Page Label: A0.3 OOF DEMOLITION CALCULATIONS
Page Index: 3
Author: sophiev
File Name: 387 Architecturals.pdf
Please check that table and diagrams correspond.
An example of the numbers being off would be
Wall B.
387 Architecturals.pdf (4)
Page Label: A1.0 EXISTING / DEMO LOWER LEVEL
FLOOR PLAN
Page Index: 4
Author: sophiev
File Name: 387 Architecturals.pdf
Is this retaining wall still being removed?
Page Label: A1.1 EXISTING / DEMO MAIN LEVEL FLOOR
PLAN
Page Index: 5
Author: sophiev
File Name: 387 Architecturals.pdf
Please lighten this shading. The writing is illegible.
Page Label: A1.4 MAIN LEVEL REFLECTED CEILING PLAN
Page Index: 8
Author: sophiev
File Name: 387 Architecturals.pdf
Will any exterior lighting be added or changed? If
so, please provide exterior lighting plan and
cutsheets.If not, please provide note stating that no
exterior lighting is in the scope of this permit.
Page Label: 1
Page Index: 1
Author: sophiev
File Name: 387 Silverlode Drive Approved RDS Checklist.pdf
Please provide stamped RDS plans that
correspond with this checklist.
387 Silverlode Drive Approved RDS Checklist.pdf (1)
Page Label: 10
Page Index: 9
Author: sophiev
File Name: City of Aspen Building Permit
Application_201901071056513870_REVISED BG.pdf
Please have contractor sign Zoning Compliance
Verification Policy.
City of Aspen Building Permit Application_201901071056513870_REVISED BG.pdf (1)
EXISTING WALL TO REMAIN
WALL AREA TO BE REMOVED
AREA REDUCED FOR FENESTRATION
A
B
I
M
6.8 SF 12.6 SF
55.4 SF Demolition CalculationsCity of Aspen Zoning Submission
Wall Demolition
Wall LabelABCDEFGHIJKLM
Wall Surface Area Total (SF)Area Reduced for Fenstration (SF)Area used for Demo Calc (SF)Wall Surface Area to be Removed (SF)
Demolition TotalsRoof + Wall Area Used for Demo Calcs (SF)Surface Area to be Removed (SF)Total
2,886.5 + 3,043122 + 1 5,929.50123.002.07%
Individual Wall Area(SF)460.0059.00784.00227.5028.5063.5028.50695.00965.0054.0057.00799.5055.50
4,277.00 1,234.003,043.00 122.00
Area Reduced for Fenestration(SF)69.0023.50327.50136.00
32.00
347.50149.0023.5023.5090.0012.50
Area of Wall to be Removed(SF)
3.5015.50
103.00
Please check thattable and diagramscorrespond. Anexample of thenumbers being offwould be Wall B.
WINDOW
REMOVE EXISTING
RETAINING WALL.
REF. A0.1 FOR
LANDSCAPE PLAN
Is this retaining wall
still being removed?
DN3R @ 6"
DN
113'-0"
111'-0"
114'-6"
PREP EXISTING BUILT-INFOR NEW FINISH.
HALL#200
DINING#203
KITCHEN#204
M. BEDROOM#206 LIVING ROOM#205
M. DECK#207
REMOVE DECKASSEMBLYTO SHEATHING
DEMO WALL ABOVEFOR NEW CLERESTORYWINDOWSM. CLST.#210
M. BATH#209 HALL#208
OUTDOORLIVING#210
INSPECT/SCOPEINTERNAL DRAIN
REMOVE EXISTINGGAS APPLIANCE,MINIMIZE DEMOEXTENTS, EXSTGFINISHES TO REMAINEXCEPT AT MANTLE
2
2
2
2
Please lighten thisshading. The writingis illegible.
Will any exterior lighting be added or
changed? If so, please provide
exterior lighting plan and cutsheets.If
not, please provide note stating that
no exterior lighting is in the scope of
this permit.
Please provide
stamped RDS plans
that correspond with
this checklist.
CITY OF ASPEN 130 S. GALENA ST | ASPEN, CO 81611
conforms to the dimensions shown on the zoning sheets of the approved building permit plan set and meets the zoning limitations for the property or shall determine which elements of the project are not in compliance. The Zoning Officer may request additional information to verify zoning compliance, which may include but is not limited to additional survey work or a site visit.
All drawings of the survey report must correlate with representations in the approved building permit set for acceptance. Modifications to field conditions or amendments to the building permit may be required.
A determination of non-compliance shall result in the issuance of a correction notice and possible work stoppage. Applicants are encouraged to verify zoning compliance as early as reasonably practical in the construction process to minimize disruption to the construction schedule.
Acknowledgment:
I (contractor name) ______________________________ understand this policy. I agree that this project will comply with the zoning limitations affecting this parcel and the representations made on the zoning sheets of the approved building permit plans. I understand that a Certificate of Occupancy will not be issued until this project complies with all applicable zoning limitations.
Contractor Signature: ___________________________________________
Date: ________________________________________________________
August 2017
Please havecontractor signZoning ComplianceVerification Policy.
Areas have been double checked and are
accurate. Shading obscured decimal points and
this has been corrected. Please see attached.
No, this has been eliminated from the scope.
Complete, please see attached.
No added or changed lighting is
proposed
Complete, please see attached.
Complete, please see attached.
03/21/2019