Loading...
HomeMy WebLinkAboutFile Documents.533 E Main St.0025.2018 (5).ACBKST. MARY CHURCH RENOVATION CONSTRUCTION MANAGEMENT PLAN St. Mary Church 533 E. Main Street, Aspen, CO 81611 Parcel ID: 273707331801 Construction Management Plan submitted to City of Aspen April 2018 Background: This Construction Management Plan (CMP) outlines and details the construction management measures that will be employed throughout the interior renovation and code required site work construction process of 533 E. Main Street, Aspen, CO 81611. This CMP is intended to address all items that are applicable to the scope of work in this project. Where items are not applicable to this scope of work, the CMP will note this. This CMP will also note where supplemental information can be found when it is located in the appendix. 2.0 Project Introduction 2.1 Project Location- Project is located at 533 E. Main Street / City and Townsite of Aspen, Block: 93, Lot: A-1, Township 10, Range 84, Section 7., City of Aspen, County of Pitkin, State of Colorado. See Appendix A for a Detailed Project Vicinity Map. 2.2 Disturbance Area- Disturbance Area for the code required sidewalk and curb and gutter construction is estimated at 5,623 square feet. See Appendix E CMP site plan for site fence/disturbance boundary. 2.3 Description of work- The scope of work will include all that is necessary for the interior renovation of the church building inclusive of interior finishes, new mechanical system, electrical upgrades, fire sprinkler system upgrades and code required upgrades to the site infrastructure. All utilities connections will be coordinated and completed prior to completion of the work. Construction waste will be hauled off via Haul/Emergency Access Map to the Landfill for recycling, see Appendix B. 3.0 Project Documentation 3.1 Permits- A. Building Permit- Please reference the permit application 3.2 Public Notification- A letter shall be sent to all neighbors within 300 feet of the Project no less than 10 days prior to construction and monthly updates until Project completion identifying any traffic/pedestrian concerns and describing hauling and staging operations. A pre-construction meeting between the Site Supervisor and all Sub-Contractors shall occur 10 days prior to construction with any impacted Utility, City, or School Departments also being notified. 3.3 Project Sign- Please see Appendix C 3/11/2018 ST. MARY CHURCH RENOVATION CONSTRUCTION MANAGEMENT PLAN 3.4 Project Contacts- Owner: Archdiocese of Denver 1300 S. Steele St. Denver, Colorado 80210 Contractor: Structural Associates Co. 4185 County Rd. 154 Glenwood Springs, CO 81601 Project Manager: Allyson Decatur (970) 945-0147 Office (970) 309-7022 Mobile Site Supervisor: Jack Shannon Structural Associates Co. 4185 County Rd. 154 Glenwood Springs, CO 81601 (970) 379-4647 Mobile Safety Officer: N/A (Contact Site Supervisor) Traffic Officer: N/A (Contact Site Supervisor) Erosion Control: N/A (Contact Site Supervisor) 4.0 Project Implementation: 4.1 Dates of construction- Please see Appendix D- Project Schedule 4.2 Hours of construction- Will be limited to 7:30 a.m. to 5:30 p.m. Monday through Friday, 9:00 a.m. through 5:00 p.m. Saturdays, with no work permitted on Sundays and federally designated holidays and other construction limitations set by the City of Aspen. 4.3 Sequence of construction- Please see Appendix D- Project Schedule 4.4 Adjoining Property Owners- N/A- no construction activity will encroach on nearby properties. 4.5 Project Fencing- Please see Appendix E- Site Plan for fencing location. 4.6 Natural Environment- No affect on the nearby natural environment will be permitted. 5.0 Project Management: 5.1 Parking Management- All parking to be contained on-site or public parking areas by permit. 