CONSTRUCTION MANAGEMENT PLAN
CHATEAU ASPEN, UNIT 9
630 EAST COOPER STREET,
ASPEN, COLORADO
CONTACT LIST:
owner: 630 E. Cooper 9 Associates, LLC
STEPHEN AND TAMAR OLITSKY 215-990-6930
contractor and site supervisor: BARRY LINDAHL 970-379-2244
a state certified safety officer, a state certified traffic control officer:
NOT APPLICABLE
state certified erosion control representative,
NOT APPLICABLE
city of aspen 920-5000
pitkin county 920-5200
fire department 925-5532
police department, 920-5400
utility companies:
natural gas, black hills energy 888-890-5554
electric 920-5148
water 920-5110
hospital contact information 925-1120
Emergency 911 911
Roaring Fork Transit Authority (RFTA), 384-4965
aspen school district 925-3760
01/08/2019
2
CONSTRUCTION MANAGEMENT PLAN
CHATEAU ASPEN, UNIT 9
630 EAST COOPER STREET,
ASPEN, COLORADO
2.2 LOCATION MAP
2.3 PROJECT DESCRIPTION
INTERIOR REMODEL
The interior of this +/- 930 sf unit is to receive a light remodel. Work does not
include exterior adjustments to the windows, building skin, or exterior doors.
Interior work will include (plans follow):
*adding a layer of drywall to the ceiling to increase acoustical performance
*new cabinets, countertops and interior doors
*replace existing flooring and ceramic tile
*some new electrical items. Existing panel will not be modified.
(radiant flooring mat, on demand water heater, LED lighting, add
airconditioning: mini-split system)
north
Unit 9
Coope
r
A
v
e
n
u
e Spring Streetalley
sidewal
k sidewalkSITE PLAN
parking
s
p
a
c
e
s
t
u
c
k
u
n
d
e
r
b
u
i
l
d
i
n
g
parkin
g
exterior
c
o
r
r
i
d
o
r
a
n
d
s
t
a
i
r
s
630 E. Cooper
Project Vicinity Map
01/08/2019
3
CONSTRUCTION MANAGEMENT PLAN
CHATEAU ASPEN, UNIT 9
630 EAST COOPER STREET,
ASPEN, COLORADO
*replace faucets
all plumbing to remain in existing locations. No modification of supply or
drain lines.
*replace appliances with energy efficient models
*Add insulation to exterior walls
*add window coverings
*replace fireplace with direct vent gas appliance
*modify closets and storage (limited demolition of framing, drywall)
*paint
Drywall has been tested and does not include asbestos. Report is attached.
3.1 PERMITS / OTHER DOCUMENTS
The contractor WILL maintain all permits that apply to the construction project AT
THE SITE.
BUILDING PERMIT APPLICATION:
ASBESTOS TEST:
DEMOLITION PERMIT APPLICATION:
01/08/2019
4
CONSTRUCTION MANAGEMENT PLAN
CHATEAU ASPEN, UNIT 9
630 EAST COOPER STREET,
ASPEN, COLORADO
3.2 PUBLIC NOTIFICATION
A project update shall be provided to the public on a basis no less than monthly,
via newspaper advertisement and on-site notices.
The first public notification will occur no later than 10 days prior to construction.
The update shall include a description of the current project phase, list any traffic
and/or pedestrian concerns, and describe hauling/staging operations. Additionally
it shall include information of the kinds of equipment, expected noise levels and
durations of loud work.
On site notice and advertising shall list a phone number where the foreman can
be prior to and during the project.
The above notification shall specifically be distributed to neighbors located within
300 feet of the project property.
The Plan shall designate a project representative, date, and time for a required
preconstruction meeting. The purpose of the meeting is to discuss the project
and summarize the project specific Construction Management Plan. The
contractor and subcontractors are required to attend the meeting. Utility
personnel, applicable City departments, the Roaring Fork Transit
Authority, neighboring property owners, and the Aspen School District shall also
be notified.
