HomeMy WebLinkAboutFile Documents.387 Silverlode Dr.0035.2019 (7).ARBK
0
2019
Construction
Management Plan
387 SILVERLODE, ASPEN COLORADO 81611
SH BUILDING GROUP LLC
03/20/2019
1
Construction Management Plan
387 Silverlode, Aspen CO 81611
1.0 General
Total square feet of soil disturbed is 0 SF.
2.0 Project Introduction
2.1 Disturbance Area: Total Interior Remodel area is 450 sf.
2.2 Location: 387 Silverlode, Aspen, CO 81611 Vicinity Map Attached Page 5
2.3 Description/Background Information : Demo walls at existing bathrooms, remodel
kitchen, resurface master deck and add snowmelt, insert new gas fireplace appliances.
3.0 Project Documentation.
3.1 Permit Types, Permit #s. IFFR Permit, Building Permit, PV ---Will be attached when
issued.
3.2 Public/Project Notification. The project specific Construction Management Plan will
be presented to the permit coordinator. The CMP will address the project representative,
project schedule and estimated impact to applicable parties. All parties within 300 ft will
be notified a minimum 10 days prior to commencement of work.
3.3 Project Sign. Project sign shall be posted according to City Municipal Code 26.510.030B4
3.4 Contact List:
Owner – Ken Sawyer, 387 Silverlode, Aspen, CO 81611
Contractor: SH Building Group
314B AABC
Aspen, CO 81611
Contact: Tom Sherlock 970-923-1122
Project Manager: Greg Hinkle
Site Supervisor: TBD
Structural Engineer: Hein Brutsaert, hbrutsaert@gmail.com, 970-300-1003
4.0 Project Implementation.
4.1 Dates of Construction:
•Begin Demo & Prep: March 25, 2019 for 2 weeks.
•April 8th start framing new walls, replacing boilers and flues, installing new
windows and exterior doors, remodeling kitchen w/ cabinet and countertop
installations, appliances, trim and siding repair, resurface master deck with
snowmelt and install fireplaces. Repair tile and finishes. 9 Week duration.
Projected end of project: June 8th, 2019.
4.2 Hours of Construction:
7:30 am - 5:30 pm Daily M-F and 9:00 am – 5:00 pm Saturday where necessary.
03/20/2019
2
Holidays and various Non Working days set forth by the City of Aspen
will be followed.
4.3 Construction Sequence-Schedule: Construction will take approximately 3 months.
Sequence: Start framing new walls, replacing boilers and flues, installing new windows
and exterior doors, remodeling kitchen w/ cabinet and countertop installations,
appliances, interior door installation, trim and siding repair, resurface master deck with
snowmelt and install fireplaces. Repair tile and finishes
4.4 Adjacent Property Owners: Adjacent Properties will be notified of the construction.
4.5 Construction Fencing. None needed for interior work.
4.6 Public Health and Welfare. All care will be taken by project proponents to protect the
public health and welfare, including dust control, noise control, and site maintenance.
4.7 Natural Environment. Interior work only.
5.0 Site and ROW management plan
5.1 ROW Management Plan – See attached Plan
5.2 Emergency Vehicle Access and Ordinance 35. Ordinance 35 will be adhered to,
emergency access at the property will be maintained at all times.
5.3 Construction Parking Details. Construction vehicles will utilize the existing street
parking and driveway on and around the Property.
5.4 Staging Areas. Staging of materials will occur on site as labeled by the CMP. All
material will be stored in an appropriate area adhering to all BMP’s. Absolutely no
staging will occur within the City ROW.
5.5 ROW Limitations. No construction trailer will be required, all materials will be
delivered at time of use, and small materials will be stored in the garage or alongside the
building. No loose material will be stored in any public right-of-way. Trucks will be able
to utilize the driveway.
5.6 CONSTRUCTION TRAILER, MATERIALS STORAGE, AND WASTE
MANAGEMENT
Waste management will be handled by bear proof waste carts placed in garage. Dumpster
will be on site.
Construction related materials will be sorted on site and placed in appropriate containers.
See ROW plan for details
6.0 Traffic Control.
6.1 General. All traffic control operations shall be managed by the designated certified
traffic control supervisor
6.2 Haul Routes. Interior work only.
6.3 Onsite Vehicle Limitations. All vehicles proposed to be used will qualify for road
vehicle weight and height limitations.
6.4 Delivery requirements. Trips will be coordinated to ensure that only one large truck
03/20/2019
3
will be onsite at any given time. Delivery vehicles will not be allowed to idle for more
than 5 mins per City of Aspen Vehicle Idling regulations
6.5 Traffic Control Plan. N/A
7.0 Pedestrian Protection. The project will comply with pedestrian safety per City code
21.04.060,MUTCD Chapter 6D, the Americans with Disability Act, and IBC Chapter 33.
8.0 Sediment Control.—N/A interior work only
8.1 [General. All necessary Best Management Practices (BMP’s) will be in place and
maintained in order to minimize sediment leaving the perimeter of our jobsite. Primary
strategies include:
• Avoid unnecessary site disturbance
• Maintain Grading; install silt fences and sediment traps prior to any soil
disturbance
• Concrete washout will be done back into the concrete trucks due to lack of
space. ]
8.2 Smuggler Mountain Restrictions. Do not apply.
8.3 Stormwater Control Plan—N/A interior work only.
03/20/2019
4
9.0 Fugitive Dust Control Plan
The project will avoid unnecessary site disturbance and keep a hose and spray nozzle
available to mitigate born dust. All exported soils and other debris will be hauled off via
covered trucks. All areas directly surrounding the site will be maintained daily with
thorough cleanings.
10.0 Emissions.
10.1 General. The project intends to comply with City Code.
10.2 Emissions for Diesel Powered Engines. The project intends to comply with City Code.
11.0 Noise Suppression.
11.1 General. The project intends to comply with City Code.
11.2 Noise Suppression Plan. No Formal Noise Suppression proposal will be submitted to
the City. Contractor will follow City Code.
11.3 Requirements for activities exceeding 70 decibels. The Project intends to comply with
City Code. Activities involving work that creates noise exceeding 70dB will not take
place between 6/1-Labor Day during the Summer Season. All other dates work will not
03/20/2019
5
exceed 80dB.
11.4 Specific restrictions related to manufacturing on site. It is not proposed that any
manufacturing will occur on site.
12.0 Enforcement.
12.1 City Construction Mitigation Officer. The project intends to comply with City Code.
12.2 Corrective Action. The project intends to comply with City Code.
12.3 Inspection Reports. The project intends to comply with City Code.
13.0 CONSTRUCTION MITIGATION COMMITTEE - The project is not applying for
any exemptions
03/20/2019
Driveway AreaDumpsterPortoletMaterials StagingAdditional Storage (in Garage) and Recycling ContainersParking Space #1Parking Space #2387 Silverlode03/20/2019