CONSTRUCTION MANAGEMENT PLAN
FOR
971 Ute Ave
Owner: Ajax Holdings
Contractor: Kaegebein Fine Homebuilding, LLC
970-379-6228
Safety Officer: Scott McClung
618-4362
Traffic Control Officer: Scott McClung
618 -4362
Erosion Control Officer: Nate Kaegebein
_______________________
BUILDING PERMIT NUMBER:
Submittal Date:
4.4.17
Received
5/11/17
KAEGEBEIN FINE HOMEBUILDING, LLC
PO Box 1570, Carbondale, CO. 81623
Phone: (970) 510-5797 Fax: (970)963-1392
office@kfhomebuilding.com
www.kfhomebuilding.com
Page 2 of 10
1. CMP INDEX:
1. INDEX 2
2. PROJECT LOCATION 3
2.1 DISTURBANCE AREA
2.2 LOCATION
2.3 DESCRIPTION
3. PROJECT DOCUMENTATION 3-4
3.1 PERMITS/OTHER DOCUMENTS
3.2 PUBLIC NOTIFICATIONS
3.3 PROJECT SIGN
3.4 CONTACT DESIGNATION
4. PROJECT IMPLEMENTATION 4-6
4.1 DATES OF CONSTRUCTION
4.2 HOURS OF CONSTRUCTION
4.3 SEQUENCE (PHASING) OF CONSTRUCTION
4.4 ADJOINING PROPERTIES
4.5 PROJECT FENCING
4.6 PUBLIC HEALTH AND WELFARE
4.7 NATURAL ENVIRONMENT
5. SITE AND RIGHT OF WAY MANAGEMENT 6-8
5.1 RIGHT OF WAY MANAGEMENT PLAN
5.2 EMERGENCY VEHICLE ACCESS AND ORDINANCE 35
5.3 CONSTRUCTION PARKING DETAILS
5.4 STAGING AREAS
5.5 RIGHT OF WAY LIMITATIONS
5.6 CONSTRUCTION TRAILER, MATERIALS STORAGE, AND WASTE MANAGEMENT
6. TRAFFIC CONTROL 8
6.1 GENERAL
6.2 HAUL ROUTES
6.3 ONSITE VEHICLE LIMITATIONS
6.4 DELIVERY REQUIREMENTS
6.5 TRAFFIC CONTROL PLAN
7. PEDESTRIAN PROTECTION 9
7.1 GENERAL
7.2 LIMITATIONS
8. SEDIMENT AND EROSION CONTROL 9
8.1 REQUIREMENTS
8.2 SMUGGLER MOUNTAIN RESTRICTIONS
9. FUGITIVE DUST CONTROL 9
9.1 FUGITIVE DUST CONTROL PLAN
9.2 REQUIREMENTS
10. EMISSIONS 9-10
10.1 GENERAL
10.2 EMISSIONS FROM DIESEL POWERED ENGINES
11. NOISE SUPRESSION PLAN 10-11
11.1 GENERAL
11.2 NOISE SUPPRESSION PLAN
Received
5/11/17
KAEGEBEIN FINE HOMEBUILDING, LLC
PO Box 1570, Carbondale, CO. 81623
Phone: (970) 510-5797 Fax: (970)963-1392
office@kfhomebuilding.com
www.kfhomebuilding.com
Page 3 of 10
2. PROJECT LOCATION
2.1. DISTURBANCE AREA
The total disturbance area of the project will be the entire lot of 0 SF. The home is
existing and the project consists of interior remodeling.
2.2. PROJECT VICINITY MAP
See attached map. Exhibit “A”
2.3. LOCATION DESCRIPTION
Background information: Existing Single Family,
Proposed Development Type: Single Family
General Information: Remodel of existing interior of home
3. PROJECT DOCUMENTATION
3.1. LIST ALL PERMITS AND PROVIDE ALL COPIES OF PERMITS:
Building Permit
Electrical Permit
Fire Permit
Mechanical Permit (HVAC)
Mechanical Permit (Fireplace)
Plumbing Permit
3.2. PUBLIC NOTIFICATION:
The Project representative is Scott McClung of Kaegebein Fine Homebuilding. The
Preconstruction meeting is scheduled for _______________2017 at 9 AM and will
be scheduled on site. A monthly project report will be posted on site in a
receptacle near the construction information sign. All neighbors will be notified in
writing 10 days prior to construction.
