HomeMy WebLinkAboutFile Documents.533 E Main St.0025.2018 (5).ACBKST. MARY CHURCH RENOVATION
CONSTRUCTION MANAGEMENT PLAN
St. Mary Church
533 E. Main Street, Aspen, CO 81611
Parcel ID: 273707331801
Construction Management Plan submitted to City of Aspen April 2018
Background:
This Construction Management Plan (CMP) outlines and details the construction management
measures that will be employed throughout the interior renovation and code required site work
construction process of 533 E. Main Street, Aspen, CO 81611. This CMP is intended to address all
items that are applicable to the scope of work in this project. Where items are not applicable to this
scope of work, the CMP will note this. This CMP will also note where supplemental information can be
found when it is located in the appendix.
2.0 Project Introduction
2.1 Project Location- Project is located at 533 E. Main Street / City and Townsite of Aspen,
Block: 93, Lot: A-1, Township 10, Range 84, Section 7., City of Aspen, County of Pitkin, State
of Colorado. See Appendix A for a Detailed Project Vicinity Map.
2.2 Disturbance Area- Disturbance Area for the code required sidewalk and curb and gutter
construction is estimated at 5,623 square feet. See Appendix E CMP site plan for site
fence/disturbance boundary.
2.3 Description of work- The scope of work will include all that is necessary for the interior
renovation of the church building inclusive of interior finishes, new mechanical system,
electrical upgrades, fire sprinkler system upgrades and code required upgrades to the site
infrastructure. All utilities connections will be coordinated and completed prior to completion of
the work. Construction waste will be hauled off via Haul/Emergency Access Map to the Landfill
for recycling, see Appendix B.
3.0 Project Documentation
3.1 Permits-
A. Building Permit- Please reference the permit application
3.2 Public Notification- A letter shall be sent to all neighbors within 300 feet of the Project no
less than 10 days prior to construction and monthly updates until Project completion identifying
any traffic/pedestrian concerns and describing hauling and staging operations. A pre-construction
meeting between the Site Supervisor and all Sub-Contractors shall occur 10 days prior to
construction with any impacted Utility, City, or School Departments also being notified.
3.3 Project Sign- Please see Appendix C 3/11/2018
ST. MARY CHURCH RENOVATION
CONSTRUCTION MANAGEMENT PLAN
3.4 Project Contacts-
Owner: Archdiocese of Denver
1300 S. Steele St.
Denver, Colorado 80210
Contractor: Structural Associates Co.
4185 County Rd. 154
Glenwood Springs, CO 81601
Project Manager: Allyson Decatur
(970) 945-0147 Office
(970) 309-7022 Mobile
Site Supervisor: Jack Shannon
Structural Associates Co.
4185 County Rd. 154
Glenwood Springs, CO 81601
(970) 379-4647 Mobile
Safety Officer: N/A (Contact Site Supervisor)
Traffic Officer: N/A (Contact Site Supervisor)
Erosion Control: N/A (Contact Site Supervisor)
4.0 Project Implementation:
4.1 Dates of construction- Please see Appendix D- Project Schedule
4.2 Hours of construction- Will be limited to 7:30 a.m. to 5:30 p.m. Monday through Friday, 9:00
a.m. through 5:00 p.m. Saturdays, with no work permitted on Sundays and federally designated
holidays and other construction limitations set by the City of Aspen.
4.3 Sequence of construction- Please see Appendix D- Project Schedule
4.4 Adjoining Property Owners- N/A- no construction activity will encroach on nearby properties.
4.5 Project Fencing- Please see Appendix E- Site Plan for fencing location.
4.6 Natural Environment- No affect on the nearby natural environment will be permitted.
5.0 Project Management:
5.1 Parking Management- All parking to be contained on-site or public parking areas by permit.
3/11/2018
ST. MARY CHURCH RENOVATION
CONSTRUCTION MANAGEMENT PLAN
5.2 Emergency Vehicle Access- Emergency vehicle access will not be affected by the scope of work
identified in this CMP. Please see Appendix B- Haul/Emergency Access Map.
5.3 Parking Details- Public transportation and carpooling efforts will be made to reduce the amount
of parking required for construction.
5.4 Staging Areas- Staging area will be limited to the existing concrete parking area and court yard
adjacent to the Rectory and Employee housing building within the project site.
5.5 Construction trailer, materials storage and waste management- A construction trailer will be
required as jobsite office. Material storage will be in the concrete parking area as identified on the
CMP site plan. A dumpster will be located on the site and efforts will be made to recycle cardboard,
drywall, wood, and metal via small waste containers. A bear proof container for food will be
adjacent to the dumpster. Portable restrooms will be available for workers.
