HomeMy WebLinkAboutFile Documents.535 E Hyman Ave.0020.2019 (3).ACBK Construction Management Plan Alice + Olivia-Tenant Improvement 535 E. Hyman Ave. Unit 105-Street Level 1. Project Introduction 1.1. Unit 105 located on the first floor of the Core building located at 535 E. Hyman Ave will have full tenant improvement work completed. New interior demising walls added, electrical fixtures, mechanical HVAC system, and FFE. This space is 927SF of floor area. Material staging will be located on the south side of the building within the alley access and long term storage will be in the space itself. 1.2. Vicinity Map: QuickTime™ and a decompressorare needed to see this picture. QuickTime™ and a decompressorare needed to see this picture. 1.3. The property contains a mixed use building located in downtown Aspen on the SW corner of Hyman and Hunter Ave. There is are existing occupied tenant spaces in the building. The scope of this remodel will be completed in 1 phase. We anticipate starting the project in the beginning of March with the expectation of total project buildout taking no more than four-six weeks. This building is serviced by public utilities. There are no plans for upgrading any of the utility services. 2. Project Documentation 2.1. Adjacent properties will be notified of work and provided contact information via the posting of the project sign the immediate neighbor will be notified of this construction and informed on an as need basis of possible construction impacts. This sign will include a brief scope of work and list contractor’s contact information. Because impacts beyond the licensed ROW area are not 03/27/2019 anticipated, specific notification and on-site meeting should not be necessary. 2.2. A project sign will be posted on the entry door of the building with the contractor's contact information. 2.3. Contact List: Owner: Alice & Olivia 450 W. 14th Street New York, NY 10014 General Contractor: G.F.Woods Construction, Greg Woods (970) 544-1833 / (970) 948-6483 Site Supervisor: Chad Roach (970) 309-8525 Safety Officer: Chad Roach (970) 309-8525 Traffic Officer: Chad Roach (970) 309-8525 3. Project Implementation 3.1. Dates of Construction: Construction is expected to last 4-6 weeks (April 22nd, 2019– May, 30th 2019) and will only occur on approved dates Monday through Saturday. 3.2. Hours of Construction: Construction activity will only occur during the allowed hours of 7:30AM and 5:30PM Mon - Friday and 9AM to 5PM on Saturdays. 3.3. Excavation will not occur or encroach within 5’ of the property line. 3.4. Project is all interior scope so no job site fencing will be installed. 3.5. Project shall uphold utmost respect for public health and welfare. 4. Project Management 4.1. Parking for subcontractors and GF Woods Construction employees will be limited to street parking. Temporary material staging will be located on the south side of the building in the alley as well. 4.2. Parking at the site is limited and is all metered. Carpooling and public transit will be encouraged and utilized to the greatest extent practicable. 4.3. Map of Construction Management Plan is attached as Exhibit A. 5. Traffic Control 5.1. Traffic Control Supervisor will manage operations, if and when necessary. 5.2. Designated haul routes will be followed. Exhibit B 5.3. Maximum vehicle weight shall not exceed 10,000lbs. 5.4. Any traffic control required for deliveries will be coordinated with the City of Aspen Engineering Department. Deliveries will not be scheduled outside of the approved hours of construction. No more than one delivery truck can be accommodated at any time. Deliveries will be unloaded via the entry doors on the Hyman Ave in early morning hours or through the alleyway to the south of the building. 5.5. A Traffic Control Plan is not included as road blockages or traffic stoppages are not scheduled or anticipated due to the limited scope and nature of the project. 6. Pedestrian Protection 6.1. Pedestrian safety will be maintained per City Code Section 21.04.060, MUTCD Chapter 6D, the Americans with Disability Act, and IBC Chapter 33. 