HomeMy WebLinkAboutFile Documents.395 Thunderbowl Ln.0255.2018 (3).ARBKParcel ID #:
Collector
Aspect,
Degress from
True South
Collector Tilt,
Degrees From
Horizontal
Solar
Orientation
Adjustment
Factor
DC side capacity
(kW)
Inverter capacity
(kW)
kW for
credit
kW Mitigation
Credit
Collector Group 1 5 5
93.10%10.15 10.15 9.45 kW
Collector Group 2 87.00%0 0.00 kW
Collector Group 3 87.00%0 0.00 kW
Collector Group 4 87.00%0 0.00 kW
Collector Group 5 87.00%0 0.00 kW
Collector Group 6 87.00%0 0.00 kW
Collector Group 7 87.00%0 0.00 kW
Collector Group 8 87.00%0 0.00 kW
Collector Group 9 87.00%0 0.00 kW
Collector Group 10 87.00%0 0.00 kW
Collector Group 11 87.00%0 0.00 kW
Collector Group 12 87.00%0 0.00 kW
Collector Group 13 87.00%0 0.00 kW
Collector Group 14 87.00%0 0.00 kW
Collector Group 15 87.00%0 0.00 kW
Collector Group 16 87.00%0 0.00 kW
Collector Group 17 87.00%0 0.00 kW
Collector Group 18 87.00%0 0.00 kW
Collector Group 19 87.00%0 0.00 kW
Collector Group 20 87.00%0 0.00 kW
Total:9.45 kW
$ Mitigation Credit:64,874.87$
Instructions:
1)
2)
3) DC side capacity is the total labled panel output kW in a group.
4) Inverter capacity is the recommended input power in kW of your inverter(s).
5)
6)
7)
8)
PREPARED BY:Date: 8/29/2019
Print Name:
Signature:
Phone & EMail:
REVIEWED:Date:
PV WORKSHEET
City of Aspen Version 11.1 UpdAted MArCh 28 2017
Permit Number:
Enter the aspect and tilt for each group. The solar orientation adjustment factor is automatically
calculated.
PROJECT ADDRESS:
The mitigation credit will be automatically entered into your RREMP or CREMP form. If your project has both RREMP and
CREMP, it will automatically divide the credits up, with priority given to mitigating the CREMP fee.
Determine how many collector groups you have. Groups are used to differentiate between collectors
(panels) with different tilts, aspects, sizing, or inverters. If all your collectors are installed similarily, you
might have just one group.
Lot 7 Thunderbowl Aspen Highlands
Charles Langston
970-748-8520 charles@aec-vail.com
The kW mitigation credit is totalled and multiplied by $6865.32/kW to get the $ Mitigation Credit
You will be given credit for the lesser of the labeled panel output or the inverter.
The kW for credit is multiplied by the solar orientation adjustment factor to get kW mitigation credit.
** micro inverter on each panel
Bonnie Muhigirwa 9/18/19