6.0 Traffic Control
6.1 General- All traffic control required shall be performed by on-site supervisory staff and
contracted professional traffic control companies as required.
6.2 Haul Routes- Please see Appendix B- Haul/Emergency Access Map.
6.3 Delivery requirements- No affect on any public roads will occur as a result of the scope of work
identified in this CMP. Due to staging limitations, only (1) delivery will be permitted at any one
time. Delivery schedule shall fall within the general project hours of 7:30 to 5:30 Monday through
Friday. No idling of delivery vehicles will be permitted for longer than 5 minutes.
6.4 Traffic Control Plan- All construction related traffic shall be controlled and maintained by the
on-site Supervisor as outlined in the Haul/Emergency Access Map, see Appendix B.
7.0 Pedestrian Protection
7.1 General- All construction activity will comply with safety per MUTCD chapter 6D, the
Americans with Disability Act, and IBC Chapter 33.
8.0 Sediment and Erosion Control
8.1 Requirements- Erosion control and storm water management will be as directed by SGM, the
projects civil engineer, and shown on plan sheets CEC-01 (Erosion Control Plan) and CSW-01
(Storm water management plan )
9.0 Fugitive Dust Control
9.1 Fugitive Dust Control Plan- Minimal exterior work, minimal fugitive dust is anticipated and will
be controlled by watering as required. See Appendix F.
10.0 Emissions
3/11/2018
ST. MARY CHURCH RENOVATION
CONSTRUCTION MANAGEMENT PLAN
10.1 General- All vehicles on site will be maintained to function within manufacturer’s
specifications
10.2 Diesel Engines- Emissions from diesel powered engines shall have an opacity of no darker than
40% except for 10 seconds during start up.
11.0 Noise Suppression
11.1 General- All construction activity shall comply with the City of Aspen’s noise limitations. See
Appendix G.
Appendices included in this CMP:
Appendix A: Project Vicinity Map
Appendix B: Haul/Emergency Access Map
Appendix C: Project Sign
Appendix D: Project Schedule – Estimated duration 6 weeks +/- from permit issue
Appendix E: Site Plan
Appendix F: Fugitive Dust Control Plan
Appendix G: Construction Noise Suppression Plan
3/11/2018
Structural Associates
Construction Management Plan
Appendix A: Project Vicinity Map
3/11/2018
Structural Associates
Construction Management Plan
Appendix B: Haul Route/Emergency Access
3/11/2018
Structural Associates
Construction Management Plan
Appendix C: Project Sign
On Green Paper
3/11/2018
IDTask ModeTask Name Duration Start Finish1St Mary church Entry Renovation35 daysMon 4/16/18Fri 6/1/182Set up barricades and tree protection1 dayMon 4/16/18Mon 4/16/183Make Pedestrian Walk way.4 daysTue 4/17/18Fri 4/20/184Get parks sign off1 dayMon 4/23/18Mon 4/23/185Brace Existing Roof2 daysTue 4/24/18Wed 4/25/186Remove Existing Roofing1 dayThu 4/26/18Thu 4/26/187Demo Brick Columns2 daysFri 4/27/18Mon 4/30/188Remove T&G at underside of Roof.1 dayTue 5/1/18Tue 5/1/189Remove Existing Glulam's1 dayWed 5/2/18Wed 5/2/1810Demo Existing concrete Steps.2 daysTue 5/1/18Wed 5/2/1811Form New Steps3 daysThu 5/3/18Mon 5/7/1812Rebar New Steps2 daysTue 5/8/18Wed 5/9/1813Inspect Rebar1 dayThu 5/10/18Thu 5/10/1814Install Wirsbo2 daysFri 5/11/18Mon 5/14/1815Inspect Wirsbo1 dayTue 5/15/18Tue 5/15/1816Pour Concrete Steps.1 dayWed 5/16/18Wed 5/16/1817Install New Structural members 2 daysThu 