HomeMy WebLinkAboutFile Documents.515 E Hopkins Ave.0120.2018 (2).ACBK Construction Management Plan
Regan construction
Bootsy Bellows Aspen
11/16/2018
Page 1 of 6
Address: 515 E. Hopkins
Permits Applied for:
tenant Finish
Property Owner’s name:
Bootsy Aspen, LLC
Andrew Sandler
(617) 233-4504 cell
Andrew@bootsybellows.com
Architect
David Johnson Architects
119 S. Spring Street , Aspen, Colorado 81611
970-925-3444
collin@djarchitects.com
Structural Engineer
James Jackson Romeo, P.E.
Structural Design Consultant, L.L.C.
3901 Mountain Drive, #11, Glenwood Springs, CO 81601
970.945.4742
jim@jjrstructural.com
Site Supervisor
Willis Buckingham
970-948-9150
wbuckingham@reganconst.com
Contractor’s name:
Regan construction
Phone: 970-923-0010
Email: Office@reganconst.com
Willis Buckingham
(970)948-9150
wbuckingham@reganconst.com
11/19/2018
Construction Management Plan
Regan construction
Bootsy Bellows Aspen
11/16/2018
Page 2 of 6
Description of work:
Tenant Finish:
Relocation of the bar and all components.
Remove two walls to increase size of main room.
Remove two walls and replace with glass(VIP/Green room).
Reconfigure entry to public restrooms.
Reconfigure hall from elevator to stairs lower level.
Build and install new bottle service seating.
Install new finishes throughout. (Flooring, paint, wood paneling, mirrors).
Relocate lighting, a/v, audio systems room.
Relocate electrical lighting panel.
Relocate coat check at entry.
Install ADA bar top.
Remove large walk in cooler.
Remove prep kitchen and replace with dish pit.
Add staff bathroom.
All work is interior and all trash and recycling will be remove daily without the use of a
dumpster.
All workers will use the existing bathroom in the lower level of the building.
Public notification:
Contractor shall send notification to neighbors addressing project phasing, schedule,
traffic and/or pedestrian concerns, and hauling/staging operations. Notifications shall
address all adjacent neighbors and all residents affected by possible traffic delays. The
neighborhood notifications shall take place periodically, throughout the duration of the
project, as required.
Dates of construction:
start: 11/16/2018
completion: 1/16/2018
11/19/2018
Construction Management Plan
Regan construction
Bootsy Bellows Aspen
11/16/2018
Page 3 of 6
Hours of construction:
7:30 AM-5:30 PM, Monday through Friday
9:00 AM-5:00 PM, Saturday
Sequencing schedule:
Demo 1 week
Plumbing, Electrical, Mechanical 2 weeks
Framing & Rough ins 1 week
Finishes 3 weeks
Total 2 months
Vicinity map:
S. Galena to landfill
Haul Map:
S. Galena st. to landfill
Attached
11/19/2018
Scanned with CamScanner
11/19/2018
Scanned with CamScanner
11/19/2018