3.3. PROJECT SIGN
Project Name: 971 Ute Ave
Building Permit Number: ___________________
Received
5/11/17
KAEGEBEIN FINE HOMEBUILDING, LLC
PO Box 1570, Carbondale, CO. 81623
Phone: (970) 510-5797 Fax: (970)963-1392
office@kfhomebuilding.com
www.kfhomebuilding.com
Page 4 of 10
General Contractor Name: KAEGEBEIN FINE HOMEBUILDING, LLC
General Contractor Contact: Charles Berger
General Contractor Phone #: 970-618-7493
Emergency Phone #: 970-379-6228
Sign will be green in color and meet the criteria of City Municipal Code 26.510.030B4.
3.4. CONTACT LIST:
Owner: Ajax Holdings LLC
Contractor: Kaegebein Fine Homebuilding, LLC
970-379-6228
Safety Officer: Joe Colonna
379-2863
Traffic Control Officer: Joe Colonna
379-2863
Erosion Control Officer: Nate Kaegebein
4. PROJECT IMPLEMENTATION
4.1. DATES OF CONSTRUCTION
8.15.17 – 2.28.17
4.2. HOURS OF CONSTRUCTION
Construction hours will comply with section 4.2 of CMP requirements manual, April
2015.
4.3. CONSTRUCTION SCHEDULING AND PHASING
This is an approximate 6 month project.
Demo: 1.0 months
Interior rough in: 2.0 months
Interior/Exterior finishes: 3.0 months
4.4. ADJOINING PROPERTIES
Received
5/11/17
KAEGEBEIN FINE HOMEBUILDING, LLC
PO Box 1570, Carbondale, CO. 81623
Phone: (970) 510-5797 Fax: (970)963-1392
office@kfhomebuilding.com
www.kfhomebuilding.com
Page 5 of 10
Will be unaffected other than a dumpster and portable toilet in the driveway. All
other work will be interior and possibly a roof replacement.
4.5. PROJECT FENCING
A six foot green screen chain link fence will also be installed around the perimeter of the
construction area.
See CMP site plan.
4.6. PROJECT RESPECTS PUBLIC HEALTH AND WELFARE
This construction project “shall uphold utmost respect to public health and welfare”.
4.7. NATURAL ENVIRONMENT
A tree removal permit will be not be necessary.
5. SITE AND RIGHT OF WAY MANAGMENT
5.1. RIGHT OF WAY MANAGEMENT PLAN
If the ROW space is deemed necessary and/or practical a temporary encroachment
permit will be submitted at least 10 working days prior to the date which it would be
used.
See CMP site plan.
5.2. EMERGENCY VEHICLE ACCESS
Emergency vehicle access will not be inhibited. The site is readily accessible from Ute
Ave.
5.3. CONSTRUCTION PARKING DETAILS
There is limited parking on site. Approx. 2-3 spaces will be utilitized thru out the project.
All construction parking will be handled with parking permits purchased by the owner.
(See CMP site plan)
Received
5/11/17
KAEGEBEIN FINE HOMEBUILDING, LLC
PO Box 1570, Carbondale, CO. 81623
Phone: (970) 510-5797 Fax: (970)963-1392
office@kfhomebuilding.com
www.kfhomebuilding.com
Page 6 of 10
This project will utilize the Carpool Program and project shuttle during the phases of
construction when this is practical and possible.
Parking passes will be issued for those vehicles which are unable to carpool or park in
designated construction parking.
5.4. SITE LOCATIONS FOR STAGING MATERIALS
The minimal on site staging area will be utilized carefully. All possible deliveries will be
thru Ute Ave. (see CMP plan)
Export of excavation truck trips: 0
Concrete truck trips: 1
Steel delivery truck trips: 1
Lumber delivery truck trips: 4
Import of backfill truck trips: 0
Misc. finish material truck trips: 25
Landscape truck trips: 1
Total truck trips: 32
5.5. RIGHT OF WAY LIMITATIONS
A. The site does not fall with the seasonal limitations for temporary encroachments.
5.6. CONSTRUCTION TRAILER, MATERIALS STORAGE, AND WASTE MANAGEMENT
No loose job materials will be stored on Ute ave. The existing driveway and garage will
be used
On site recycling separation will occur on this project per the CMP manual section 5.6.
During demolition, concrete and scrap metal will be sorted and kept separate on site in
designated areas.
Any trash receptacle that is used for food refuse will be constructed in such a manner to
render it bear proof.
Received
5/11/17
KAEGEBEIN FINE HOMEBUILDING, LLC
PO Box 1570, Carbondale, CO. 81623
Phone: (970) 510-5797 Fax: (970)963-1392
office@kfhomebuilding.com
www.kfhomebuilding.com
Page 7 of 10
A hazardous material spill cleanup kit will be on-site if specified by the City Engineer.
