Loading...
HomeMy WebLinkAboutFile Documents.395 Thunderbowl Ln.0153.2017 (16).ARBKTHUNDERBOWL LOT #7 CONSTRUCTION MANAGEMENT PLAN Thunderbowl Lot #7 395 Thunderbowl Ln, Aspen, CO 81611 Parcel ID: 273514310007 Construction Management Plan Background: This Construction Management Plan (CMP) outlines and details the construction management measures that will be employed throughout the construction process of 395 Thunderbowl Ln. Lot #7, Aspen, CO 81611. This CMP is intended to address all items that are applicable to the scope of work in said project. Where items are not applicable to the scope of work, the CMP will note this. The provided CMP will outline supplemental information along with its location when addressed in the attached appendices. 2.0 Project Introduction 2.1 Project Location- Project is located at 395 Thunderbowl Ln. / Aspen Highlands Village Block: A Lot: 7 City of Aspen, County of Pitkin, State of Colorado. See Appendix A for a Detailed Project Vicinity Map. 2.2 Disturbance Area- .693 acres 2.3 Description of work- The scope of work will include all that is necessary for the construction of a 9,500SF single-family residence. Project duration is estimated at 27 months from acceptance of Building Permit until Close-out. All utilities connections will be coordinated and completed prior to the completion of work. Construction waste will be hauled off via Haul/Emergency Access Map to the Landfill for recycling. See Appendix B 3.0 Project Documentation 3.1 Permits- A. Building Permit- Please reference the permit application B. MEP Permits- Please reference the permit application C. Tower Crane Permit- Please reference the permit application 3.2 Public Notification- A letter shall be sent to all neighbors within 300 feet of the Project no less than ten days prior to construction, along with monthly updates until Project completion. Updates are to identify any traffic/pedestrian concerns and to outline hauling/staging operations. A pre-construction meeting between the Site Supervisor and all Sub-Contractors shall occur ten days prior to construction with all impacted stakeholders to be notified as well. 3.3 Project Sign- See Appendix C City of Aspen Received 07/26/17 Building Department THUNDERBOWL LOT #7 CONSTRUCTION MANAGEMENT PLAN 3.4 Project Contacts- Owner Rep: James I. Veshancey 1261 Juniper Hill Road Aspen, CO 81611 (970) 319-8686 Office jamesve@me.com Contractor: Structural Associates Co. 4185 County Rd. 154 Glenwood Springs, CO 81601 Project Manager: Brian Hanlen (970) 945-0147 Office (970) 846-3216 Mobile Site Supervisor: Phil Perry Structural Associates Co. 4185 County Rd. 154 Glenwood Springs, CO 81601 (970) 456-7370 Mobile Safety Officer: N/A (Contact Site Supervisor) Traffic Officer: N/A (Contact Site Supervisor) Erosion Control: N/A (Contact Site Supervisor) 4.0 Project Implementation: 4.1 Dates of Construction- Pending Contract Procurement 4.2 Hours of Construction- Will be limited to 7:30 a.m. to 5:30 p.m. Monday through Friday, 9:00 a.m. through 5:00 p.m. Saturdays, with no work permitted on Sundays and federally designated holidays and other construction limitations set by the City of Aspen. 