HomeMy WebLinkAboutFile Documents.535 E Hyman Ave.0125.2018.ACBK Construction Management Plan 535 E. Hyman Ave. Unit 003-Basement Level 1. Project Introduction 1.1. Unit 003 located on the second floor of the Core building located at 535 E. Hyman Ave will have walls added, electrical panel added along with mechanical HVAC system. This space is 2,550 SF of floor area. Material staging will be located on the south side of the building with in the alley access and long term storage will be in the space itself. 1.2. Vicinity Map: QuickTime™ and a decompressorare needed to see this picture. QuickTime™ and a decompressorare needed to see this picture. 1.3. The property contains a mixed use building located in downtown Aspen on the SW corner of Hyman and Hunter Ave. There is an existing occupied tenant space in the basement of this building. The scope of this remodel will be completed in 1 phase. We anticipate starting the project in the beginning of December with the expectation of total project buildout taking no more than three weeks. This building is serviced by public utilities. There are no plans for upgrading any of the utility services. 2. Project Documentation 2.1. Adjacent properties will be notified of work and provided contact information via the posting of the project sign the immediate neighbor will be notified of this construction and informed on an as need basis of possible construction impacts. This sign will include a brief scope of work and list contractor’s contact information. Because impacts beyond the licensed ROW area are not anticipated, specific notification and on-site meeting should not be necessary. 11/29/2018 2.2. A project sign will be posted on the entry door of the building with the contractor's contact information. 2.3. Contact List: Owner: Mocking Bird Interests Aspen, LLC General Contractor: G.F.Woods Construction, Greg Woods (970) 544-1833 / (970) 948-6483 Site Supervisor: Chris Dykes (970) 379-1282 Safety Officer: Chris Dykes (970) 379-1282 Traffic Officer: Chris Dykes (970) 379-1282 3. Project Implementation 3.1. Dates of Construction: Construction is expected to last 3 weeks (December 1, 2018 – December,21 2018) and will only occur on approved dates Monday through Saturday. 3.2. Hours of Construction: Construction activity will only occur during the allowed hours of 7:30AM and 5:30PM Mon - Friday and 9AM to 5PM on Saturdays. 3.3. Excavation will not occur or encroach within 5’ of the property line. 3.4. Project is all interior scope so no job site fencing will be installed. 3.5. Project shall uphold utmost respect for public health and welfare. 4. Project Management 4.1. Parking for subcontractors and GF Woods Construction employees will be limited to street parking. Temporary material staging will be located on the south side of the building in the alley as well. 4.2. Parking at the site is limited and is all metered. Carpooling and public transit will be encouraged and utilized to the greatest extent practicable. 4.3. Map of Construction Management Plan is attached as Exhibit A. 5. Traffic Control 5.1. Traffic Control Supervisor will manage operations, if and when necessary. 5.2. Designated haul routes will be followed. Exhibit B 5.3. Maximum vehicle weight shall not exceed 10,000lbs. 5.4. Any traffic control required for deliveries will be coordinated with the City of Aspen Engineering Department. Deliveries will not be scheduled outside of the approved hours of construction. No more than one delivery truck can be accommodated at any time. Deliveries will be unloaded via the entry doors on the Hyman Ave in early morning hours or through the alleyway to the south of the building. 5.5. A Traffic Control Plan is not included as road blockages or traffic stoppages are not scheduled or anticipated due to the limited scope and nature of the project. 6. Pedestrian Protection 6.1. Pedestrian safety will be maintained per City Code Section 21.04.060, MUTCD Chapter 6D, the Americans with Disability Act, and IBC Chapter 33. 7. Sediment and Erosion Control – NA 8. Fugitive Dust Control – N/A. 9. Emissions – All construction vehicles will be maintained and in good running order. 10. Noise Suppression 10.1. Construction noise will be limited to 80 decibels at the property line whenever possible. And are not expected to be a concern with all construction activity contained indoors. 