ISSUE
CMP.1
7/2/2018Plotted On:CONSTRUCTION MANAGEMENT PLAN- INTERIOR REMODELALL DESIGNS, IDEAS ARRANGEMENTS AND PLANS
INDICATED BY THESE DRAWINGS AND
SPECIFICATIONS ARE THE PROPERTY AND
COPYRIGHT OF KIM RAYMOND ARCHITECTS, INC.
AND SHALL NEITHER BE USED ON ANY OTHER WORK
NOR BE USED BY ANY OTHER PERSON FOR ANY USE
WHATSOEVER WITHOUT WRITTEN PERMISSION.
WRITTEN DIMENSIONS SHALL TAKE PRECEDENCE
OVER SCALED DIMENSIONS AND SHALL BE VERIFIED
AT THE SITE. ANY DIMENSIONAL DISCREPANCY
SHALL BE BROUGHT TO THE ATTENTION OF THE
ARCHITECT PRIOR TO COMMENCEMENT OF WORK.
IF THE ABOVE DIMENSION DOES
NOT MEASURE ONE INCH (1")
EXACTLY, THIS DRAWING WILL HAVE
BEEN ENLARGED OR REDUCED,
AFFECTING ALL LABELED SCALES.
1" ACTUAL
AS NOTED
DATE www.KimRaymondArchitects.comtel 970-925-2252 email kim@krai.usKIM RAYMOND ARCHITECTS, INC. RED MT RIVERFRONT REMODELASPEN, COSCHEMATIC DESIGN12/20/17
7/2/2018 PRINTED 120 RED MOUNTAIN ROADINTERIOR PERMIT6/12/181234567891011121314W40W39W38W37
D17 D39W61W60 W68W66W67D18
W41 W60BW56W55
D19D18
D38
D40W57
D26
D27
W35
W46 W45W47W48
W27W26W25
W31D31D33
D36
D36
W62
D33 W62D36 D36 12345678121211212'-7"12'-2 1/2"50'-5 3/8"
15' FROM TOP OF
SLOPE
TOP OF
SLOPEW91W90 TOP OF SLOPE
(TYPICAL)
APPROXIMATE
EDGE OF CREEK
100-YEAR FLOOD LINE
SHRUBS AND FLOWERS
SHRUBS AND FLOWERS
STONE ENTRY PATIO
STONE PATH
SHRUBS AND
FLOWERS
GARDEN
15' OFFSET TO TOP
OF SLOPE
EXISTING DRIVEWAY
110 RED
MOUNTAIN ROAD
PROPERTY
BOUNDARY
PROPERTY
BOUNDARY
INGRESS/
EGRESS
EASEMENT
TOP OF SLOPE
(TYPICAL)
100-YEAR FLOOD LINE
10' SIDE YARD
SETBACK
25' FRONT
YARD
SETBACK
EXISTING TREES TO REMAIN
EXISTING TREES TO REMAIN
EXISTING TREES TO REMAIN
EXISTING TREES TO REMAIN
GARAGE WITH LIVING
SPACE ABOVE
EXISTING LOWER LEVEL
STONE RETAINAGE TO
REMAIN APPROVED
BUILDING ENVELOPE
APPROVED
BUILDING ENVELOPE
TOP OF SLOPE
(TYPICAL)
TOP OF SLOPE
(TYPICAL)
15' OFFSET TO TOP
OF SLOPE
PROPOSED
BUILDING
ENVELOPE
10' SIDE YARD
SETBACK
EXISTING STONE PATIO,
NEW GAS FIRE PIT
NEW PATIO AT
GRADE
STONE
PATIO
STONE
PATIO
MATERIALS
STORAGE AREA
TOILET to
be placed
only if
interior
plumbing
is disrupted
TRASH
REMOVAL
TRAILER
CONCRETE
CLEANOUT
CONTRACTOR
PARKING
CONTRACTOR PARKING
ON EXISTING DRIVEWAY
RECYCLE
ARCH 100'-0" =
SITE EL. 7882.11
ARCH 100'-0" =
SITE EL. 7882.11
CONSTRUC
T
I
O
N
FENCE
APPROVED
BUILDING ENVELOPE
10' BACK YARD
SETBACK
MATERIALS STORAGE AREAW93W94W91W90D20W96W95W97D21
W30D22 W28W29W6913 sq ft
4.1 THIS PROJECT WILL COMMENCE UPON RECEIPT OF A PERMIT
AND WILL LAST UP TO 10 MONTHS.