4.3 Sequence of Construction- See Appendix D- Project Schedule 4.4 Adjoining Property Owners- Adjoining properties will be protected from onsite runoff by silt fencing and Project-Site isolation. Notification of all foreseen disturbances will be communicated to adjacent neighbors by the Site Supervisor. All notices will be made prior to the initiation of any such disturbances; this includes but is not limited to: noise disturbances, hauling/staging, Right of Way limitations/disruptions. 4.5 Project Fencing- See Appendix E- Site Plan City of Aspen Received 07/26/17 Building Department THUNDERBOWL LOT #7 CONSTRUCTION MANAGEMENT PLAN 4.6 Natural Environment- No adverse effects on the nearby, natural environment are anticipated. Any unforeseen environmental impacts will be promptly mitigated by Structural Associates’ management team and controlled in accordance with the City of Aspen’s building regulations. 5.0 Project Management: 5.1 Parking Management- All parking to be contained along street front or public parking areas designated by permit. 5.2 Emergency Vehicle Access- Emergency vehicle access will not be affected by the scope of work identified in this CMP. See Appendix B- Haul/Emergency Access Map 5.3 Parking Details- Public transportation and carpooling efforts will be made to reduce the amount of onsite parking required for construction. Parallel parking will be available along site-curb with additional parking available on the North end of site (as needed). See Appendix E- Site Plan 5.4 Staging Areas- Designated staging area will be limited to onsite property boundary. 5.5 Construction Trailer, Materials Storage, and Waste Management- A construction trailer will be required as a jobsite office. Material storage will be reserved to on-site and identified on the CMP site plan. A dumpster will be located on-site and efforts will be made to recycle cardboard, drywall, wood, and metal via small waste containers. A bear proof container for food will be adjacent to the dumpster. Portable restrooms will be available for workers. 6.0 Traffic Control 6.1 General- All required traffic control shall be performed on-site by supervisory staff. Professional Traffic Control Companies will be contracted as required. 6.2 Haul Routes- See Appendix B- Haul/Emergency Access Map 6.3 Delivery requirements- No affect on any public roads will occur as a result of the scope of work identified in this CMP. Due to staging limitations, only (1) delivery will be permitted at any one time. Delivery schedule shall fall within the general project hours of 7:30 to 5:30 Monday through Friday. No idling of delivery vehicles will be permitted for longer than five minutes. 6.4 Traffic Control Plan- All construction related traffic shall be controlled and maintained by the on-site Supervisor as outlined in the Haul/Emergency Access Map. See Appendix B 7.0 Pedestrian Protection 7.1 General- All construction activity will comply with safety per MUTCD chapter 6D, the Americans with Disability Act, and IBC Chapter 33. City of Aspen Received 07/26/17 Building Department THUNDERBOWL LOT #7 CONSTRUCTION MANAGEMENT PLAN 8.0 Sediment and Erosion Control 8.1 Requirements- Erosion control and storm water management will be as directed by the project’s civil engineer and shown on designated plan sheets: (Erosion Control Plan, Storm Water Management Plan). A perimeter encompassing silt fence will aid in the mitigation of onsite runoff; SA is to ensure proper installation and maintenance. 