Request for Information 052R1
Aspen Ambulance District Facility FCI Constructors, Inc. - GJProject # 10-17-033
Aspen, CO 81611 Tel: 970-434-9093 Fax: 970-434-7583
RFI #: 052R1 Date Created: 1/7/2019
Author Company Authored ByAnswer Company Answered By
Chamberlin Architects, Inc. Jonathan West FCI Constructors, Inc. - GJ Sam Meeks
437 Main Street
Grand Junction, CO 81501
P. O. Box 1767
Grand Junction, CO 81502
Co-Respondent Author RFI Number
DisciplineSubject Category
ConfirmationCivilDoolittle Sidewalk Ramp Elevations
Company Name Contact Name Copies NotesCc:
FCI Constructors, Inc. - GJ Brady Blackmer 1
FCI Constructors, Inc. - GJ Brian Young 1
FCI Constructors, Inc. - GJ David Hale 1
Chamberlin Architects, Inc. Daniel Gartner 1
Question Date Required: 11/2/2018
Please refer to the attached.
The elevations on the original drawings for the curb and gutter and sidewalk at the southeast corner of the parking lot did
not work with the elevations of the existing sidewalk. Per discussions and site walks with Roaring Fork Engineering the
attached drawing has been issued to revise the elevations of the proposed sidewalk and curb and gutter. Due to the
elevations changing an additional 50' of sidewalk and curb and gutter will have to be removed and replaced so the new
sidewalk and old sidewalk will match.
RFI-052R1 Doolittle Sidewalk Ramp Elevations
Per additional conversations between Roaring Fork Engineering and FCI it was confirmed that the elevations for the
sidewalk and sidewalk ramp per RFI-052 would not meet the construction requirements. The attached sketch has been
approved by the City of Aspen and FCI has confirmed that it will work with the existing elevations. The attached sketch will
be used for the construction of the southeast corner of the HHS parking lot at Doolittle Road.
Suggestion
Answer Date Answered: 1/7/2019
This RFI is for Confirmation only. No response is required.
Prolog Manager Printed on: 1/7/2019 FCI_Integration Page 1
C-401.1DRAWN BY:CHECKED BY:SHEET NO:PROJECT NO:DATE:C 2016 CHAMBERLIN ARCHITECTSNO:ISSUED FOR:DATE:P:\2017\44 - Pitkin Ambulance Facility\04-DWG\04-Sheetset\SS-AADF Grading Details Doolittle Ramps Rev.dwg12/7/2018 12:44 PM592 HIGHWAY 133Carbondale, Colorado 81623PH 970.340.4130F 866.876.5873CHAMBERLIN ARCHITECTS437 Main St.Grand Junction, Colorado 81501T 970.242.6804725 Saint Joseph St., Suite B1Rapid City, South Dakota 57701T 605.355.6804www.chamberlinarchitects.comASPENAMBULANCEDISTRICT FACILITYCASTLE CREEK RDASPEN, COLORADOGRADINGDETAILSPROJECT STATUS: 100% CDSWWRBG2017-4412/07/20181PR#1 7/18/182PR#011 9/10/183 RAMP REV.12/7/18PLANS APPROVED BY JUSTIN FOREMANWITH CITY OF ASPEN ON 12/07/2018