3/11/2018 ST. MARY CHURCH RENOVATION CONSTRUCTION MANAGEMENT PLAN 5.2 Emergency Vehicle Access- Emergency vehicle access will not be affected by the scope of work identified in this CMP. Please see Appendix B- Haul/Emergency Access Map. 5.3 Parking Details- Public transportation and carpooling efforts will be made to reduce the amount of parking required for construction. 5.4 Staging Areas- Staging area will be limited to the existing concrete parking area and court yard adjacent to the Rectory and Employee housing building within the project site. 5.5 Construction trailer, materials storage and waste management- A construction trailer will be required as jobsite office. Material storage will be in the concrete parking area as identified on the CMP site plan. A dumpster will be located on the site and efforts will be made to recycle cardboard, drywall, wood, and metal via small waste containers. A bear proof container for food will be adjacent to the dumpster. Portable restrooms will be available for workers. 6.0 Traffic Control 6.1 General- All traffic control required shall be performed by on-site supervisory staff and contracted professional traffic control companies as required. 6.2 Haul Routes- Please see Appendix B- Haul/Emergency Access Map. 6.3 Delivery requirements- No affect on any public roads will occur as a result of the scope of work identified in this CMP. Due to staging limitations, only (1) delivery will be permitted at any one time. Delivery schedule shall fall within the general project hours of 7:30 to 5:30 Monday through Friday. No idling of delivery vehicles will be permitted for longer than 5 minutes. 6.4 Traffic Control Plan- All construction related traffic shall be controlled and maintained by the on-site Supervisor as outlined in the Haul/Emergency Access Map, see Appendix B. 7.0 Pedestrian Protection 7.1 General- All construction activity will comply with safety per MUTCD chapter 6D, the Americans with Disability Act, and IBC Chapter 33. 8.0 Sediment and Erosion Control 8.1 Requirements- Erosion control and storm water management will be as directed by SGM, the projects civil engineer, and shown on plan sheets CEC-01 (Erosion Control Plan) and CSW-01 (Storm water management plan ) 9.0 Fugitive Dust Control 9.1 Fugitive Dust Control Plan- Minimal exterior work, minimal fugitive dust is anticipated and will be controlled by watering as required. See Appendix F. 10.0 Emissions 3/11/2018 ST. MARY CHURCH RENOVATION CONSTRUCTION MANAGEMENT PLAN 10.1 General- All vehicles on site will be maintained to function within manufacturer’s specifications 10.2 Diesel Engines- Emissions from diesel powered engines shall have an opacity of no darker than 40% except for 10 seconds during start up. 11.0 Noise Suppression 11.1 General- All construction activity shall comply with the City of Aspen’s noise limitations. See Appendix G. Appendices included in this CMP: Appendix A: Project Vicinity Map Appendix B: Haul/Emergency Access Map Appendix C: Project Sign Appendix D: Project Schedule – Estimated duration 6 weeks +/- from permit issue Appendix E: Site Plan Appendix F: Fugitive Dust Control Plan Appendix G: Construction Noise Suppression Plan 3/11/2018 Structural Associates Construction Management Plan     Appendix A: Project Vicinity Map 3/11/2018 Structural Associates Construction Management Plan     Appendix B: Haul Route/Emergency Access 3/11/2018 Structural Associates Construction Management Plan     Appendix C: Project Sign On Green Paper 3/11/2018 IDTask ModeTask Name Duration Start Finish1St Mary church Entry Renovation35 daysMon 4/16/18Fri 6/1/182Set up barricades and tree protection1 dayMon 4/16/18Mon 4/16/183Make Pedestrian Walk way.4 daysTue 4/17/18Fri 4/20/184Get parks sign off1 dayMon 4/23/18Mon 4/23/185Brace Existing Roof2 daysTue 4/24/18Wed 4/25/186Remove Existing Roofing1 dayThu 4/26/18Thu 4/26/187Demo Brick Columns2 