9.0 Fugitive Dust Control 9.1 Fugitive Dust Control Plan- All fugitive dust will be controlled by watering as required. 10.0 Emissions 10.1 General- All onsite vehicles/equipment will be maintained to manufacturer’s specifications. 10.2 Diesel Engines- Emissions from diesel powered engines shall have an opacity of no darker than 40% except for ten seconds during start up. 11.0 Noise Suppression 11.1 General- All construction activity shall comply with the City of Aspen’s noise limitations. Appendices: Appendix A: Project Vicinity Map Appendix B: Haul/Emergency Access Map Appendix C: Project Sign Appendix D: Project Schedule Appendix E: Site Plan City of Aspen Received 07/26/17 Building Department Structural Associates Construction Management Plan   Appendix A: Project Vicinity Map City of Aspen Received 07/26/17 Building Department Structural Associates Construction Management Plan   Appendix B: Haul Route / Emergency Access City of Aspen Received 07/26/17 Building Department Structural Associates Construction Management Plan   Appendix C: Project Sign City of Aspen Received 07/26/17 Building Department ID Task NameDuration Start Finish1PRE-CONSTRUCTION38 daysThu 7/20/17Mon 9/11/172Permits30 daysThu 7/20/17Wed 8/30/173Survey 1 dayFri 9/1/17Fri 9/1/174Jobsite layout (Trailer, Dumpster, Temp Toilet, Silt Fence, Parking, & Laydown)5 daysTue 9/5/17Mon 9/11/175EXCAVATION 159 daysFri 9/8/17Fri 5/4/186Grub Site1 dayFri 9/8/17Fri 9/8/177Create Jobsite Access & Parking3 daysFri 9/8/17Tue 9/12/178Install Temporary Electrical Panel1 dayTue 9/12/17Tue 9/12/179Strip & Stockpile Topsoil4 daysTue 9/12/17Fri 9/15/1710Excavate Foundation 11 daysFri 9/15/17Fri 9/29/1711Underground Slab Prep5 daysMon 11/13/17Fri 11/17/1712Install Foundation Drain 5 daysWed 11/15/17Tue 11/21/1713Backfill Foundation11 daysMon 11/20/17Fri 12/8/1714Finish Backfill5 daysMon 12/18/17Fri 12/22/1715Final Grade5 daysMon 4/30/18Fri 5/4/1816UTILITIES10 daysMon 4/23/18Fri 5/4/1817Install Water Line2 daysMon 4/23/18Tue 4/24/1818Install Sewer Line 3 daysWed 4/25/18Fri 4/27/1819Install Natural Gas Line3 daysMon 4/30/18Wed 5/2/1820Install Phone & Cable Line2 daysThu 5/3/18Fri 5/4/1821CONCRETE 165 daysThu 9/28/17Fri 6/1/1822Form & Pour Footings8 daysThu 9/28/17Mon 10/9/1723Form & Pour Walls24 daysTue 10/10/17Fri 11/10/1724Form & Pour Lower Slab5 daysMon 12/11/17Fri 12/15/1725Form & Pour Garage Slab5 daysMon 5/28/18Fri 6/1/1826SITE CONCRETE21 daysMon 11/13/17Fri 12/15/1727Form & Pour Site Footings9 daysMon 11/13/17Wed 11/29/1728Form & Pour Site Walls15 daysFri 11/24/17Fri 12/15/1729UNDERGROUND MEP16 daysMon 11/13/17Fri 12/8/1730Underground Radon Rough-in3 daysMon 11/13/17Wed 11/15/1731Underground Plumbing Rough-in4 daysThu 11/16/17Tue 11/21/1732Install Rigid Foam Insulation 4 daysTue 11/28/17Fri 12/1/1733Hydronic Rough-in5 daysMon 12/4/17Fri 12/8/1734WATERPROOFING 26 daysMon 11/13/17Fri 12/22/1735Waterproof Foundation Walls 5 daysMon 11/13/17Fri 11/17/1736Waterproof Site Walls 5 daysMon 12/18/17Fri 12/22/1737STRUCTURAL STEEL 118 daysMon 10/2/17Fri 3/30/1838Structural Steel Shop Drawing Review & Approval20 daysMon 10/2/17Fri 10/27/1739Main Level Steel Fabrication 16 daysMon 11/13/17Fri 12/8/1740Deliver & Install Main Level Structural Steel 10 daysMon 12/11/17Fri 12/22/1741Upper Level Steel Fabrication 15 daysMon 1/22/18Fri 2/9/1842Deliver & Install Upper Level Structural Steel 10 daysMon 2/12/18Fri 