HomeMy WebLinkAboutFile Documents.535 E Hyman Ave.0044.2018 (6).ACBK Construction Management Plan 535 E. Hyman Ave. Units 103 1. Project Introduction 1.1. Unit 103 located on the 1st floor of the Core building located at 535 E. Hyman Ave. will have a floor system framed up to street level. This space is 1,737SF of floor area. Material staging will be located on the south side of the building with in the alley access and long term storage will be in the space itself. 1.2. Vicinity Map: 1.3. The property contains a mixed use building located in downtown Aspen on the SW corner of Hyman and Hunter Ave. There is an existing occupied tenant space in the basement of this building. The scope of this remodel will be completed in 1 phase. We anticipate starting the project in the beginning of October with the expectation of total project buildout taking no more than four weeks. This building is serviced by public utilities. There are no plans for upgrading any of the utility services. 2. Project Documentation 2.1. Adjacent properties will be notified of work and provided contact information via the posting of the project sign the immediate neighbor will be notified of this construction and informed on an as need basis of possible construction impacts. This sign will include a brief scope of work and list contractor’s contact information. Because impacts beyond the licensed ROW area are not anticipated, specific notification and on-site meeting should not be necessary. 2.2. A project sign will be posted on the entry door of the building with the 9/28/17 contractor's contact information. 2.3. Contact List: Owner: Garfield and Hecht PC, 970-925-1936 General Contractor: G.F.Woods Construction, Greg Woods (970) 544-1833 / (970) 948-6483 Site Supervisor: Eric Wynne (970) 319-6938 Safety Officer: Eric Wynne (970) 319-6938 Traffic Officer: Eric Wynne (970) 319-6938 3. Project Implementation 3.1. Dates of Construction: Construction is expected to last 4 weeks (October 1, 2017 – October 27, 2017) and will only occur on approved dates Monday through Saturday. 3.2. Hours of Construction: Construction activity will only occur during the allowed hours of 7:30AM and 5:30PM Mon - Friday and 9AM to 5PM on Saturdays. 3.3. Excavation will not occur or encroach within 5’ of the property line. 3.4. Project is all interior scope so no job site fencing will be installed. 3.5. Project shall uphold utmost respect for public health and welfare. 4. Project Management 4.1. Parking for subcontractors and GF Woods Construction employees will be limited to street parking. Temporary material staging will be located on the south side of the building in the alley as well. 4.2. Parking at the site is limited and is all metered. Carpooling and public transit will be encouraged and utilized to the greatest extent practicable. 4.3. Map of Construction Management Plan is attached as Exhibit A. 5. Traffic Control 5.1. Traffic Control Supervisor will manage operations, if and when necessary. 5.2. Designated haul routes will be followed. Exhibit B 5.3. Maximum vehicle weight shall not exceed 10,000lbs. 5.4. Any traffic control required for deliveries will be coordinated with the City of Aspen Engineering Department. Deliveries will not be scheduled outside of the approved hours of construction. No more than one delivery truck can be accommodated at any time. Deliveries will be unloaded via the entry doors on the Hyman Ave in early morning hours or through the alleyway to the south of the building. 5.5. A Traffic Control Plan is not included as road blockages or traffic stoppages are not scheduled or anticipated due to the limited scope and nature of the project. 6. Pedestrian Protection 6.1. Pedestrian safety will be maintained per City Code Section 21.04.060, MUTCD Chapter 6D, the Americans with Disability Act, and IBC Chapter 33. 7. Sediment and Erosion Control – NA 8. Fugitive Dust Control – N/A. 9. Emissions – All construction vehicles will be maintained and in good running order. 