HomeMy WebLinkAboutFile Documents.505 Walnut St.0156.2018 (5).ARBKCONSTRUCTION MANAGEMENT PLAN
Fishman Residence
505 Walnut
Aspen, Colo
Nichols Construction Services inc will be removing and re-installing approximately 870 Sq ft of
concrete sidewalk, curb and driveway at 505 Walnut in order to install snowmelt. The project
schedule will be determined upon receipt of permit. Project should take approximately 5-7
working days. Hours of construction will be from 8:30am to 4:30 pm during the week and if
needed Saturday from 9am-4pm.
Removal of old concrete will be immediately put into a medium sized dump truck and removed
from the site using a small Cat 308 rubber tracked hoe. Re-installation of concrete will be
performed in 3 loads. A pump truck will be used for 1-2 pours. Sequencing will be 1st pour
Curb, 2ndpour, sidewalk and 3rd Driveway. Trucks will turn left off of Gibson street onto Walnut
st to residence and leave via Walnut st to Lone Pine st. Labor trucks will use private parking at
nearby house with permission of owner.
Site drainage will remain the same as originally designed. Silt fencing will be installed at
perimeter of work area. Staging of materials will be directly in the area of work. Mud track will
be in the removed driveway area and consist of gravel area. Work will not be performed at
times of foul weather. Dust control will be by use of clean gravel in work area and with hose to
keep any dust down. All vehicles to be in good working order and work noise shall be held to
less than 80 db.
All neighbors have been notified and they will have cell phone contact number for Tim Nichols
the contractor who will be onsite at all times to address any concerns or issues that might arise.
If there are any questions regarding this plan please call Tim Nichols @ 970-379-2728