2/23/1843Roof Level Steel Fabrication 15 daysMon 2/26/18Fri 3/16/1844Deliver & Install Roof Level Structural Steel 10 daysMon 3/19/18Fri 3/30/1845FRAMING 110 daysWed 12/6/17Fri 5/18/1846Set Tower Crane 3 daysWed 12/6/17Fri 12/8/1747Lower Level Framing22 daysMon 12/11/17Fri 1/19/1848Main Level Framing35 daysMon 1/22/18Fri 3/9/1849Upper Level Framing20 daysMon 2/26/18Fri 3/23/1850Roof Framing30 daysMon 3/26/18Fri 5/4/1851Finish Framing20 daysMon 4/23/18Fri 5/18/1852ROOFING 292 daysMon 5/14/18Fri 7/12/1953Dry-In15 daysMon 5/14/18Fri 6/1/1854Install Metal Roofing25 daysMon 6/4/18Fri 7/6/1855Install Snow Guards and Fences 10 daysMon 7/2/18Fri 7/13/1856Install Chimney Caps 2 daysFri 7/13/18Mon 7/16/1857Install Gutters & Downspouts10 daysMon 7/16/18Fri 7/27/1858Install Heat Tape 5 daysMon 7/30/18Fri 8/3/1859Preparation for Green Roof15 daysMon 6/3/19Fri 6/21/1960Install Decorative Ballast 15 daysMon 6/24/19Fri 7/12/1961WINDOWS & DOORS 170 daysMon 11/13/17Tue 7/24/1862Window & Ext Door Shop Drawings16 daysMon 11/13/17Fri 12/8/1763Window & Ext Door Shop Drawings Review12 daysMon 12/11/17Fri 1/5/1864Order Window & Exterior Doors1 dayMon 1/8/18Mon 1/8/1865Windows & Door Delivery 2 daysThu 5/24/18Fri 5/25/1866Window & Ext Doors Installation20 daysMon 5/28/18Fri 6/22/1867Garage Door Installation 2 daysMon 7/23/18Tue 7/24/1868EXTERIOR DECORATIVE STEEL 45 daysMon 4/30/18Fri 6/29/1869Shop Drawings & Review15 daysMon 4/30/18Fri 5/18/1870Ext. Steel Fabrication15 daysMon 5/21/18Fri 6/8/1871Installation of Ext. Decorative Steel15 daysMon 6/11/18Fri 6/29/1872EXTERIOR FINISHES 278 daysFri 3/9/18Fri 4/19/1973Order Wood Siding & Trim1 dayFri 3/9/18Fri 3/9/1874Pre-Finish Wood Siding & Trim10 daysMon 4/30/18Fri 5/11/1875Install Soffit & Fascia 25 daysMon 5/14/18Fri 6/15/1876Install Wood Siding45 daysMon 6/18/18Fri 8/17/1877Build Pergola10 daysMon 8/20/18Fri 8/31/1878Install Alternative Wood Siding35 daysMon 3/4/19Fri 4/19/1979EXTERIOR MASONRY 115 daysMon 4/30/18Fri 10/5/1880Install Wall Veneer60 daysMon 4/30/18Fri 7/20/1881Site Wall Veneer30 daysMon 7/9/18Fri 8/17/1882Install Patio 20 daysMon 8/6/18Fri 8/31/1883Install Upper Patio25 daysMon 9/3/18Fri 10/5/1884MEP ROUGH-IN 66 daysMon 5/7/18Mon 8/6/1885Fire Suppression System Rough-In25 daysMon 5/7/18Fri 6/8/1886HVAC Rough-In55 daysMon 5/14/18Fri 7/27/1887Pluming Rough-In30 daysMon 5/28/18Fri 7/6/1888Water Treatment Install10 daysMon 6/18/18Fri 6/29/1889Electric Rough-In40 daysMon 6/11/18Fri 8/3/1890AV Rough-In25 daysMon 7/2/18Fri 8/3/1891Security Pre-Wire15 daysMon 7/9/18Fri 7/27/1892Rough-In Inspection1 dayMon 8/6/18Mon 8/6/1893BUILD MECHANICAL ROOM30 daysMon 9/10/18Fri 10/19/1894HVAC20 daysMon 9/10/18Fri 10/5/1895Plumbing10 daysMon 10/1/18Fri 10/12/1896Electric10 daysMon 10/8/18Fri 10/19/1897INSULATION 14 daysTue 8/7/18Fri 8/24/1898Insulate Walls9 daysTue 8/7/18Fri 8/17/1899Insulate Roof8 daysMon 8/13/18Wed 8/22/18100Insulation Inspection2 daysThu 8/23/18Fri 8/24/18101INTERIOR MASONRY 64 daysTue 8/14/18Fri 11/9/18102Install wall veneer34 daysTue 8/14/18Fri 9/28/18103Install stone floors 10 daysMon 10/29/18Fri 11/9/18104POOL ROUGH-IN15 daysMon 5/21/18Fri 6/8/18105Excavate Pool & Spa5 daysMon 5/21/18Fri 5/25/18106Rough-In for Pool & Spa5 daysMon 5/28/18Fri 6/1/18107Form and Pour Pool & Spa5 daysMon 6/4/18Fri 6/8/18108DRYWALL 247 daysMon 8/6/18Fri 8/2/19109Hang Drywall30 