HomeMy WebLinkAboutFile Documents.ASPEN ST.0142.2015 (2).ARBK
Checklist for S. Aspen PUD to obtain a CO
Note: No Co on the free market units can be issued until the CO for the Deed Restricted unit has been issued per approvals
Item Section CO Finished? Responsibility Notes
Condo Plat Recorded SIA – Art 1, Sec 18 Lot 2 Y – 11/20/19 Community Development Rec #660593 Bk126:056
Deed restriction(s) SIA – Art I, Sec 5 Lot 2 Y – 11/20/19 APCHA Rec #660595
Condo doc review & Capital reserve
study
SIA – Art 1, Sec 5 Lot 2 Y APCHA Per email from CC on 11/21/19
Parking Signage Plan SIA – Art 1, Sec 7 Lot 2 N – still couple
of items left
Engineering & Parking OK to issue CO per Blake
Developer to provide update
Ground Stability readings
SIA – Art I, Sec 11 Lot 2 Y Engineering Per email from HG on 11/21/19
List of required Subdivision
improvements
SIA – Art II, Sec 1-2 Lot 2 Y Engineering Per email from HG on 11/21/19
S. Aspen Street reconstruction &
Surety refund
SIA – Art II, Sec 2 Lot 2 Y Engineering and City Attorney Letter of credit has expired.
Engineering has their own deposit
Release of escrow funds -$250K Site
protection & $250K Site
enhancement
Lot 2 Y Not to be done until very last CO –
Engineering, Community
Development and City Attorney
Escrow release signed by Sarah Ott