10.2. Loud or obtrusive work will be completed during the approved hours of 9AM to 5PM (Monday through Friday only). Neighbors will be notified 3 days advance. 11/29/2018 E MAIN S T W MAI N S T E DURA N T A V E E HOP K I N S A V E GI B S O N A V E E COO P E R A V E W HAL L A M S T W BLE E K E R S T N THIRD STS ASPEN STW FRA N C I S S T N FIFTH STW HOP K I N S A V E N MILL STNORTH S T N SIXTH STW SMU G G L E R S T N FOURTH STS MONARCH STPARK AVES MILL STR E D M T N R D N FIRST STS ORIGINAL STLAKE AVEN SECOND STS GARMISCH STLO N E P I N E R D O A K L N S HUNTER STS WEST END STE BLEE K E R S T N SPRING STNEALE AVEVINE ST S FIRST STSHADY LNMIDLAND AVEE HYM A N A V E S GALENA STGILLESPIE AVE W HYM A N A V E DEAN S T KIN G S T RI O G R A N D E P LN EIGHTH STS SPRUCE STMA P L E L N PARK CIRN GARMISCH STRACE STE HALL A M S T WATER S A V EN ASPEN STS THIRD STN SPRUCE ST TEAL CTA J A X A V ENICHOLAS LN W COO P E R A V E JUAN S T WILLIAMS WYASPEN MTN R DPUPPY SM ITH ST QUEEN ST CLEVELAND STLACET LN FOUN D E R S P L A C E C O T T O NW O O D L N S RIVERSIDE AVEN SEVENTH STPEARL CT SOUTH AVE SUMMI T S T GILBE R T S TS FIFTH STS SIXTH STW NO R T H S T S FOURTH STS SPRING STN RIVERSIDE AVES SPRING STDEAN S T S GALENA STN SEVENTH STP A R K C I R DEAN S TS MILL STASPEN MTN RDMap prepared by Engineering and GIS Department City of Aspen, CO 81611 May 4,2007 0 600300 Feet Legend Designated Heavy Haul Route Roads Parcels City Boundary OFFICIAL HEAVY HAUL ROUTE MAP Exhibit B 11/29/2018 1 2 3 5 A B C D E 4 SERVICE AREA E XIT S E P A R A TIO N 44' - 9" EXIT TO FIRST FLOOR R E T A IL D I A GO N A L 1 2 0' - 6 5/8 " O V E R A LL D IA G O N A L 132' - 9 1 /4"SHAFT 3+5=8 2 26+4=30 4+1=5 4 4 4+1=571+2=73 73+1+5=79 (6' - 2")(10' - 6") (7' - 0")(9' - 9")(22' - 9")43+26+1+1=71 (11' - 2")(13' - 2") (8' - 9") (6' - 5") (2' - 1") (8' - 6")(8' - 1") (17' - 4") (13' - 7") (2' - 3")(6' - 2") (14' - 7") (16' - 7")4' - 3 3/8"OCCUPANCY STOR RM (S-2) GROSS AREA 933 sq.ft. OCCUPANT LOAD = 1/300 PER IBC 2015 TABLE 1004.1.2 EXIT P OCCUPANTS 79 1 (4' - 0")(9' - 1")(8' - 11")(11' - 4")(9' - 2") (10' - 4") (7' - 11")(2' - 2")(2' - 3")(2' - 8")(2' - 0") 1 1 1 1 4 3(3' - 9")UNIT 002 UNIT 001 153 SF OCC. LOAD = 1 UNIT 001-1 188 SF OCC. LOAD = 1 UNIT 001-2 189 SF OCC. LOAD = 1 UNIT 001-3 171 SF OCC. LOAD = 1 UNIT 001-4 232 SF OCC. LOAD = 1 UNIT 003 UNIT 003-1 EXIT STAIR TO FIRST FLOOR MAINTAIN EXISTING 2 HR FIRE ASSEMBLY PER U.L. U419 OCCUPANCY A-3 GYMNASIUM GROSS AREA 2,555 S.F. OCCUPANT LOAD FACTOR = 50 GROSS 2,555/50 = 52 OCCUPANTS PER IBC 2015 TABLE 1004.1.2 (23'-6")(1'-10")(6'-8")(43'-0")(25'-3")(1'-10")(1'-10")(1'-10")(6'-8") (1 1 '-8 ")(17'-0")(4'-5")(11'-7")(0'-9")(5'-5")(2'-0")(9'-0")(11'-4") 52 26 26 26 43 1 1 1 CODE ANALYSIS LEGEND: ONE HOUR FIRE WALL TWO HOUR FIRE WALL EXIT SIGN PER 2009 IBC SECTION 1006 FEC FIRE EXTINGUISHER CABINET AREA BOUNDARY LINE (SHOWN AT INSIDE FACE OF WALL FOR CLARITY - OCCUPANT LOAD IS BASED ON IBC 2015 TABLE 1004.1.2) EXIT PATH [DISTANCE OF TRAVEL] OCCUPANT LOAD/ EXIT DISCHARGE DIRECTION OF PATH 119 OCCUPANT LOAD EXIT ACCESS COMMON PATH OF EGRESS TRAVEL (CPET) EXIT - OCCUPANTS - DECISION POINT START POINT GENERAL NOTE: 1. SPRAY APPLIED FIRE PROOFING TO EQUAL 1 HOUR RATING AT ALL STEEL STRUCTURAL MEMBERS TYP. - REFER TO STRUCTURAL DRAWINGS FOR STEEL STRUCTURAL MEMBER LOCATION, TYPE, SIZE, AND LAYOUT. ( REFER TO UL DESIGN X795 FOR SPRAY THICKNESS SCHEDULE ) 2. REFER TO DOOR AND WINDOW SCHEDULE FOR FIRE RATING ASSEMBLY ON ALL FIRE RATED DOORS AND WINDOWS INCLUDING DOOR HARDWARES. 3. ALL WALL PARTITIONS WHICH ARE NOT SHOWING FIRE RATED ARE NON- RATED ASSEMBLIES. 4. MAINTAIN ALL EXISTING FIRE RATED ASSEMBLIES - REFER TO U.L. ASSEMBLIES FOR REQURIEMENTS ISSUE: SHEET: DESCRIPTION: SCALE: c Rybak Architecture and Development, P. C., 2017 535 E. HYMAN AVE. UNIT 003 ASPEN, COLORADO As indicated C:\Users\DAVE\Dropbox (Rybak Architecture)\RAD CURRENT PROJECTS\ASPEN CORE REVIT MODEL UPDATE\ASPEN CORE-T.I. PERMIT.rvt11/16/2018 5:22:03 PMA-011 BASEMENT CODE PLAN T.I. SOULCYCLE PROGRESS 11/15/18 1/8" = 1'-0"1 BASEMENT CODE PLAN - SOULCYCLE T.I. NORTH 3/16" = 1'-0" CODE ANALYSIS LEGEND 3/16" = 1'-0" CODE ANALYSIS NOTES Work Area 1,113 sf Area of designated construction. Basement Level-Unit 003-2,550sqft Material Staging and delivery area E. Hyman Ave. Hunter Ave 11/29/2018