daysFri 4/27/18Mon 4/30/188Remove T&G at underside of Roof.1 dayTue 5/1/18Tue 5/1/189Remove Existing Glulam's1 dayWed 5/2/18Wed 5/2/1810Demo Existing concrete Steps.2 daysTue 5/1/18Wed 5/2/1811Form New Steps3 daysThu 5/3/18Mon 5/7/1812Rebar New Steps2 daysTue 5/8/18Wed 5/9/1813Inspect Rebar1 dayThu 5/10/18Thu 5/10/1814Install Wirsbo2 daysFri 5/11/18Mon 5/14/1815Inspect Wirsbo1 dayTue 5/15/18Tue 5/15/1816Pour Concrete Steps.1 dayWed 5/16/18Wed 5/16/1817Install New Structural members 2 daysThu 5/17/18Fri 5/18/1818Install New Columns 2 daysMon 5/21/18Tue 5/22/1819Inspect Rough Framing1 dayWed 5/23/18Wed 5/23/1820Install New Fascia2 daysThu 5/24/18Fri 5/25/1821Install New Cedar Roofing 2 daysThu 5/17/18Fri 5/18/1822Install new T&G to Underside of Roof2 daysThu 5/24/18Fri 5/25/1823Install Handrail2 daysMon 5/21/18Tue 5/22/1824Paint Fascia, Soffit & Handrails2 daysMon 5/28/18Tue 5/29/1825Install New Gutter1 dayThu 5/31/18Thu 5/31/1826Final Inspections1 dayFri 6/1/18Fri 6/1/18TFSSMTWTFSSMTWMar 4, '18Mar 11, '18TaskSplitMilestoneSummaryProject SummaryExternal TasksExternal MilestoneInactive TaskInactive MilestoneInactive SummaryManual TaskDuration‐onlyManual Summary RollupManual SummaryStart‐onlyFinish‐onlyDeadlineProgressPage 1Project: St Mary Entry RenovationDate: Fri 3/2/183/11/2018 WTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMMar 18, '18Mar 25, '18Apr 1, '18Apr 8, '18Apr 15, '18Apr 22, 'TaskSplitMilestoneSummaryProject SummaryExternal TasksExternal MilestoneInactive TaskInactive MilestoneInactive SummaryManual TaskDuration‐onlyManual Summary RollupManual SummaryStart‐onlyFinish‐onlyDeadlineProgressPage 2Project: St Mary Entry RenovationDate: Fri 3/2/183/11/2018 TWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSS'18Apr 29, '18May 6, '18May 13, '18May 20, '18May 27, '18Jun 3TaskSplitMilestoneSummaryProject SummaryExternal TasksExternal MilestoneInactive TaskInactive MilestoneInactive SummaryManual TaskDuration‐onlyManual Summary RollupManual SummaryStart‐onlyFinish‐onlyDeadlineProgressPage 3Project: St Mary Entry RenovationDate: Fri 3/2/183/11/2018 XFRMTRASH EXISTING RECTORY RE-GRADED SIDEWALK PER ASPEN CITY ENGINEERING DEPARTMENT; REF. CIVIL EXISTING KITCHEN TO REMAINEXISTING TRASH AND TRANSFORMER TO REMAIN; EXIST. TRANSFORMER TO BE RESET ON PAD, REF. CIVIL. CLASSROOM CLASSROOM CLASSROOM CLASSROOM CLASSROOM CLASSROOM CLASSROOM KITCHEN WOMEN'S ROOM MEN'S ROOM RECEPTION/LOBBY OFFICES ENTRY MEETING ROOM EXISTING LAWN TO REMAIN NOTE: PER ASPEN ENGINEERING DEPARTMENT • HUNTER STREET SIDEWALK TO BE 6' WIDE • MAIN STREET SIDEWALK TO BE 5' WIDE • GALENA STREET SIDEWALK DOES NOT REQUIRE WORK PER ASPEN BUILDING DEPARTMENT • SNOW-MELTING LIKE-FOR-LIKE AREAS ACCEPTED • CITY WILL EXEMPT 4' WIDE STRIPS OF SNOW-MELTED SIDEWALKS FOR ACCESSIBLE ROUTES EXIST. EMPLOYEE HOUSING CHARLES CUNNIFFE ARCHITECTS COPYRIGHT CHARLES CUNNIFFE ARCHITECTSC 610 EAST HYMAN AVE. ASPEN, CO 81611 TEL: 970.925.5590 FAX: 970.920.4557 cunniffe.com SHEET NO. JOB NO.2/15/2017 11:04:22 AMA1.0 1511 PROPOSED SITE PLANST. MARY CATHOLIC CHURCH533 E. MAIN STREETASPEN, CONORTH ISSUE: DATE: 100% DD 10/11/16 DD ADDENDUM 1 11/14/16 PERMIT DRAWINGS 01/12/17 100% CD 02/15/17 1/8" = 1'-0" 1 PROPOSED SITE PLAN pedestrian walkway with nonslip surface construction barricade. Pilasters with caution tape. toilets dumpster parking material storage Appendix E page 1 of 2 3/11/2018 15" 13" 20" 20" 30" 30"24"26"24"3"3"33"21" Job No. Drawn by: Date: Of File: PE:QC: Revision#Date By Graphic Scale In Feet: 1" = 10' 0 5 10 20 Highway-82 Sidewalk Plan & Profile 2016.195.001 XX 8/11/2016 XX PlanProfile XX CRD-02 14 St. Mary Catholic Church Aspen, CO Preliminary Not For Construction 118 West Sixth Street, Suite 200 Glenwood Springs, CO 81601 970.945.1004 www.sgm-inc.com Tree Protection Tree Protection Appendix E Page 2 of 2 Area of work 3/11/2018