daysMon 8/27/18Fri 10/5/18110Tape & Finish35 daysMon 9/17/18Fri 11/2/18111Plaster20 daysMon 4/22/19Fri 5/17/19112Okan Top Coat5 daysMon 5/20/19Fri 5/24/19113Drywall Inspection1 dayFri 9/7/18Fri 9/7/18114Drywall Inspection1 dayFri 9/21/18Fri 9/21/18115Drywall Inspection1 dayMon 10/8/18Mon 10/8/18116WOOD FLOOR 247 daysMon 8/6/18Fri 8/2/19117Order Wood Floor1 dayMon 8/6/18Mon 8/6/18118Acclimate Wood Flooring35 daysMon 9/17/18Fri 11/2/18119Install Wood Flooring26 daysMon 11/5/18Fri 12/14/18120Sand & Finish Wood Flooring11 daysMon 12/17/18Fri 1/11/19121Final Coat 10 daysMon 7/22/19Fri 8/2/19122INTERIOR DOORS78 daysMon 8/6/18Wed 11/21/18123Interior Door Shop Drawings & Approval20 daysMon 8/6/18Fri 8/31/18124Order Interior Doors1 dayMon 9/3/18Mon 9/3/18125Interior Door Delivery2 daysMon 10/29/18Tue 10/30/18126Interior Door Installation16 daysWed 10/31/18Wed 11/21/18127INTERIOR CARPENTRY 182 daysMon 11/5/18Fri 8/2/19128Install Ceiling Paneling35 daysMon 11/5/18Wed 1/9/19129Staircase Installation 35 daysMon 1/7/19Fri 2/22/19130Install Case & Base34 daysWed 11/28/18Fri 1/25/19131Specialty Trim Work35 daysMon 1/7/19Fri 2/22/19132Punchlist 50 daysMon 5/27/19Fri 8/2/19133TILE & SLAB 127 daysMon 8/27/18Fri 3/8/19134Shop drawing and review30 daysMon 8/27/18Fri 10/5/18135Order Materials1 dayMon 10/8/18Mon 10/8/18136Delivery of Tile 1 dayFri 11/30/18Fri 11/30/18137Install Shower Pans8 daysWed 11/28/18Fri 12/7/18138Install Tile56 daysMon 12/10/18Fri 3/8/19139Lower Level 16 daysMon 12/10/18Fri 1/11/19140Main Level20 daysMon 1/14/19Fri 2/8/19141Upper Level20 daysMon 2/11/19Fri 3/8/19142Install Kitchen Backsplash5 daysMon 3/4/19Fri 3/8/19143Template & Fabrication for Shower Slab10 daysMon 12/24/18Wed 1/16/19144Delivery of Slab1 dayFri 1/11/19Fri 1/11/19145Install Lower Slab15 daysMon 1/14/19Fri 2/1/19146Install Main Slab15 daysMon 2/4/19Fri 2/22/19147Install Upper Slab15 daysMon 2/25/19Fri 3/15/19148CABINETRY 132 daysMon 8/13/18Fri 3/1/19149Shop drawings and review30 daysMon 8/13/18Fri 9/21/18150Sample Door / Finish Review & Approval15 daysMon 9/3/18Fri 9/21/18151Order Cabinetry1 dayMon 9/24/18Mon 9/24/18152Cabinetry Fabrication76 daysTue 9/25/18Fri 1/25/19153Delivery of Cabinets2 daysMon 1/28/19Tue 1/29/19154Installation of Cabinets23 daysWed 1/30/19Fri 3/1/19155HARDWARE 15 daysMon 5/27/19Fri 6/14/19156Install Window & Ext Door Hardware5 daysMon 5/27/19Fri 5/31/19157Install Int. Door Hardware5 daysMon 6/3/19Fri 6/7/19158Install Bathroom Hardware5 daysMon 6/10/19Fri 6/14/19159INTERIOR DECORATIVE STEEL 49 daysWed 11/28/18Fri 2/15/19160Shop Drawings & Review18 daysWed 11/28/18Fri 12/21/18161Int. Steel Fabrication17 daysMon 1/7/19Tue 1/29/19162Installation of Int. Decorative Steel13 daysWed 1/30/19Fri 2/15/19163GLASS 64 daysWed 11/28/18Fri 3/8/19164Glass Railing Shop Drawings & Review15 daysMon 1/21/19Fri 2/8/19165Glass Railing Template10 daysMon 2/11/19Fri 2/22/19166Installation of Glass Railing 10 daysMon 2/25/19Fri 3/8/19167Shower Glass Shop Drawings & Review15 daysWed 11/28/18Tue 12/18/18168Installation of Shower Glass: Lower14 daysWed 12/19/18Fri 1/18/19169Installation of Shower Glass: Main15 daysMon 1/14/19Fri 2/1/19170Installation of Shower Glass: Upper15 daysMon 1/28/19Fri 2/15/19171PAINTING 60 daysMon 2/25/19Fri 5/17/19172Finish Wood Ceilings 15 daysMon 2/25/19Fri 3/15/19173Interior Painting Stain30 daysMon 3/11/19Fri 