HomeMy WebLinkAboutagenda.council.worksession.202103161
AGENDA
CITY COUNCIL WORK SESSION
Amended 3/15/2021 3:10 PM
March 16, 2021
4:00 PM, City Council Chambers
130 S Galena Street, Aspen
WEBEX
www.webex.com
Enter Meeting Number 142 904 7591
Password provided 81611
Click "Join Meeting"
OR
Join by phone
Call: 1-408-418-9388
Meeting number (access code): 142 904 7591#
I.WORK SESSION
I.A.City Offices Construction Update
1
Page 1 of 4
MEMORANDUM
TO:Mayor Torre and City Council
FROM:Robert Schober, Capital Asset Project Manager
THROUGH:Scott Miller, Public Works Director/Interim Assistant City Manager
DATE OF MEMO:March 10, 2021
MEETING DATE:March 16, 2021
RE:New City Hall Project Update –Overall Project Status and AV
Equipment Options
REQUEST OF COUNCIL: The project team has been tasked with providing: 1) An overall
update on project status; 2) Finalize the Audio-Visual package for the building.
BACKGROUND: The timeline for governmental approval, design and construction of this
project is detailed below:
September 10, 2019 –Staff presented to Council (2) options for final programming of
the New Galena City Offices:
Option #1: Council Chambers remains at the Armory
Option #2: Council Chambers at the Galena City Offices building
Council decision is that the best choice is Option #2 changing the location of the “seat
of government” to the Galena City Offices building and establishing a final
programming direction for the new building.
July 27, 2020 –Staff presented to Council the final interior drawing package. Council
gave direction to deploy REMP funding and interest income from debt financing
proceeds to complete the GMP allowance reconciliation for the interiors.
August 18, 2020 –Parks staff presented to Council the schematic design for Galena
Plaza and was directed to take the design to construction documents.
DISCUSSION:
Overall project update -Currently, the project is moving into the finish stages of construction.
While there is still a significant amount of mechanical, electric &piping work remaining in order
to have the building systems ready for commissioning, the building is fully enclosed, and most of
the drywall installation has been completed. In upcoming months there will be trim installed,
painting, interior doors and fixtures will be hung as we push towards completion in the fall.
2
Page 2 of 4
Currently the project is working on a modified completion schedule due to the impacts from the
ongoing Covid-19 pandemic. We have incurred schedule delays due to the initial shutdown,
crew quarantines affecting critical path and limited manpower availability working within the
Pitkin County Covid-19 guidelines (50%). To date we have contained the financial implications
of the delays within project contingency and GMP savings and are working to minimize any
further impacts moving forward.
The completion schedule is outlined below:
Substantial Completion –September 2021
Commissioning/FF&E –October 2021
Soft Opening –November 2021
Grand Opening –Thanksgiving
As mentioned above, the project has managed to contain the impacts from Covid-19 within the
contingency as well as the impacts of reprogramming the interiors during the construction
process. This has left us with a limited contingency of $267,769 heading into the final stages of
construction,although we are through the periods of highest risk.
Audio Video Package -The past year of COVID has dramatically changed the expectations of
how community members, staff, and elected officials conduct public meetings, complete work
through remote participation, and support the use of technology for delivering public
involvement and accessibility in policy making discussions.
In the design of the AV system for the new city hall, staff and the consultant have considered
several new preferences that are much different than pre-COVID days. These include:
Councilmembers desire to fully participate including voting, remotely and having the
flexibility of both on-site and remote elected officials at meetings in the future
Staff and consultant preferences to have the option to present remotely, particular during
evening meetings
The potential to take remote public comment, should Council or a commission desire to
allow it on specific agenda items
For a more detailed explanation of the AV systems capabilities as designed please see the
attached Exhibit A –Audio Video Experts Design Narrative. Staff is recommending an
incremental approach to adding peripherals to the audio-visual systems of the new City Hall.For
the small group (4-5 people)meeting spaces, we are recommending the rooms have basic audio-
visual technology, focused on being able to share screens from a laptop for discussion purposes.
Additionally, 6 rooms have been identified for increased AV equipment that allow for
videoconferencing with more robust audio-visual hardware and software. These rooms are
spread between the 2nd and 3rd floors of the new City Hall, as well as one room in the Rio Grande
building.These rooms were identified due to a combination of size and purpose to support
activities such as Council Chambers, and overflow areas; City Council’s executive sessions;
3
Page 3 of 4
Councilmember and staff remote participation in organization meetings (CML, NLC, CAST,
etc.); remote interviewing of job applicants and consultants; use of trainers and/or consultants
that can deliver services remotely; hybrid in-person and remote meetings, and potential
community use of the multipurpose training room.
By far, the build out of the technology for the new Council Chambers is the most elaborate and
expensive component of the building. This system includes upgrades to the AV and
microphone systems, allowing remote participation of Council members, staff,and the public, as
well as upgrading the broadcasting system for Grassroots, Facebook, and the city’s website. A
letter of endorsement from Grassroots is attached as Exhibit B.