3.3 PROJECT SIGN A project sign will be constructed and posted that includes
the items shown in Appendix A: Required Construction Sign. The sign shall be
posted in a location where it is readable from the street or driveway and shall
meet criteria in City Municipal Code 26.510.030B4.
3.4 CONTACT DESIGNATION The Plan shall have a contact list with associated
phone numbers located at the front of the document. The list will include: the
owner, contractor appointed overall site supervisor, a state certified safety officer,
a state certified traffic control officer, and a state certified erosion control
representative. Other information shall include city and county phone numbers,
fire department, police department, Roaring Fork Transit Authority (RFTA),
school district, and all applicable utility company contact information. The contact
list should include hospital contact information and the Emergency 911 reminder.
01/08/2019
5
CONSTRUCTION MANAGEMENT PLAN
CHATEAU ASPEN, UNIT 9
630 EAST COOPER STREET,
ASPEN, COLORADO
4.0 PROJECT IMPLEMENTATION
4.1 DATES OF CONSTRUCTION
Begin work: April 1, 2019, or dates when HOA permit
Complete work : June 31, 2019, or dates required by City/HOA
no work will be in a ROW.
4.2 HOURS OF CONSTRUCTION
7:30am – 5:30pm Monday through Friday and 9am – 5pm on Saturday.
No construction on Sundays,
4.3 SEQUENCE (PHASING) OF CONSTRUCTION
Demolition week one April 1 start
Framing week one/two
Electrical/Plumbing modification week two/three
Drywall week four
cabinets week five
finishes week six/seven May 25 finish
4.4 ADJOINING PROPERTIES
This is an interior condo remodel. Adjacent owners will be notified and contact
with our project manager/superintendent will be provided
4.5 PROJECT FENCING
This is an interior condo remodel, no fencing will be provided.
4.6 PUBLIC HEALTH AND WELFARE
Care will be given to protect public when entering , exiting, and working on the
property.
01/08/2019
6
CONSTRUCTION MANAGEMENT PLAN
CHATEAU ASPEN, UNIT 9
630 EAST COOPER STREET,
ASPEN, COLORADO
4.7 NATURAL ENVIRONMENT
This is an interior condo remodel. The natural environment will be considered.
5.0 SITE AND RIGHT OF WAY MANAGEMENT
5.1 RIGHT OF WAY MANAGEMENT PLAN
Trucks bringing supplies, and personnel will use Highway 82 via Original Street
to Cooper Avenue. Waste material will exit the same way.
A waste container will be place on site for a few days during demolition and
removed thereafter.
Parking by workers who do not take mass transit will be on the streets in paid
parking. Efforts will be made to carpool workers and supplies when possible.
5.2 EMERGENCY VEHICLE ACCESS AND ORDINANCE 35
The contractor shall maintain continuous emergency vehicle access, on and
around site, including but not limited to police, fire, and ambulance services. This
includes projects adjacent to roads and alleys.
5.3 CONSTRUCTION PARKING DETAILS
A covered waste container will be place on site in one of the off-street spaces for
a few days during demolition and removed thereafter.
Parking by workers who do not take mass transit will be on the streets in paid
parking. Efforts will be made to carpool workers and supplies when possible.
01/08/2019
7
CONSTRUCTION MANAGEMENT PLAN
CHATEAU ASPEN, UNIT 9
630 EAST COOPER STREET,
ASPEN, COLORADO
5.4 STAGING AREAS
staging area location will be in the private parking spaces on-site adjacent to the
alley, without blocking public flow on the alley.
Four trips/day are anticipated to the site. Duration of vehicles on the site
averaging one half hour.
No right of way encroachments are needed, nor are any storage of material on
the exterior of the site anticipated.
5.6 SITE PLAN
This is and interior remodel. No exterior work is required.
5.7 WASTE MANAGEMENT
Compliance with the City of Aspen requirements for recycling of materials, both
conventional and construction related shall be done according to this document
and City of Aspen Municipal Code Title 12.
Project site conventional recycling of co-mingled materials (plastics #1-#7, tin,
aluminum, and glass), and cardboard shall have an assigned space/area and be
separated on-site during the project.