4/19/19174Exterior Paint / Stain 20 daysMon 4/22/19Fri 5/17/19175EXTERIOR CONCRETE 25 daysMon 4/22/19Fri 5/24/19176Driveway & Sidewalk Prep5 daysMon 4/22/19Fri 4/26/19177Install Rigid Insulation4 daysMon 4/29/19Thu 5/2/19178Install Hydronic Tubing & Manifolds 4 daysFri 5/3/19Wed 5/8/19179Form Driveway & Sidewalks5 daysThu 5/9/19Wed 5/15/19180Pour Driveway & Sidewalks7 daysThu 5/16/19Fri 5/24/19181MEP TRIM 60 daysMon 5/27/19Fri 8/16/19182Fire Suppression System Trim-Out10 daysMon 5/27/19Fri 6/7/19183HVAC Trim-Out25 daysMon 5/27/19Fri 6/28/19184Plumbing Trim-Out25 daysMon 5/27/19Fri 6/28/19185Electrical Trim-Out25 daysMon 6/3/19Fri 7/5/19186Security Trim-Out10 daysMon 6/24/19Fri 7/5/19187Appliance Install5 daysMon 6/24/19Fri 6/28/19188Water Treatment Install5 daysMon 6/24/19Fri 6/28/19189HVAC Commissioning3 daysMon 8/12/19Wed 8/14/19190HVAC Test & Balance 2 daysThu 8/15/19Fri 8/16/19191AV50 daysMon 6/17/19Fri 8/23/19192Shade Install10 daysMon 8/12/19Fri 8/23/19193Build Av Room – Install Racks 15 daysMon 6/17/19Fri 7/5/19194AV Trim-Out15 daysMon 6/24/19Fri 7/12/19195Equipment Testing3 daysWed 8/21/19Fri 8/23/19196POOL FINISH30 daysMon 6/24/19Fri 8/2/19197Tile Pool & Spa5 daysMon 6/24/19Fri 6/28/19198Plaster Pool & Spa5 daysMon 7/1/19Fri 7/5/19199Install Pool Mechanical System10 daysMon 7/8/19Fri 7/19/19200Acid Wash2 daysMon 7/22/19Tue 7/23/19201Commission Pool 3 daysWed 7/24/19Fri 7/26/19202Install Pool & Spa Covers 5 daysMon 7/29/19Fri 8/2/19203LANDSCAPING 50 daysMon 5/27/19Fri 8/2/19204Hardscape Install 20 daysMon 5/27/19Fri 6/21/19205Irrigation Install10 daysMon 6/17/19Fri 6/28/19206Softscape Install 20 daysMon 7/1/19Fri 7/26/19207Install Green Roof 15 daysMon 7/15/19Fri 8/2/19208PROJECT CLOSE-OUT 25 daysMon 8/5/19Fri 9/6/19209Final Clean5 daysMon 8/5/19Fri 8/9/19210Demobilization5 daysMon 8/12/19Fri 8/16/19211Dumpster Removal1 dayMon 8/19/19Mon 8/19/19212Temp Toilet Removal 1 dayMon 8/19/19Mon 8/19/19213Final Inspections 5 daysMon 8/19/19Fri 8/23/19214Furniture & Decoration10 daysMon 8/26/19Fri 9/6/19PermitsSurvey Jobsite layout (Trailer, Dumpster, Temp Toilet, Silt Fence, Parking, & Laydown)EXCAVATION Grub SiteCreate Jobsite Access & ParkingInstall Temporary Electrical PanelStrip & Stockpile TopsoilExcavate Foundation Underground Slab PrepInstall Foundation Drain Backfill FoundationFinish BackfillFinal GradeUTILITIESInstall Water LineInstall Sewer Line Install Natural Gas LineInstall Phone & Cable LineCONCRETE Form & Pour FootingsForm & Pour WallsForm & Pour Lower SlabForm & Pour Garage SlabSITE CONCRETEForm & Pour Site FootingsForm & Pour Site WallsUNDERGROUND MEPUnderground Radon Rough-inUnderground Plumbing Rough-inInstall Rigid Foam Insulation Hydronic Rough-inWATERPROOFING Waterproof Foundation Walls Waterproof Site Walls STRUCTURAL STEEL Structural Steel Shop Drawing Review & ApprovalMain Level Steel Fabrication Deliver & Install Main Level Structural Steel Upper Level Steel Fabrication Deliver & Install Upper Level Structural Steel Roof Level Steel Fabrication Deliver & Install Roof Level Structural Steel FRAMING Set Tower Crane Lower Level FramingMain Level FramingUpper Level FramingRoof FramingFinish FramingROOFING Dry-InInstall Metal RoofingInstall Snow Guards and Fences Install Chimney Caps Install Gutters & DownspoutsInstall Heat Tape Preparation for Green RoofInstall Decorative Ballast