HomeMy WebLinkAboutFile Documents.415 E Hyman Ave.0078.2017 (2).ACBKPROJECT ADDRESS:415 East Hyman Ave
Aspen, CO 81611
2.0 PROJECT INTRODUCTION
2.1 DISTURBANCE AREA
2.2 LOCATION
2.3 DESCRIPTION
3.0 PROJECT DOCUMENTATION
3.1 PERMITS / OTHER DOCUMENTS
3.2 PUBLIC NOTIFICATION
3.3 PROJECT SIGN
3.4 CONTACT DESIGNATION
4.0 PROJECT IMPLEMENTATION
4.1 DATES OF CONSTRUCTION
4.2 HOURS OF CONSTRUCTION
4.3 PHASING OF CONSTRUCTION
4.4 ADJOINING PROPERTY OWNERS
4.5 PROJECT FENCING
4.6 PUBLIC HEALTH AND WELFARE
4.7 NATURAL ENVIRONMENT
5.0 PARKING MANAGEMENT
5.1 PARKING MANAGEMENT FORM
5.2 EMERGENCY VEHICLE ACCESS
5.3 CONSTRUCTION PARKING DETAILS
Roughly 1,300 sq.ft.
See vicinity map on plans
Tenant improvement of existing office space.
N/A
Include all permits / inspections with the Permit Set of Plans. Copies of all Ordinances
included with the CMP
Completed.
Completed.
Directory of contacts on a separate document. All key personnel and emergency
numbers included and available on site.
Project commencement planned for May, 2017
M-F 7:30AM-5:30PM, Saturday 9-5, and no work Sundays and Holidays
All work completed before August, 2017
Requirements understood. No impact or endangerment.
As necessary strictly for parking management.
CMP will be followed to maintain the standards and requirements outlined.
Parking permits will not be needed. Limited subcontractors onsite each day to use
designated spots for each unit.
Access will be maintained at all times.
Parking permits will not be needed. Limited subcontractors onsite each day.
1
5.4 STAGING AREAS
5.5 TRAILER, MATERIALS, TEMP
FACILITIES
6.0 TRAFFIC CONTROL
6.1 GENERAL
6.2 HAUL ROUTES
6.3 ONSITE VEHICLE LIMITATIONS
6.4 DELIVERY REQUIREMENTS
6.5 TRAFFIC CONTROL PLAN
7.0 PEDESTRIAN PROTECTION
7.1 GENERAL
8.0 SEDIMENT AND EROSION CONTROL
8.1 REQUIREMENTS
8.2 SMUGGLER MT RESTRICTIONS
9.0 FUGITIVE DUST CONTROL
9.1 DUST CONTROL PLAN N/A
9.2 REQUIREMENTS
10.0 EMISSIONS
10.1 GENERAL
10.2 EMISSIONS FROM DIESEL ENGINES
11.0 NOISE SUPPRESSION
11.1 GENERAL
11.2 NOISE SUPPRESSION PLAN
11.3 REQUIREMENTS
11.4 SPECIFIC RESTRICTIONS
12.0 ENFORCEMENT
12.1 CONSTRUCTION MITIGATION
OFFICER
12.2 CORRECTIVE ACTION
12.3 INSPECTION REPORTS
Read and acknowledged
Proper suppression will be implemented on all equipment.
Timing requirements understood.
No manufacturing will take place.
Read and acknowledged
Read and acknowledged
N/A
N/A
N/A
Exterior noise at the lot line shall be kept below 80 decibels.
May not be applicable- no pedestrian corridor / sidewalks.
N/A
N/A
Traffic control is not expected.
N/A
Construction workers will commute and carpool in the work trucks, none of which are
larger than typical 2 axle trucks.
No more than 1 delivery vehicle will be scheduled at a time. Deliveries will be pre-
scheduled.
N/A- due to low volume and work location.
Not needed.
no outdoor temp facilities are needed.
2
3