NO disposal of electronic waste, fluorescent light bulbs, hazardous waste or yard
waste. These materials may not be disposed of in the trash.
During the demolition phase of a project, deconstruction related activities are
required (recycling and/or salvaging of material such as wood products, drywall,
flooring, etc.).
Concrete and scrap metals shall be sorted and kept separate on-site and must
have an assigned space/area.
Per municipal code (12.08.010), any dumpster or other trash receptacle that is
used for food refuse must be constructed in such a manner as to render it bear
proof.
01/08/2019
8
CONSTRUCTION MANAGEMENT PLAN
CHATEAU ASPEN, UNIT 9
630 EAST COOPER STREET,
ASPEN, COLORADO
All containers shall be adequately covered at all times until transferred to the
landfill.
The City of Aspen municipal code states it shall be unlawful to permit
accumulated debris, litter, or trash on any construction site to blow or scatter onto
adjoining properties (12.04.020).
12 An onsite hazardous material spill cleanup kit shall be required, as specified
by the City Engineer, that contains, at a minimum, a 25 pound bag of Floor-Dri
(or equal), absorbent pads, and other spill kit materials.
All waste containers will be located adjacent to the alley.
6.0 TRAFFIC CONTROL
6.1 GENERAL
All traffic control operations shall be managed by the designated certified traffic
control supervisor.
6.2 HAUL ROUTES
The City of Aspen has designated specific project haul roads throughout the City
and these will be complied with as described above.
The project shall follow the designated routes and specify any additional routes
necessary to complete hauling operations. Project haul routes shall be oriented
to minimize traffic congestion and maximize pedestrian safety.
6.3 ONSITE VEHICLE LIMITATIONS
All construction related vehicle activities are:
Delivery of waste containers
Removal of waste
Delivery of material
Delivery and removal of workers
Maximum vehicle weights and sizes shall be specified.
Waste vehicles shall be limited to normal garbage truck size.
01/08/2019
9
All other vehicles are limited to small panel trucks and pickup truck sizes.
CONSTRUCTION MANAGEMENT PLAN
CHATEAU ASPEN, UNIT 9
630 EAST COOPER STREET,
ASPEN, COLORADO
6.4 DELIVERY REQUIREMENTS
Traffic control required for deliveries shall be fully coordinated with the City of
Aspen Engineering Department.
Roads will not be closed under any circumstances
The maximum number of delivery vehicles onsite will not be greater than two at
any time, during normal working hours listed above.
Delivery and Heavy Duty Vehicles must have a visible sign on the vehicle that
specifies the project contractors name and phone number.
Delivery vehicles and all other onsite vehicles shall not allowed to idle for more
than five (5) minutes.
6.5 TRAFFIC CONTROL PLAN
This is a small interior remodel. Traffic control is not required.
7.0 PEDISTRIAN PROTECTION
7.1 GENERAL
The Plan shall comply with pedestrian safety per City code 21.04.060, MUTCD
Chapter 6D, the Americans with Disability Act, and IBC Chapter 33.
7.2 LIMITATIONS
No Sidewalk closures will occur.
8.0 SEDIMENT AND EROSION CONTROL
8.1 REQUIREMENTS
This is a small interior remodel. Erosion control is not required.
8.2 SMUGGLER MOUNTAIN RESTRICTIONS
not applicable
01/08/2019
10
CONSTRUCTION MANAGEMENT PLAN
CHATEAU ASPEN, UNIT 9
630 EAST COOPER STREET,
ASPEN, COLORADO
9.0 FUGITIVE DUST CONTROL
9.1 FUGITIVE DUST CONTROL PLAN
This is a small interior remodel. Fugitive dust control is not required.
9.2 REQUIREMENTS
This is a small interior remodel. Fugitive dust control is not required.
10.0 EMISSIONS
10.1 GENERAL
All vehicles and equipment used on site will be properly maintained such that the
engines will function within manufacture’s standards or parameters.
10.2 EMISSIONS FROM DIESEL POWERED ENGINES
Emissions from diesel engines operated within the City of Aspen shall be of a
shade or density no darker than 40% opacity, except for starting motion no longer
than 10 seconds or for stationary operation not exceeding 10 seconds.
