS ADDRESS: 729 W FRANCIS STREET, ASPEN CO 81611 PERMIT NO: GC: JOHN WALKER BUILDER / 970 379 7598 EMERGENCY CONTACT: NOELLE 970 379 5401 NICOLE 970 948 5494
PROJECT DESCRIPTION: INTERIOR REMODEL PARTNER: G+B, LLC WWW.MATTERINTERIORS.COM
04/26/2019
APPENDIX B: CONSTRUCTION PHASING PLAN
729 W Francis
Phasing Plan
Task Name June Jul Aug
1 Mobilize 3-Jun
2 Selective Demolition 3-Jun
3 Plumbing Relocation 7-Jun
4 Floor Leveling + Skinny Slab 10-Jun
5 Electrical Rough-In 17-Jun
6 Plumbing Rough-In 17-Jun
7 Rough-In Inspection 24-Jun
8 Drywall Repair 25-Jun
9 Install Wood Flooring 26-Jun
10 Install Cabinets 1-Jul
11 Tile Install 1-Jul
12 Countertop Install 1-Jul
13 Shower Enclosure 3-Jul
14 Interior Trim 3-Jul
15 Paint Finishes 8-Jul
16 Electrical Trim Out 8-Jul
17 Plumbing Trim Out 8-Jul
18 Carpet 15-Jul
19 Final Clean 17-Jul
20 Final Inspection 22-Jul
21 Demobilize 29-Jul
04/26/2019
APPENDIX C: SITE PLAN
04/26/2019
APPENDIX D: DESIGNATED HAUL ROUTE
04/26/2019