HomeMy WebLinkAboutFile Documents.520 E Cooper Ave.0124.2018 (2).ACBKCOMcheck Software Version COMcheck-Web
Interior Lighting Compliance Certificate
Project Title:
2015 IECC
Project Type:Alteration
Permit No.0085.2018.ACBK
Permit Date:10/12/2018
Construction Site:
520 E Cooper
Aspen, Colorado 81611
Owner/Agent:Designer/Contractor:
Project Information
Energy Code:
520 E COOPER UNIT C7&C9 CHANGE ORDER
Allowed Interior Lighting Power
A
Area Category
B
Floor Area
(ft2)
C
Allowed
Watts / ft2
D
Allowed Watts
1-Shared Office Space (Common Space Types:Office - Open Plan)3076 0.98 3014
2-Ski Lockers (Common Space Types:Locker Room)946 0.75 710
3724Total Allowed Watts =
Proposed Interior Lighting Power
E
(C X D)
D
Fixture
Watt.
A
Fixture ID : Description / Lamp / Wattage Per Lamp / Ballast
B
Lamps/
Fixture
C
# of
Fixture
Shared Office Space (Common Space Types: Office - Open Plan, 3076 sq.ft.)
LED - Surface Mounted LED: S1: LED Panel 19W:1 66 19 1254
LED - Linear Tape LED: R1: LED Linear Lamp 15W:1 122 12 1464
Ski Lockers (Common Space Types: Locker Room, 946 sq.ft.)
LED - Surface Mounted LED: S1: LED Panel 19W:1 17 19 323
3041Total Proposed Watts =
Interior Lighting Compliance Statement
Compliance Statement: The proposed interior lighting alteration project represented in this document is consistent with the
building plans, specifications, and other calculations submitted with this permit application. The proposed interior lighting
systems have been designed to meet the 2015 IECC requirements in COMcheck Version COMcheck-Web and to comply with any
applicable mandatory requirements listed in the Inspection Checklist.
Interior Lighting PASSES
Project Title:
Data filename:
520 E COOPER UNIT C7&C9 CHANGE ORDER 12/12/18Report date:
51 ofPage
Owner/Agent:
Brandi Solberg
Mission Peak Capital
1908 Main St
Kansas City, Missouri 64108
646 742-7535
brandi.solberg@missionpeakcapital
.com
Designer/Contractor:
Alison Agley
Rowland + Broughton
234 E Hopkins
Aspen, Colorado 81611
9702749796
alison.agley@rowlandbroughton.co
m
02/01/2019
justinh
Inspection Checklist
Requirements: 0.0% were addressed directly in the COMcheck software
COMcheck Software Version COMcheck-Web
Text in the "Comments/Assumptions" column is provided by the user in the COMcheck Requirements screen. For each
requirement, the user certifies that a code requirement will be met and how that is documented, or that an exception
is being claimed. Where compliance is itemized in a separate table, a reference to that table is provided.
Energy Code: 2015 IECC
Section
#
& Req.ID
Plan Review Complies?Comments/Assumptions
C103.2
[PR4]1
Plans, specifications, and/or
calculations provide all information
with which compliance can be
determined for the interior lighting
and electrical systems and equipment
and document where exceptions to
the standard are claimed. Information
provided should include interior
lighting power calculations, wattage of
bulbs and ballasts, transformers and
control devices.
Complies
Does Not
Not Observable
Not Applicable
Additional Comments/Assumptions:
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title:
Data filename:
520 E COOPER UNIT C7&C9 CHANGE ORDER 12/12/18Report date:
52 ofPage
Section
#
& Req.ID
Rough-In Electrical Inspection Complies?Comments/Assumptions
C405.2.1
[EL15]1
Lighting controls installed to uniformly
reduce the lighting load by at least
50%.
Complies
Does Not
Not Observable
Not Applicable
C405.2.1
[EL18]1
Occupancy sensors installed in
required spaces.
Complies
Does Not
Not Observable
Not Applicable
C405.2.1,
C405.2.2.
3
[EL23]2
Independent lighting controls installed
per approved lighting plans and all
manual controls readily accessible and
visible to occupants.
Complies
Does Not
Not Observable
Not Applicable
C405.2.2.
1
[EL22]2
Automatic controls to shut off all
building lighting installed in all
buildings.
Complies
Does Not
Not Observable
Not Applicable
C405.2.3
[EL16]2
Daylight zones provided with
individual controls that control the
lights independent of general area
lighting.
Complies
Does Not
Not Observable
Not Applicable
C405.2.3,
C405.2.3.
1,
C405.2.3.
2
[EL20]1
Primary sidelighted areas are
equipped with required lighting
controls.
Complies
Does Not
Not Observable
Not Applicable
C405.2.3,
C405.2.3.
1,
C405.2.3.
3
[EL21]1
Enclosed spaces with daylight area
under skylights and rooftop monitors
are equipped with required lighting
controls.
Complies
Does Not
Not Observable
Not Applicable
C405.2.4
[EL4]1
Separate lighting control devices for
specific uses installed per approved
lighting plans.
Complies
Does Not
Not Observable
Not Applicable
C405.2.4
[EL8]1
Additional interior lighting power
allowed for special functions per the
approved lighting plans and is
automatically controlled and
separated from general lighting.
Complies
Does Not
Not Observable
Not Applicable
C405.3
[EL6]1
Exit signs do not exceed 5 watts per
face.
Complies
Does Not
Not Observable
Not Applicable
Additional Comments/Assumptions:
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title:
Data filename:
520 E COOPER UNIT C7&C9 CHANGE ORDER 12/12/18Report date:
53 ofPage
Section
#
& Req.ID
Final Inspection Complies?Comments/Assumptions
C303.3,
C408.2.5.
2
[FI17]3
Furnished O&M instructions for
systems and equipment to the
building owner or designated
representative.
Complies
Does Not
Not Observable
Not Applicable
C405.4.1
[FI18]1
Interior installed lamp and fixture
lighting power is consistent with what
is shown on the approved lighting
plans, demonstrating proposed watts
are less than or equal to allowed
watts.
Complies
Does Not
Not Observable
Not Applicable
See the Interior Lighting fixture schedule for values.
C408.2.5.
1
[FI16]3
Furnished as-built drawings for
electric power systems within 90 days
of system acceptance.
Complies
Does Not
Not Observable
Not Applicable
C408.3
[FI33]1
Lighting systems have been tested to
ensure proper calibration, adjustment,
programming, and operation.
Complies
Does Not
Not Observable
Not Applicable
Additional Comments/Assumptions:
1 High Impact (Tier 1)2 Medium Impact (Tier 2)3 Low Impact (Tier 3)
Project Title:
Data filename:
520 E COOPER UNIT C7&C9 CHANGE ORDER 12/12/18Report date:
54 ofPage
Project Title:
Data filename:
520 E COOPER UNIT C7&C9 CHANGE ORDER 12/12/18Report date:
55 ofPage