WINDOWS & DOORS Window & Ext Door Shop DrawingsWindow & Ext Door Shop Drawings ReviewOrder Window & Exterior DoorsWindows & Door Delivery Window & Ext Doors InstallationGarage Door Installation EXTERIOR DECORATIVE STEEL Shop Drawings & ReviewExt. Steel FabricationInstallation of Ext. Decorative SteelEXTERIOR FINISHES Order Wood Siding & TrimPre-Finish Wood Siding & TrimInstall Soffit & Fascia Install Wood SidingBuild PergolaInstall Alternative Wood SidingEXTERIOR MASONRY Install Wall VeneerSite Wall VeneerInstall Patio Install Upper PatioMEP ROUGH-IN Fire Suppression System Rough-InHVAC Rough-InPluming Rough-InWater Treatment InstallElectric Rough-InAV Rough-InSecurity Pre-WireRough-In InspectionBUILD MECHANICAL ROOMBUILD MECHANICAL ROOMHVACPlumbingElectricINSULATION Insulate WallsInsulate RoofInsulation InspectionINTERIOR MASONRY Install wall veneerInstall stone floors POOL ROUGH-INExcavate Pool & SpaRough-In for Pool & SpaForm and Pour Pool & SpaDRYWALL Hang DrywallTape & FinishPlasterOkan Top CoatDrywall InspectionDrywall InspectionWOOD FLOOR Order Wood FloorAcclimate Wood FlooringInstall Wood FlooringSand & Finish Wood FlooringFinal Coat Interior Door Shop Drawings & ApprovalOrder Interior DoorsInterior Door DeliveryInterior Door InstallationINTERIOR CARPENTRY Install Ceiling PanelingStaircase Installation Install Case & BaseSpecialty Trim WorkPunchlist TILE & SLAB Shop drawing and reviewOrder MaterialsDelivery of Tile Install Shower PansInstall TileLower Level Main LevelUpper LevelInstall Kitchen BacksplashTemplate & Fabrication for Shower SlabDelivery of SlabInstall Lower SlabInstall Main SlabInstall Upper SlabCABINETRY Shop drawings and reviewSample Door / Finish Review & ApprovalOrder CabinetryCabinetry FabricationDelivery of CabinetsInstallation of CabinetsHARDWARE Install Window & Ext Door HardwareInstall Window & Ext Door HardwareInstall Int. Door HardwareInstall Int. Door HardwareInstall Bathroom HardwareINTERIOR DECORATIVE STEEL Shop Drawings & ReviewInt. Steel FabricationInstallation of Int. Decorative SteelGLASS Glass Railing Shop Drawings & ReviewGlass Railing TemplateInstallation of Glass Railing Shower Glass Shop Drawings & ReviewInstallation of Shower Glass: LowerInstallation of Shower Glass: MainInstallation of Shower Glass: UpperPAINTING Finish Wood Ceilings Interior Painting StainExterior Paint / Stain EXTERIOR CONCRETE Driveway & Sidewalk PrepInstall Rigid InsulationInstall Hydronic Tubing & Manifolds Form Driveway & SidewalksPour Driveway & SidewalksMEP TRIM Fire Suppression System Trim-OutHVAC Trim-OutPlumbing Trim-OutElectrical Trim-OutSecurity Trim-OutAppliance InstallWater Treatment InstallHVAC CommissioningHVAC Test & Balance AVShade InstallBuild Av Room – Install Racks AV Trim-OutEquipment TestingTile Pool & SpaPlaster Pool & SpaInstall Pool Mechanical SystemAcid WashCommission Pool Install Pool & Spa Covers LANDSCAPING Hardscape Install Irrigation InstallSoftscape Install Install Green Roof PROJECT CLOSE-OUT Final CleanDemobilizationDumpster RemovalTemp Toilet Removal Final Inspections Furniture & DecorationTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTJul 16, '17Jul 23, '17Jul 30, '17Aug 6, '17Aug 13, '17Aug 20, '17Aug 27, '17Sep 3, '17Sep 10, '17Sep 17, '17Sep 24, '17Oct 1, '17Oct 8, '17Oct 15, '17Oct 22, '17Oct 29, '17Nov 5, '17Nov 12, '17Nov 19, '17Nov 26, '17Dec 