HomeMy WebLinkAboutresolution.council.019-14 RESOLUTION #19
(Series of 2014)
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF ASPEN,
COLORADO, APPROVING CONTRACT AMENDMENT #26 BETWEEN THE
CITY OF ASPEN AND OZ ARCHITECTURE AUTHORIZING THE CITY
MANAGER TO EXECUTE SAID CONTRACT ON BEHALF OF THE CITY OF
ASPEN, COLORADO.
WHEREAS, there has been submitted to the City Council contract
amendment #26 for Burlingame Phase II construction administration services
between the City of Aspen and OZ Architecture, a true and accurate copy of which
is attached hereto as Exhibit "A";
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF
THE CITY OF ASPEN, COLORADO,
That the City Council of the City of Aspen hereby approves contract
amendment 426 for Burlingame Phase II construction administration services
between the City of Aspen and OZ Architecture, a copy of which is annexed
hereto and incorporated herein, and does hereby authorize the City Manager to
execute said agreement on behalf of the City of Aspen.
INTRODUCED, READ AND ADOPTED by the City Council of the City of
Aspen on the 10th day of March 2014.
teven Skadron, Mayor
I, Kathryn S. Koch, duly appointed and acting City Clerk do certify that the
foregoing is a true and accurate copy of that resolution adopted by the City
Council of the City of Aspen, Colorado, at a meeting held March 10, 2014.
� Kathryn S. Koch, City Clerk
Exhibit B:Detailed 2014 Project Budget
Burlingame Ranch Phase IIAii, Buildings 5-7, 34 uni72013not
2014 Detailed Budget Estimate (carry-forward frincluded)
rev.Jan 17,2014 ce
SOURCES Budget Actual Variance
L2013 Carry-Forward Balance tbd
2014 City Council Budget Approval $ 15,056,020
Grant Funding tbd
Sources $ 15,056,020 $ $
I
USES — —
A. Construction-General Contractor $ 11,429,114 $ $ (11,429,114)
Access/Infrastructure Remaining
tbd �
Vertical Buildings 1-4 Remaining(HCL) tbd
11,279,114 $ (11,279,114)
Vertical Buildings 5-7 including Solar Thermal(RAN) $
2014 Irrigation connectivity-design and construction $
1s0,000 $ (150,000)
City of Aspen Parks Contribution(pumps/pumphouse) $
000 $ $ (129,000)
,
B. Construction-Developer Responsibilities(City of Aspen) $ 129n $
jSite tes Sunk $
ation Sunk
$
te Storm Sewer $
Gas Supply,E lectrical Design,Utility Oversight
Site Elect Underground $
Site Elect Supply $
Site Sanitary Line 129,000)
Owners OCIP Insurance I $ 129,000 $
C. Soft Costs $ 1,772,003 $ $ (1,772,003)
Desi n
Administrative Services
COA PM $ 200,000 $ (200,000)
$ 20,000 $ (20,000)
Legal
Presales $ 10,000 $ (10,000)
Owner's Agent $ 390,880 $ (390,880)
Architect&Consultants $ 408,609 $ (408,609)
CxA Constr Phase $ 74,600 $ (74,600)
Enhanced Civil Oversight
Enhanced Vertical Oversight $ 64,130 $ (64,130)
Professional Services
Materials Testing
Geotech(inc materials testing) $ 44,000 $ (44,000)
Survey $ 40,000 $ (40,000)
Medium voltage electrical oversight $ 5,000 $ (5,000)
Fees
S 191,784 $ (191,784)
Sewer Tap Fee
Water Tap Fee-waived
Parks Impact Fee-waived
TDM Impact Fee-when buildings online $ 37,000 $ (37,000)
School Impact Fee-when buildings online $ 31,000 $ (31,000)
Road Impact Fee-n/a only for Pitkin County Permit
Building Permit Fee $ 150,000 $ (150,000)
Stormwater Fee-waived
Land Use Fee
Home Sales Fee
HOA Setup $ 20,000
Burlingame Phase I Parking,Design&Engineering $
75,000
Other
Construction Power and Water $ 10,000 $ (10,000)
D. Contingencies $ 1,725,903 $ $ (1,725,903)
2013 Contingency $ 11725,903 $ (1,725,903)
Project contingency expressed as%of construction cost 15.1%
Total Uses(A+B+C+D) $ 15,056,020 $ $ (15,056,020)
Page 1 of 1
Exhibit A - Amendment#26
ARCHITECTURE MEMORANDUM
URBAN DESIGN
® INTERIOR DESIGN
Scott Miller DATE: September 26,2013
TO:
FROM: Tim Ross PROJECT: Burlingame Ranch Phase II
SUBJECT: Burlingame Phase II PROJECT#: 809003
Contract Amendment No.21
OZ Architecture B195-2oo8
CC: Chris Everson,Rob Taylor FILE#:
Amendment 26-Completion of CA Services for 133.-134
Proposed Amendment to AIA Document B195-2oo8 Agreement between Owner and Architect for Integrated Project
Delivery for the Burlingame Ranch Phase 11 Project Dated January 25,2010.
Description of Service
OZ Architecture and its Consultants have previously provided a fee for CA for Buildings 1-4 to be completed in 2013 which
carried over into 2014 as part of Amendment 20,however only the fees to be invoiced in 2013 were approved by
Amendment 20 This request is for authorization to proceed with the 2014 CA fees for Buildings 1-4 as previously
presented as Additional Services for the Burlingame Ranch Phase II Project:
Supporting Documents (See attached)
Fee Matrix dated 1/8/2013(previously submitted with Amendment 20)
Deliverables
Construction Administration Services as more specifically described by the AIA Document 8195 dated 1/25/20so and A295
dated 1115/2010.
