Construction Management Plan
June 7, 2017
2.0 Project Introduction
2.1 Disturbance Area:
None: Interior renovation
2.2 Location:
120 E Hyman Ave
Aspen, CO 81611
2.3 Description:
An interior renovation of an existing 3 bedroom/ 3 bath condominium
unit. Entire unit gutted (asbestos mitigation). New gas boiler and new
electrical. All new interior finishes. NO Exterior fenestration modification
3.0 Project Documentation
3.1 Permits:
A City of Aspen permit has been applied for on June 8th, 2018
3.2 Public Notification:
North of Nell Management has been informed and will notify all other
tenants in the building before the start of construction complying with City
of Aspen requirements.
3.3 Project Sign
A project sign, complying with City of Aspen specifications, will be
erected before the start of construction.
3.4 Contact List
Owner: Robert Zarnegin
Contractor: Doug Throm Construction, Inc
Supervisor: Mike McKie
Safety Officer: Mike Mckie
Traffic Officer: Mike Mckie
Erosion Control representative: N/A
Received
6/13/17
Doug Throm Construction, Inc
617 W. Main Street
Aspen, CO
970 920-1719
4.0 Project Implementation
4.1 Dates of Construction:
September 1st 2017- December 15, 2017
4.2 Hours of Construction:
Per City of Aspen regulations:
Monday – Friday 7:30 am to 5:30 pm
Saturday 9:00 am to 5:00 pm
4.3 Construction Schedule:
5.0 Parking Management
5.1 Parking Management Form
5.2 Emergency Vehicle Access and Ordinance 35
Emergency vehicle access will remain open at all times
5.4 Staging Areas
See Exhibit “A” CMP site plan
5.5 Construction Trailer, materials storage and Waste Management
See Exhibit “A” CMP site plan
6.0 Traffic Control
Not Applicable to this permit
6.5 Traffic Control Plan
Not Applicable to this permit
8.0 Sediment and Erosion Control
Not Applicable to this permit
9.0 Fugitive Dust Control
Not Applicable to this permit
10.0 Emissions
Not Applicable to this permit
11.0 Noise Suppression
11.1 General
Compliance with the 70-decibel noise limit will be insured from June 1st
through Labor Day. Compliance of the 80-decibel noise limit will be
insured from Labor Day through May 31st.
11.2 Noise Suppression Plan
Exhibit”C” is the signed copy of the City of Aspen Construction Noise
Suppression Plan.
11.3 Requirements for Activities Exceeding 80 Decibels
All applicable rules & regulations will be complied with. Written
notification to surrounding neighbors within 300 feet of the project will be
distributed as necessary.