10. Noise Suppression 10.1. Construction noise will be limited to 80 decibels at the property line whenever possible. And are not expected to be a concern with all construction activity contained indoors. 10.2. Loud or obtrusive work will be completed during the approved hours of 9AM to 5PM (Monday through Friday only). Neighbors will be notified 3 days advance. 9/28/17 1 1 2 2 3 3 5 5 A B C D E 4 4 RES ELEV. EXITSTAIR OFFICE ELEV TRASH AREA 517 E. HYMAN AVE. RESTAURANT 118' - 5 1/4"98' - 10"SHAFT HYMAN AVENUEHUNTER STREETCLC OF ALLEY ALLEY PROPERTY LINEPROPERTY LINE PROPERTY LINE PROPERTY LINEBUILD'S ACCESS UNIT 103 103 UNIT 104 A 104A UNIT 104 B 104B UNIT 104 C 104 C BENTON 16 SERVICE AREA 102 ELEV. LOBBY 110 ENTRY 112 STAIR #2 109 HUNTER LOBBY 15 535 E. HYMAN AVE.521 E. HYMAN AVE. ISSUE: SHEET: DESCRIPTION: SCALE: c Rybak Architecture and Development, P. C., 2017 DRAWING INDEX PROJECT DIRECTORY VICINITY MAP PROJECT INFORMATION 535 E. HYMAN AVE. ASPEN, COLORADO 1/8" = 1'-0"C:\Users\DAVE\Documents\RAD PROJECTS\ASPEN CORE REVIT MODEL UPDATE\ASPEN CORE-T.I. PERMIT.rvt9/1/2017 4:56:10 PMA-000 COVER ASPEN CORE DEMISING DEMISING AUG. 22, 2017 OWNER:ASPEN CORE VENTURES, LLC. 435 E. HYMAN AVE. ASPEN, CO 81611 ARCHITECT: RYBAK ARCHITECTURE & DEVELOPMENT, P.C.600 E. HOPKINS AVE., SUITE 303 ASPEN, CO 81611 ATTN: DAVE RYBAK PH: 970 925 1125 STRUCTURAL ENGINEER:ALBRIGHT & ASSOCIATES, INC. 402 PARK AVE., UNIT A BASALT, CO 81621 ATTN: CRAIG BIEREPH: 970 927 4363 GENERAL CONTRACTOR:G.F. WOODS CONSTRUCTION, INC. 430 E. HYMAN AVE. ASPEN, CO 81611 ATTN: GREG WOODS PH: 970 544 1833 MECHANICAL/ELECTRICAL ENGINEERS: BG BUILDINGWORKS, INC. 222 CHAPEL PLACE, UNIT AC-201 AVON, CO 81620 ATTN: ERIN PASOLD PH: 970 221 5691 ADDRESS:535 E. HOPKINS AVE., UNIT 103 & 104 PARCEL DESCRIPTION:ASPEN CORE CONDOMINIUMS, UNITS 103 &104 PARCEL I.D.:UNIT 103 - 2737 182 54 009; UNIT 104 - 2737 182 54 010 ZONE DISTRICT:CC PROJECT SCOPE:RAISE FLOOR IN UNIT 103, DEMISE UNIT 104 OCCUPANCY TYPE:M CONSTRUCTION TYPE:V-A CONSTRUCTION AREA:UNIT 103 1,737 SF UNIT 104 3,603 SF TOTAL 5,340 SF BUILDING CODES:I.B.C. 2015, I.M.C. 2015, N.E.C.2014 FIRE SUPPRESSION:N.F.P.A. 13 1/8" = 1'-0"1 ASPEN CORE CONDO SITE PLAN NORTH A-000 COVER Z-001 LAND USE APPROVALS Z-002 LAND USE APPROVALS Z-003 F.A.R. Z-004 NET LEASABLE DRAWINGS A-001 BUILDING CODE ANALYSISA-002 U.L. ASSEMBLIES A-003 U.L. ASSEMBLIES A-201 FIRST FLOOR PLAN A-601 DETAILS M-001 FIRST FLOOR MECHANICAL PLAN M-002 E-001 E-002 Unit with in the Core building that will be the focus of the scope of work. Temporary Material Staging Exhibit A Material Delivery and Unloading Zone / Temporary Material Staging 9/28/17 Unloading and carry in only please, no room for storage in alley. E MAIN S T W MAIN S T E DURA N T A V E E HOPK I N S A V E GI B S O N A V E E COOP E R A V E W HALL A M S T W BLEE K E R S T N THIRD STS ASPEN STW FRA N C I S S T N FIFTH STW HOPK I N S A V E N MILL STNORTH S T N SIXTH STW SMU G G L E R S T N FOURTH STS MONARCH STPARK AVES MILL STR E D M T N R D N FIRST STS ORIGINAL STLAKE AVEN SECOND STS GARMISCH STLON E P I N E R D O A K L N S HUNTER STS WEST END STE BLEE K E R S T N SPRING STNEALE AVEVINE ST S FIRST STSHADY LNMIDLAND AVEE HYMA N A V E S GALENA STGILLESPIE AVE W HYM A N A V E DEAN S T KIN G S T RI O G R A N D E P LN EIGHTH STS SPRUCE STM A P L E L N PARK CIRN GARMISCH STRACE STE HALL A M S T WATERS A V EN ASPEN STS THIRD STN SPRUCE ST TEAL CT A J A X A V ENICHOLAS LN W COO P E R A V E JUAN ST WILLIAMS WYASPEN MTN R DPUPPY SM ITH ST QUEEN ST CLEVELAND STLACET LN FOUND E R S P L A C E C O T T O N W O O D L N S RIVERSIDE AVEN SEVENTH STPEARL CT SOUTH AVE SUMMI T S T GILBE R T S TS FIFTH STS SIXTH STW NOR T H S T S FOURTH STS SPRING STN RIVERSIDE AVES SPRING STDEAN ST S GALENA STN SEVENTH STP A R K C I R DEAN S TS MILL STASPEN MTN RDMap prepared by Engineering and GIS Department City of Aspen, CO 81611 May 4,2007 0 600300 Feet Legend Designated Heavy Haul Route Roads Parcels City Boundary OFFICIAL HEAVY HAUL ROUTE MAP Exhibit B 9/28/17