6. TRAFFIC CONTROL
6.1. GENERAL
All traffic control operation shall be managed by the designated certified traffic control
supervisor.
6.2. PROJECT HAUL ROUTES
Heavy haul routes will not be necessary for this project.
6.3. ONSITE VEHICLE LIMITATIONS
Max: 40 ft and 48,000 pounds
6.4. DELIVERY REQUIREMENTS
Road closures will not be required during construction operations. If it is determined
that a road closure is required, the proper permit will be obtained from the City of Aspen
Engineering Dept.
The site has capacity for one delivery at a time and will be limited to the hours of
construction. There will be no exceptions to the delivery schedule.
6.5. TRAFFIC CONTROL PLAN
A traffic control plan will be provided if requested by City Engineer.
7. PEDESTRIAN PROTECTION
No pedestrian sidewalks will be impacted by this construction project.
8. SEDIMENT AND EROSION CONTROL
8.1. REQUIREMENTS
N/A
Received
5/11/17
KAEGEBEIN FINE HOMEBUILDING, LLC
PO Box 1570, Carbondale, CO. 81623
Phone: (970) 510-5797 Fax: (970)963-1392
office@kfhomebuilding.com
www.kfhomebuilding.com
Page 8 of 10
8.2. SMUGGLER MOUNTAIN RESTRICTIONS
This site is not on smuggler mountain.
9. FUGITIVE DUST CONTROL
The project will utilize the following fugitive dust control measures.
An onsite pressure washer shall be used to keep the public ROW clean.
Vehicle speeds will be kept to 15 MPH
24 HOUR EMERGENCY CONTACT: Charlie Berger 970-618-7493
10. EMISSIONS
10.1. GENERAL
All vehicles and equipment used on site shall be properly marinated such that the
engines will function within manufactures standards or parameters.
10.2. EMISSIONS FROM DIESEL POWERED ENGINES
Emissions from diesel engines operated within the city of Aspen shall be a shade or
density no darker than 40% opacity except for starting motion no longer than 10
seconds or for stationary operation not exceeding 10 seconds.
Received
5/11/17
KAEGEBEIN FINE HOMEBUILDING, LLC
PO Box 1570, Carbondale, CO. 81623
Phone: (970) 510-5797 Fax: (970)963-1392
office@kfhomebuilding.com
www.kfhomebuilding.com
Page 9 of 10
11. NOISE SUPPRESSION
11.1. GENERAL
All Construction equipment shall b e adequately muffled and maintained to minimize
project noise.
11.2. NOISE SUPPRESION PLAN
All activity that generates noise in excess of 80 decibels will be restricted to operating
between the hours of 9AM and 5PM Monday thru Friday.
11.3. CONTINUED NOISE MONITORING
Continued noise monitoring will be installed if required by the Engineering dept.
11.4. REQUIREMENTS FOR ACTIVITIES EXCEEDING 80 DECIBELS
1. Any work producing noise levels over 80 decibels is not permitted to commence
until after 9:00 AM and is not permitted on Saturdays. This does not restrict quiet work
inside and outside that does not require a power source, including a battery, on
Saturday.
2. All neighbors within three hundred feet of the project will be notified. Informing
them of the kinds of equipment, expected noise levels and duration of work.
COMMUNICATION WITH THE NEIGHBORS WILL BE MAINTAINED AT ALL TIMES
WITH THE INTENT OF REDUCING COMPLAINTS.
3. Equipment will be operated in accordance with the manufacturer’s specificiations
and with all standard manufacturers mufflers and noise reducing equipment in use and
properly operating condition.
4. Notices to inform works, including sub contractors, will be posted about basic
noise requirements, as well as specific noise restrictions.
5. Table 1 of Appendix C will be followed for noise barriers.
6. Portable loud equipment will be moved to different sides of the property to reduce
noise impact on individual neighbors.
7. Radios will not be on prior to 8:00 AM.
11.5. SPECIFIC RESTRICTIONS RELATED TO MANUFACTURING ON SITE
Received
5/11/17
KAEGEBEIN FINE HOMEBUILDING, LLC
PO Box 1570, Carbondale, CO. 81623
Phone: (970) 510-5797 Fax: (970)963-1392
office@kfhomebuilding.com
www.kfhomebuilding.com
Page 10 of 10
There will be no manufacturing on site as described in this section of the manual.
EXHIBIT “A”
Vicinity Map
Received
5/11/17