Schedule
Services in this proposal will commence on January 1,2014 and continue through completion of construction and issuance
of Temporary Certificates of Occupancy for Buildings 1 through 4. These services will overlap with the services proposed in
Amendment 27.
Exclusions
Proposal is for CA services related to completion and closeout of Buildings 1-4 only.Services will overlap with the start of
construction of Buildings 5-7,however CA services for Buildings 5-7 have been submitted as a separate proposal.
FARCHITECTURE MEMORANDUM
� I URBAN DESIGN
® INTERIOR DESIGN
Fee Breakdown
• Alpine Engineers,Inc.;civil design and documentation $18,750.00
• Monroe and Newell Consulting Engineers;structural design and documentation $ 0.00
• REG Consulting Engineers;mechanical design and documentation $ 3,347.00
• MV Consulting Engineers;electrical design and documentation $ 3,000.00
• BA Consulting Engineers;plumbing design and documentation $ 3,000.00
• Mt.Daly;landscape&irrigation design and documentation $ 9,000.00
• Western Heritage;irrigation design and doc.(as a sub consultant to Mt Daly) $ 7,000.00
• Shaner Consulting Engineer ire protection design and documentation(est.by OZ) $ 1,200.00
Subtotal-1(Consultants) $45297.00
• OZ;administration of Consultants services(1o%per Section 4.3 $ 4,530-00
• OZ Architecture architectural design and documentation $ on-on .00
Subtotal-2(OZ+Consultants) $139,827.00
Reimbursable Expenses Estimated at 1o%to be invoiced as accrued per contract $ 111g8-A.00
Proposed Total Amendment 26 $ 153,809.00
Authorization
Pursuant Article 1.5 and Section 4.3 of the Owner-Architect agreement referenced above,please indicate acceptance of
the terms of Amendment 23 as described herein by providing your signature below.
City of Aspen OZ Architecture
0/
Owner Architect
BOULDER PHONE:303 449.8900
1805 29TH STREET,SUITE 2054 FAX:303.449.3886
DENVER BOULDER COLORADO SPRINGS LAS VEGAS LAKE TAHOE BOULDER,COLORADO 80301 WWW.OZARCH.COM
Burlingame Ranch Phase 2A CA
Base Fee Summary
EX.B-BASE FEE Burn Rate By Month P.C..-Ph2B construction Administration Phase 28+complete A&I
2013 2014
Last Updated: 1/8/2013 By:TR Jan Feb Mar April May June July August Sept Oct Nov Dec ]an Feb Mar April May June
13,000
PreCon $13,000 4,333 4,333 4,333
CA-Base $225,000 15,000 15,000 15,000 15,000 15,000 15,000 15,000 15,000 15,000 1350000 15,000 15,000 15,000 15,000 15,000 15,000 90,000
148,000 901
Architecture
$238,000
13,000
PreCon $13,000 6,500 6,500
6,250 6,250 6,250 6,250 6,250 6,250 6,250 6,250 6,250 56,250 6,250 6,250 6,250 18,750
CA-Base $75,000 18,750
Civil $88,000 69,250
3,000
PreCon $3,000 1,500 1,500
2,000 2,000 2,000 2,000 2,000 2,000 12,000 0
CA-Base $12,000 15,000 0 '
Structural $15,000
PreCon $3,440 1,720 1,720 3,440
CA-Base $10,040
1,673 1,673 1,673 1,673 6,693 1,673 1,673 3,347
10,133 ' 3'347
Mechanical $13,480
PreCon $3,000 1,500 1,500 3,000
CA-Base $9•000
1,500 1,500 1,500 1,500 6,000 1,500 1,500 3,000
9,000 3,000 Electrical $12,000
PreCon $3,000 1,500 1,500 3,000
1,SOD 1,500 1,500 1,500 6,000 1,500 1,500 3•�
CA-Base $9,000 3,000
Plumbing $12,000 9 000
nD
PreCon 720 360 360
CA-Base 14,000 750 750 1,750 1,750 5,000 1,750 1,750 2,750 1,750 9,000
5,720 9'�
Landscape 14,720
PreCon 4,000 2,000 2,000 4,000
10,000 500 1,500 500 500 3,000 3,000 1,000 1,000 20000 7,000
CA-Base 7 000 7,000
Irrigation 14.000
Subtotal-1 $407,200 4,333 19,413 19,413 23,750 30,173 23,250 29,173 23,250 30,173 21,250 27,673 21,250 273,103 25,923 21,250 30,673 17,750 18,750 19,750 134,097
2,000 2,000 6,000 2,000 2•�
Waterproofing $8,000 2,000 6,000 2,000 2,000 Acoustical $8,000 2,000 2,000 2,000
600 600 600 1,800 600 600 1,200
Fire Protection $3.000 0
0
Other $0
0 4,600 0 4,600 0 0 0 13,800 0 4,000 600 0 600 0 5,200
Subtotal-2 $19,000 0 0 4,600 0 0
tt
Reimb.(Est @ 10%) 42,620 433 1,941 2,401 2,375 3,017 2,325 3,377 2,325 3,477 2,125 2,767 2,125 2013 2,592 2,525 3,127 1,775 1,935 1,975 2014
lan Feb Mar April May June July August Sept Oct Nov Dec lan Feb Mar April May June
315,594 153,226
t
Fees Authorized in Authorization requested for
2013,authorized 2014 Fees for B1-B4 only
by Amendment 20 by Amendment 26
(G:\2009\809003.00 Burlingame Ranch Phase II\Project Management\Contracts\Contract Addendum\In Process\Amendment 20-NEX7\Burlingame Ph2B CA Fee APPROVED_2012-11-30.xlsx)