4.2 CONSTRUCTION HOURS
MONDAY - FRIDAY: 7:30 am-5:30 pm
SATURDAY: 9am-5pm
NO WORK WILL BE CONDUCTED ON SUNDAYS, JULY 4, (AND THAT WEEKEND
IF THE 4TH IS ON A MONDAY OR FRIDAY; MEMORIAL AND LABOR DAY WEEKENDS;
THANKSGIVING DAY, CHRISTMAS DAY AND NEW YEAR'S DAY.
HAUL ROUTE:
EXIT THE DRIVEWAY ONTO RED MOUNTAIN
ROAD. TURN LEFT ONTO MILL STREET. PROCEED
TO MAIN ST., TURN RT ON HWY 82 / MAIN ST. EXIT
HWY 82 AT PITKIN COUNTY LANDFILL. RECYCLE
MATERIALS AS REQUIRED.
2.2 VICINITY MAP
CONSTRUCTION MANAGEMENT NOTES:
2.1 NO DISTURBANCE TO THE EXTERIOR WILL OCCUR
2.3 THE EXISTING BUILDING IS NOW ON THE ASPEN MODERN LIST AND
WILL BE PROTECTED AS SUCH THROUGHOUT CONSTRUCTION.
THE PROJECT INCLUDES INTERIOR CONSTRUCTION AND REPLACEMENT OF FINISHES.
THE INTERIOR REMODEL INCLUDES LOWERING THE LOWER LEVEL SLAB FLOOR, REMOVING
A WALL AT THE MASTER SITTING ROOM AND REPLACING AND RESURFACING THE LIVING
ROOM FIREPLACE
3.2 PUBLIC NOTIFICATION IS NOT REQUIRED
3.3 A PROJECT SIGN WILL BE POSTED IN THE FRONT YARD OF THE
PROJECT PRIOR TO CONSTRUCTION COMMENCEMENT. THIS SIGN WILL
BE NO MORE THAN 6 SQ FT PER MUNICIPAL CODE 26.510.040 (2) AND
WILL USE THE TEMPLATE AS SHOWN IN APPENDIX A.
3.4 THE LIST OF CONTACTS IS PRINTED ON THE FRONT COVER OF
THE PERMIT SET, WHICH WILL BE ON SITE AT ALL TIMES.
5.2 EMERGENCY VEHICLE ACCESS WILL BE MAINTAINED AT THE SITE
AT ALL TIMES VIA RED MOUNTAIN ROAD AND THE EXISTING
DRIVEWAY. PLEASE SEE ATTACHED COPY OF ORDINANCE 35 TO
PERMIT DOCUMENTS.
5.4 STAGING AREAS ARE LOCATED ON THE SITE PLAN BELOW;
DELIVERIES WILL BE TAKEN FROM THE DRIVEWAY OFF RED MT. ROAD FOR THE
PROJECT
STAGING WILL BE IN THE DRIVEWAY AND GARAGE .
EXISTING PARKING WILL BE MAINTAINED FOR THE DURATION OF CONSTRUCTION
A DUMPSTER WILL BE PLACED IN THE FRONT YARD DURING
DEMOLITION, ADJACENT TO THE DRIVEWAY FOR EASY REMOVAL.
ALL RECYCLING WILL BE PLACED IN CONTAINERS TO BE TAKEN OFF SITE TO BE
RECYCLED WEEKLY.
THE EXCAVATION AND HAULING OF THE DEMOLITION DEBRIS AND RECYCLING
WILL OCCUR PRIMARILY AT THE START OF CONSTRUCTION. PLEASE SEE HAULING
ROUTE OUT OF TOWN BELOW THE
VICINITY MAP.
5.5 THERE WILL BE NO CONSTRUCTION TRAILER ON SITE.
THERE WILL BE A PORTA-POTTY IN THE FRONT YARD IN THE EVENT THAT
THE PLUMBING IS DISRUPTED.
11.1 NOISE SUPPRESSION
ALL EQUIPMENT USED ON THE PROJECT WILL ADEQUATELY MUFFLED
AND MAINTAINED TO MINIMIZE NOISE FROM THE SITE. 80 DECIBLES
IS THE NOISE LIMIT.
CONCRETE JACK HAMMERING WILL OCCUR ONLY IN THE COMPLETELY-
ENCLOSED SUBGRADE LOWER LEVEL AREA
07/25/2018
CMP references interior work only. No
exterior work addressed in this
approval