TRANSMITTAL
Project: 520 E Cooper Ave, Unit C7 – MP ASPENOF C7 LLC –
Permit # 0085.2018.ACBK
Subject: CHANGE ORDER #1 for Interior Only Alteration
Date: 19 November 2018
To: Justin Hahn/Sofie Varga
From: Alison Agley
Via: City of Aspen Portal
Attachments: See Below
If you do not receive all attachments listed below, please call immediately.
Dear Justin and Sophie,
Please find downloaded to the portal the below items. New drawing sheets for Change Order #1.
The Change Order has added to the project 349 SF of Office Space, we have adjusted the proposed lighting plan and
specifications, and adjusted the ceiling assembly.
Please find downloaded, the below files:
00_Transmittal
01_Change Order Application Form
14_Change Order #1 Drawing Set_2018-11-19
15_Spec Sheets (Lighting Changes)
Thank you and please be in touch with any questions or requests for more information.
Alison Agley 970.274.9796