HomeMy WebLinkAboutFile Documents.934 S Mill St.0095.2018 (3).ARBKConstruction Management Plan
934 S. Mill Street, Aspen, CO 81611
April 10, 2018
1.0 General
a) Total SF of soil disturbance/SF of Building demolition:
a. There is no native soil disturbance for this project. Addition is located on existing
deck/patio.
b. The is approximately 196 SF of building demolition in the areas of the kitchen, pantry,
living room and dining room as shown on the plans.
b) Table of Contents per the CMP checklist
2.0 Project Introduction
2.1 Total Project Disturbance Area: there is no native soil disturbance area because the addition
is located on existing deck/patio and utilizing the existing grade beam for the foundation.
This area comprises of 196 sf. Approximately 1,195 sf of the interior will be renovated with
some new windows, new skylights, new addition to the breakfast area and the pantry. As
well as new paint/stain in the affected areas.
2.2 Project Vicinity Map:
4/11/2018
2.3 Description that includes:
2.3.1 Background information: The existing home was originally built in 2008/09. It is
located at Lot 5 in the Aspen Mountain PUD. The proposed work involved
adding a breakfast room and removing bays in the living and dining room and
pantry. There is no net change to the buildings FAR or gross square footage as
we will be removing an equal amount of square footage as what we are adding.
There will be new windows and skylights added to the home. Refer to the plans
by Galambos Architects Inc.
2.3.2 The development type is a renovation single family residential.
3.0 Project Documentation:
3.1 Describe permit types, list permit #s and include copies of all permits: there are no open
permits on this project. The contractor will maintain all applicable local, state and federal
licenses and permits that apply to the construction project.
3.2 Indicate project notification per CMP manual: A project sign will be posted at the address.
This project is in a private neighborhood that is monitored by the Top of Mill HOA. The Top
of Mill HOA and the neighbors will be notified of the construction scope and duration of this
project.
3.3 Project sign: A project sign will be constructed and posted. See Appendix A.
3.4 The contact list is as follows:
3.4.1 Owner: SMSA Capital LLC, 3450 Sacramento Street #722, San Francisco, CA
94118.
3.4.2 Contractor: Wonderland Construction Inc., Bryan Murray, (970) 948‐1396
76 Cherry Lane, Basalt, CO 81821
3.4.3 Site supervisor: TBD
3.4.4 Safety Officer: N/A.
3.4.5 Traffic Officer: N/A.
3.4.6 Erosion Control Representative: N/A.
4.0 Project Implementation:
4.1 Dates of Construction: June 23‐Dec 23, 2018. No work on July 4th, labor day or Thanksgiving
Day. Monday through Saturday. This project is not located within the CRA.
4.2 Hours of Construction: 7:30 Am – 5:30 Monday thru Friday. To 5:00 pm on Saturdays.
4.3 Construction Schedule: approximately 5 ½ month June 23‐Dec 23, 2018.
4.4 No project fencing required
4.5 No tree protection required
4.6 No park issues related to trees, driplines required
5.0 Project Management:
5.1 Parking Management Form: This project is located on a private street controlled by the Top
of Mill HOA. All parking will be on site as there is room for 3 work vehicles. Any additional
vehicles will be required to obtain parking permits from the Top of Mill HOA. See Appendix
B for map showing parking locations.
5.2 The Contractor has read the Emergency vehicle access and attached is a copy of Ordinance
35.
5.3 Not used in checklist
5.4 Map showing location of staging, trailer, materials, waste management, recycling. See
attached map (appendix B).
5.4.1 Staging: One delivery at a time and all deliveries will be staged in the garage
5.4.2 Materials: all materials will be stored in the garage
4/11/2018
5.4.3 Waste management: Wonderland Construction Inc owns a trash trailer. All
trash will be stored inside the garage and trash will be picked up on‐site as
needed. A portable Construction Toilet will be on site the duration of the
project.
5.4.4 Recycling: all recyclable materials will go to the correct location.
6.0 Traffic Control:
6.1 Not used in checklist
6.2 Project haul routes: It is not anticipated that this project will utilize any heavy hauling
equipment. But in case it does, see attached map.
6.3 Weight and size limitation of vehicles: N/A
6.4 Construction vehicle actives
6.4.1 Maximum number of deliveries at a time: One delivery at a time.
6.4.2 Hours of deliveries: during construction hours as noted in 4.2 above.
6.4.3 Exceptions: no exceptions.
6.5 Traffic Control Plan: N/A
8.0 Sediment and Erosion Control: N/A
9.0 Fugitive Dust Control: N/A
10.0 Emmissions: N/A
11.0 Noise Suppression: N/A.
4/11/2018
Appendix A Job Sign
934 South Mill Renovation
BUILDING PERMIT # TBD
Wonderland Construction Inc.
General Contractor Contact:
Bryan Murray
(970) 948‐ 1396
Emergency Phone#
(970) 948‐1396
24 Hour Emergency Contact:
Bryan Murray (970) 948‐1396