11.0 NOISE SUPRESSION
11.1 GENERAL
This is a small interior remodel. Doors and windows shall remain closed during
work to reduce noise.
11.2 NOISE SUPPRESSION PLAN
This is a small interior remodel. Doors and windows shall remain closed during
work to reduce noise.
The use of radios on the site before 8:00 am is not allowed. Only classical music
will be played on KAJX 91.5 FM or from Colorado Public Radio.
01/08/2019
11
The site shall be posted with notices to inform workers, including sub-contractors,
about the basic noise requirements, as well as specific noise restrictions, to the
project
CONSTRUCTION MANAGEMENT PLAN
CHATEAU ASPEN, UNIT 9
630 EAST COOPER STREET,
ASPEN, COLORADO
11.4 NOISE LEVEL MEASUREMENTS
11.5 CONTINUNED NOISE MONITORING
11. 6 SPECIFIC RESTRICTIONS RELATED TO MANUFACTURING ON SITE
This is a small interior remodel.
PROJECT SIGN (GREEN BACKGROUND COLOR AS REQUIRED):
PROJECT NAME UNIT 9, CHATEAU ASPEN REMODEL
BUILDING PERMIT #
General Contractor: TARGET CONSTRUCTION
Contact BARRY LINDAHL 970-379-2244
24 Hour Emergency Contact
BARRY LINDAHL
970-379-2244
01/08/2019
12
CONSTRUCTION MANAGEMENT PLAN
CHATEAU ASPEN, UNIT 9
630 EAST COOPER STREET,
ASPEN, COLORADO
Salvage
salvage materials from this project prior to include:
doors, windows, casing, toilets, sinks, fixtures, cabinets, appliances
Facility or Salvage company receiving material:
Receipt attached: no
Source Separation
Do you plan to source separate any materials for delivery to a recycling facility?
Yes/No
(e.g. separation of material such as wood, concrete, metal into separate bins)
Do you plan any on-site reuse activities for this project (e.g. reuse of wood forms
for concrete, on-site crushing of concrete for on-site use, use of reusable
containers or pallets for material deliveries, etc.)? NO
Disposal at landfill Will any materials be disposed of (not recycled or salvaged) at
the landfill? Yes No
Estimate the number of tons of material to be taken to the landfill for disposal :
Construction & Demolition Summary Report (CDSR)
Deliver completed CDSR to Building Inspector.
Call 970-379-2244, Barry Lindahl or email blindahl69@yahoo.com with inquiries
regarding this form.
DO NOT ATTACH ADDITIONAL ITEMS
Permit #:_____________________________________
Project Address: (include floor, suite, etc.):
unit 9, Chateau Aspen,
630 E. Cooper Avenue, Aspen, Colorado
Contact Name: Barry Lindahl
Title: General Contractor,
Company: Target Construction
Contact Mailing Address:
01/08/2019
13
City________________________________________
State____________________ ZIP_________________
CONSTRUCTION MANAGEMENT PLAN
CHATEAU ASPEN, UNIT 9
630 EAST COOPER STREET,
ASPEN, COLORADO
Phone: 970-379-2244 Fax: __________________
Email: blindahl69@yahoo.com
For lines 1, 2 &3 please check only 1 item for each
1) Project Type: Alteration
2) Building Type: Apartment/Multifamily
3) Tenant Improvement (check one): Yes
4) Size of Project ___930____________ sq. ft. Project Valuation $100,000
5) Completion Date__5_/__31__/_2019___
6) Describe any difficulties you encountered in complying with your waste
management plan and tell us how to remedy the problem in the future.
________________________________________________________________
__________________________________
For City Use Only: App Filed____/____/____ CDSR Submitted____/____/___
Received___/___/___ Counter Staff
________________________________________ Diversion Goal Approved
Good Cause Non-Attainment Conditional Approval _____________ Not
Approved, reason ______________________________ Permit #: Address:
REQUIREMENT: Recycle______% of Asphalt & Concrete materials and no less
than _____ % of all other debris (measured in tons).
01/08/2019