3, '17Dec 10, '17Dec 17, '17Dec 24, '17Dec 31, '17Jan 7, '18Jan 14, '18Jan 21, '18Jan 28, '18Feb 4, '18Feb 11, '18Feb 18, '18Feb 25, '18Mar 4, '18Mar 11, '18Mar 18, '18Mar 25, '18Apr 1, '18Apr 8, '18Apr 15, '18Apr 22, '18Apr 29, '18May 6, '18May 13, '18May 20, '18May 27, '18Jun 3, '18Jun 10, '18Jun 17, '18Jun 24, '18Jul 1, '18Jul 8, '18Jul 15, '18Jul 22, '18Jul 29, '18Aug 5, '18Aug 12, '18Aug 19, '18Aug 26, '18Sep 2, '18Sep 9, '18Sep 16, '18Sep 23, '18Sep 30, '18Oct 7, '18Oct 14, '18Oct 21, '18Oct 28, '18Nov 4, '18Nov 11, '18Nov 18, '18Nov 25, '18Dec 2, '18Dec 9, '18Dec 16, '18Dec 23, '18Dec 30, '18Jan 6, '19Jan 13, '19Jan 20, '19Jan 27, '19Feb 3, '19Feb 10, '19Feb 17, '19Feb 24, '19Mar 3, '19Mar 10, '19Mar 17, '19Mar 24, '19Mar 31, '19Apr 7, '19Apr 14, '19Apr 21, '19Apr 28, '19May 5, '19May 12, '19May 19, '19May 26, '19Jun 2, '19Jun 9, '19Jun 16, '19Jun 23, '19Jun 30, '19Jul 7, '19Jul 14, '19Jul 21, '19Jul 28, '19Aug 4, '19Aug 11, '19Aug 18, '19Aug 25, '19Sep 1, '19Sep 8, '19Sep 15, '19Sep 22, '19Thunderbowl Lot #7Appendix D: Schedule6/27/2017City of Aspen Received 07/26/17Building Department DRAWING ISSUELOT 7 THUNDERBOWL Aspen, COSHEET No. CONCEPTUAL DESIGN DRAWN BY: PROJECT No:1113 MTE PERMIT SET 418 East Cooper Ave Suite 206 Aspen, CO 81611 970-925-3444 970-920-2186 All ideas, designs, arrangements and plans indicated or represented by this drawing are TEL FAX 2.3 SITE PLAN (PROPOSED) (1" = 10'-0") 2/10/17 owned by and are the property of David Johnston Architects, PC and developed for use and in conjunction with the specified project. None of the ideas, designs, arrangements or plans shall be used by or disclosed for any purpose whatsoever without the written authorization of David Johnston Architects, PC.X:\Projects\Aspen\'16 Projects\1605 - Lot 7 Thunderbowl\DWG\1605 - LOT 7 THUNDERBOWL - CURRENT PLANS.pln | 9:27 AM | Monday, April 24, 20173/06/17 SHEET No.FRONT SETBACKDNDWDWSTRETCHBREAKFAST NOOK12"STRETCHFIRE PLACE ELEVATION12"SPEED OVENABOVE30" OVENCOFFEE UNIT ORSTEAM OVENABOVE30" OVENA18"PANTRYUNIT18"WINEUNITC30"REF DRWS ?PREPSINKPLOTTER/ PRINTERBDSTRETCH BREAKFAST NOOK 12"BUTLERSPANTRYCHILDRENSTOYS/TRANSITIONALEXPANDEDPANTRYMEDIUMTALLOPENSTORAGESERVING UNITAREAELEVATORPOWDERROOMPANTRYSUGGESTEDCLOUD ABOVE ISLANDW/ PERIMETERLIGHT DETAIL& DOWN LIGHTINGGHJKICLBREAKFAST NOOK/DOOR OPENING/SHUTTER UNIT IN PANTRYFIREPLACEBUIL D I N G ENV E L O P E LOT 8LOT 6EDG E OF PAVE M E N T BUILDING ENVELOPE10' ACTI V I T Y EASE M E N T 10' ACTIVITY EASEMENTP R O P E R Y B O U N D A R Y PRO P E R Y BOU N D A R Y 5' A C T I V I T Y E N V E L O P EPROPERY BOUNDARYBUILDING ENVELOPEUTILITYEASEMENTTELEPHONE RISERCABLE RISERELECTRIC TRANSFORMER823482368238824082428244824682488250825282548256825882608262THUNDERBO W L LANE5' ACTIVITY ENVELOPEB U I L D I N G E N V E L O P E LOT 70.693 ACRESPRIVATE SKI EASEMENTNFOUND NO. 5 REBAR WITHYELLOW PLASTIC CAP MARKEDL.S. #20133ELEV = 8,232.43'FIRE HYDRANTPOOLFIREPITOUTDOOR LOUNGEDNBBQDNDNDNSPABENCHWATERFEATURESITE 8,244' = ARCH 100'-0" On Site Tower Crane Dumpster, Recycling, Bear-Proof Container Construction Office Material Laydown Portable Toilets Parallel Parking Parallel Parking Concrete Washout Project Fencing / Silt Barrier Project Fencing / Silt Barrier Additional Laydown/Parking (As Necessary) Appendix E: Site Plan City of Aspen Received 07/26/17 Building Department