7. Sediment and Erosion Control – NA 8. Fugitive Dust Control – N/A. 9. Emissions – All construction vehicles will be maintained and in good running order. 10. Noise Suppression 10.1. Construction noise will be limited to 80 decibels at the property line whenever possible. And are not expected to be a concern with all construction activity contained indoors. 10.2. Loud or obtrusive work will be completed during the approved hours of 9AM to 03/27/2019 5PM (Monday through Friday only). Neighbors will be notified 3 days advance. 03/27/2019 1 1 2 2 3 3 5 5 A B C D E 4 4 RES ELEV. EXIT STAIR OFFICE ELEV TRASH AREA 517 E. HYMAN AVE. RESTAURANT 118' - 5 1/4"98' - 10"SHAFT HYMAN AVENUEHUNTER STREETCLC OF ALLEY ALLEY PROPERTY LINEPROPERTY LINE PROPERTY LINE PROPERTY LINEBUILD'S ACCESS 535 E. HYMAN AVE. 521 E. HYMAN AVE. UNIT 106UNIT 105UNIT 104 UNIT 108 UNIT 107 UNIT 103 UNIT 102 UNIT 101 ISSUE: SHEET: DESCRIPTION: SCALE: c Rybak Architecture and Development, P. C., 2017 DRAWING INDEX PROJECT DIRECTORY VICINITY MAP PROJECT INFORMATION 535 E. HYMAN AVE. UNIT 105 ASPEN, COLORADO 1/8" = 1'-0"C:\Users\DAVE\Dropbox (Rybak Architecture)\RAD CURRENT PROJECTS\ASPEN CORE REVIT MODEL UPDATE\ASPEN CORE-T.I. PERMIT.rvt3/15/2019 5:12:52 PMA-000 GENERAL REFERENCE ALICE + OLIVIA 03/01/19 1/8" = 1'-0"1 ASPEN CORE CONDO SITE PLAN NORTH GENERAL CONTRACTOR: G.F. WOODS CONSTRUCTION 430 E. HYMAN AVE. ASPEN, CO 81621 ATTN: GREG WOODS PH: 544-1833 MECHANICAL/ELECTRICAL ENGINEERS: BG BUILDINGWORKS, INC. 222 CHAPEL PLACE, UNIT AC-201 AVON, CO 81620 ATTN: ERIN PASOLD PH: 970 221 5691 OWNER: ALICE + OLIVIA 450 W. 14 STREET NEW YORK, NY 10014 ARCHITECT OF RECORD: RYBAK ARCHITECTURE & DEVELOPMENT, P.C. 600 E. HOPKINS AVE., SUITE 303 ASPEN, CO 81611 ATTN: DAVE RYBAK PH: 970 925 1125 A-000 GENERAL REFERENCE Z-001 LAND USE APPROVALS Z-002 LAND USE APPROVALS Z-003 F.A.R. Z-004 NET LEASABLE A-001 FIRST FLOOR CODE ANALYSIS A-025 U.L. ASSEMBLIES A-105 DEMOLITION PLAN A-205 FLOOR PLAN & RCP A-305 ELEVATIONS & BUILDING SECTIONS A-601 DETAILS A-805 INTERIOR ELEVATIONS M-000 MECHANICAL COVER SHEET M-001 MECHANICAL SCHEDULES M-002 MECHANICAL SPECIFICATIONS M-101 MECHANICAL FLOOR PLAN E-000 ELECTRICAL COVER SHEET E-001 ELECTRICAL ONE-LINE DIAGRAM E-101 ELECTRICAL FLOOR PLAN ADDRESS:535 EAST HYMAN AVE., UNIT 105 PARCEL DESCRIPTION:ASPEN CORE CONDOMINIUMS, UNIT 104 PARCEL I.D.:2737 182 54 010 ZONE DISTRICT:CC PROJECT SCOPE:TENANT IMPROVEMENT OCCUPANCY TYPE:A-3 CONSTRUCTION TYPE:V-A CONSTRUCTION AREA:927 S.F. BUILDING CODES:I.B.C. 2015, I.M.C. 2015, N.E.C.2017, 2009 I.C.C. A117.1 FIRE SUPPRESSION:N.F.P.A. 13 Temporary Material Delivery/Unloading Zone during construction Designated area of construction activities Exhibit A-CMP 03/27/2019 E MAIN S T W MAI N S T E DURA N T A V E E HOP K I N S A V E GI B S O N A V E E COO P E R A V E W HAL L A M S T W BLE E K E R S T N THIRD STS ASPEN STW FRA N C I S S T N FIFTH STW HOP K I N S A V E N MILL STNORTH S T N SIXTH STW SMU G G L E R S T N FOURTH STS MONARCH STPARK AVES MILL STR E D M T N R D N FIRST STS ORIGINAL STLAKE AVEN SECOND STS GARMISCH STLO N E P I N E R D O A K L N S HUNTER STS WEST END STE BLEE K E R S T N SPRING STNEALE AVEVINE ST S FIRST STSHADY LNMIDLAND AVEE HYM A N A V E S GALENA STGILLESPIE AVE W HYM A N A V E DEAN S T KIN G S T RI O G R A N D E P LN EIGHTH STS SPRUCE STMA P L E L N PARK CIRN GARMISCH STRACE STE HALL A M S T WATER S A V EN ASPEN STS THIRD STN SPRUCE ST TEAL CTA J A X A V ENICHOLAS LN W COO P E R A V E JUAN S T WILLIAMS WYASPEN MTN R DPUPPY SM ITH ST QUEEN ST CLEVELAND STLACET LN FOUN D E R S P L A C E C O T T O NW O O D L N S RIVERSIDE AVEN SEVENTH STPEARL CT SOUTH AVE SUMMI T S T GILBE R T S TS FIFTH STS SIXTH STW NO R T H S T S FOURTH STS SPRING STN RIVERSIDE AVES SPRING STDEAN S T S GALENA STN SEVENTH STP A R K C I R DEAN S TS MILL STASPEN MTN RDMap prepared by Engineering and GIS Department City of Aspen, CO 81611 May 4,2007 0 600300 Feet Legend Designated Heavy Haul Route Roads Parcels City Boundary OFFICIAL HEAVY HAUL ROUTE MAP Exhibit B 03/27/2019