5/17/18Fri 5/18/1818Install New Columns 2 daysMon 5/21/18Tue 5/22/1819Inspect Rough Framing1 dayWed 5/23/18Wed 5/23/1820Install New Fascia2 daysThu 5/24/18Fri 5/25/1821Install New Cedar Roofing 2 daysThu 5/17/18Fri 5/18/1822Install new T&G to Underside of Roof2 daysThu 5/24/18Fri 5/25/1823Install Handrail2 daysMon 5/21/18Tue 5/22/1824Paint Fascia, Soffit & Handrails2 daysMon 5/28/18Tue 5/29/1825Install New Gutter1 dayThu 5/31/18Thu 5/31/1826Final Inspections1 dayFri 6/1/18Fri 6/1/18TFSSMTWTFSSMTWMar 4, '18Mar 11, '18TaskSplitMilestoneSummaryProject SummaryExternal TasksExternal MilestoneInactive TaskInactive MilestoneInactive SummaryManual TaskDuration‐onlyManual Summary RollupManual SummaryStart‐onlyFinish‐onlyDeadlineProgressPage 1Project: St Mary Entry RenovationDate: Fri 3/2/183/11/2018
WTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMMar 18, '18Mar 25, '18Apr 1, '18Apr 8, '18Apr 15, '18Apr 22, 'TaskSplitMilestoneSummaryProject SummaryExternal TasksExternal MilestoneInactive TaskInactive MilestoneInactive SummaryManual TaskDuration‐onlyManual Summary RollupManual SummaryStart‐onlyFinish‐onlyDeadlineProgressPage 2Project: St Mary Entry RenovationDate: Fri 3/2/183/11/2018
TWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSSMTWTFSS'18Apr 29, '18May 6, '18May 13, '18May 20, '18May 27, '18Jun 3TaskSplitMilestoneSummaryProject SummaryExternal TasksExternal MilestoneInactive TaskInactive MilestoneInactive SummaryManual TaskDuration‐onlyManual Summary RollupManual SummaryStart‐onlyFinish‐onlyDeadlineProgressPage 3Project: St Mary Entry RenovationDate: Fri 3/2/183/11/2018
XFRMTRASH
EXISTING RECTORY
RE-GRADED SIDEWALK PER ASPEN CITY
ENGINEERING DEPARTMENT; REF. CIVIL
EXISTING KITCHEN TO REMAINEXISTING TRASH AND TRANSFORMER
TO REMAIN; EXIST. TRANSFORMER TO
BE RESET ON PAD, REF. CIVIL.
CLASSROOM
CLASSROOM
CLASSROOM
CLASSROOM
CLASSROOM
CLASSROOM
CLASSROOM
KITCHEN
WOMEN'S
ROOM
MEN'S
ROOM
RECEPTION/LOBBY
OFFICES
ENTRY
MEETING ROOM
EXISTING LAWN TO REMAIN
NOTE:
PER ASPEN ENGINEERING DEPARTMENT
• HUNTER STREET SIDEWALK TO BE 6' WIDE
• MAIN STREET SIDEWALK TO BE 5' WIDE
• GALENA STREET SIDEWALK DOES NOT REQUIRE WORK
PER ASPEN BUILDING DEPARTMENT
• SNOW-MELTING LIKE-FOR-LIKE AREAS ACCEPTED
• CITY WILL EXEMPT 4' WIDE STRIPS OF SNOW-MELTED SIDEWALKS FOR
ACCESSIBLE ROUTES
EXIST. EMPLOYEE HOUSING
CHARLES
CUNNIFFE
ARCHITECTS
COPYRIGHT CHARLES CUNNIFFE ARCHITECTSC
610 EAST HYMAN AVE.
ASPEN, CO 81611
TEL: 970.925.5590
FAX: 970.920.4557
cunniffe.com
SHEET NO.
JOB NO.2/15/2017 11:04:22 AMA1.0
1511
PROPOSED SITE
PLANST. MARY CATHOLIC CHURCH533 E. MAIN STREETASPEN, CONORTH
ISSUE: DATE:
100% DD 10/11/16
DD ADDENDUM 1 11/14/16
PERMIT DRAWINGS 01/12/17
100% CD 02/15/17
1/8" = 1'-0"
1 PROPOSED SITE PLAN
pedestrian
walkway with
nonslip surface
construction barricade.
Pilasters with caution
tape.
toilets
dumpster
parking
material storage
Appendix E page 1 of 2
3/11/2018
15"
13"
20"
20"
30"
30"24"26"24"3"3"33"21"
Job No.
Drawn by:
Date:
Of
File:
PE:QC:
Revision#Date By
Graphic Scale
In Feet: 1" = 10'
0 5 10 20
Highway-82 Sidewalk Plan
& Profile
2016.195.001
XX
8/11/2016
XX
PlanProfile
XX
CRD-02
14
St. Mary Catholic Church
Aspen, CO
Preliminary
Not For
Construction
118 West Sixth Street, Suite 200
Glenwood Springs, CO 81601
970.945.1004 www.sgm-inc.com
Tree Protection
Tree Protection
Appendix E Page 2 of 2
Area of work
3/11/2018