Below is a table which outlines the costs of (2) different options for outfitting the building with
equipment. Option #1 (staff recommendation)includes the six rooms described above which
will have the full AV functionality as outlined in Exhibit A. Option #2 is dialed back and only
includes the 3rd floor areas (Council Chambers, Multi-Purpose Room, Civic Lobby) with the
remaining rooms being outfitted with a basic package only. Please keep in mind that the rough-
in for the full functionality of the 6 rooms was previously approved via Resolution #22-2021 so
the equipment may be installed in the future.
Option #1 Option #2
Room #/Description
Equipment Cost: Full
Connectivity
Equipment Cost:
3rd Floor Only
Council Chambers #3020 $166,142 $166,142
Multi-Purpose Room #3003 $47,937 $47,937
Conference Room #2002 (Large Mid-Level)$21,919
Civic Lobby #3002 $5,910 $5,910
HR Conference Room Rio Grande Building #2314 $23,142
Council Conference Room #2003 $25,105
Subtotal Equipment $290,155 $219,989
Commissioning $43,523 $32,998
Total Cost $333,678 $252,987
Existing Uncommitted AV Budget ($21,127)($21,127)
Net New Spending Authority Request $312,551 $231,860
Cost for outfitting the building including Council Chambers are outside of the current project
budget. The gap in costs will be funded via the AMP.
City Hall Audio-Visual Project Budget
Current Project Budget Audio Visual $155,000
Current AV Committed (Full Rough-In Option #1)$133,873
Uncommitted AV Project Funds $21,127
4
Page 4 of 4
Galena Plaza –In response to the “Friends of Galena Plaza” request to reimagine the plaza
design from the original plan in the GMP,and per council direction (resolution #97-2019)a
public outreach process was conducted in Fall/Winter of 2019. Schematic design was completed
in August 2020 and Council directed the team to proceed forward and finalize construction
documents. These documents were recently completed,and a value engineering process is
underway.
Staff is currently working with the contractor finalizing pricing and phasing options. The project
team will be back in front Council to discuss this in the future.
RECOMMENDED ACTION: Staff recommends approving Option #1 for the Audio-Visual
package at the New City Hall.
5
NEW CITY OFFICES
UPDATE
City Council Work Session | March 16, 2021
6
TRA
•Project Update
•AV Equipment Decision
AGENDA
7
TRA
Progress Photos
8
TRA
Progress Photos
9
TRA
Progress Photos
10
TRA
Progress Photos
11
TRA
Progress Photos
12
TRA
Project Update
City Hall Schedule Update
Substantial Completion September 2021
Commissioning/FFE October 2021
Soft Opening November 2021
Grand Opening Around Thanksgiving
City Hall Project Contingency Update
Percentage Complete 65%
Project Contingency $2,400,000
Remaining Project Contingency $268,000
13
TRA
Initial Covid shutdown cost an additional $39K and
a 30-day addition to the schedule that was funded
by contingency
Shaw has noticed $60K reserve and 30 days for
additional Covid delays and impacts which we are
attempting to mitigate through GMP savings and
schedule acceleration
Future risks include Galena Plaza implementation,
Covid, supply chain issues (Texas storms)
Covid Impacts and Future Risks
14
TRA
Council Chambers Rendering
15
TRA
Audio Visual
Per AV Experts, these are the highlights of the
proposed system:
•Each room is very similar in operation, creating synergy
•All rooms feature video conferencing capacity, except for overflow
space. Zoom, WebEx, Teams etc.
•All rooms have a touchscreen, located on table in room
•All rooms will have a scheduling panel outside room
•All rooms will have pan tilt zoom cameras, desktop & hidden ceiling
microphones, HDMI inputs at tables, and 4k flat panel displays
Council Chambers will feature:
•Video conferencing and TV broadcast
•5 cameras, 3 large flat panel displays, monitor facing Mayor’s location,
14 gooseneck microphones, wireless microphone for movable
presenter’s podium, large touch screen and audio recorder for clerk,
overhead document camera, and hearing assist system
•Video and audio can be shared to overflow, and each room can call
another room or join all rooms together via video
16
TRA
Audio Visual Financials
•Additional spending authority for either option, if
approved by Council, would be supported by existing
fund balance from the Asset Management Plan Fund.
City Hall Audio-Visual Project Budget
Current Project Budget Audio Visual $155,000
Current AV Committed (Full Rough-in Option #1)$133,873
Uncommitted AV Project Funds $21,127
17
TRA
•Things to Consider
$290K additional expense today
Allows us to operate today as needed and flexible in times like a
public health crisis
Forward thinking, universal connectivity to any conferencing
platform
Staff recommendation
Audio Visual Option 1 – Full Package
Room #/Description Equipment Cost: Full Connectivity
Council Chambers #3020 $166,142
Multi-Purpose Room #3003 $47,937
Conference Room #2002 (Large Mid-Level)$21,919
Civic Lobby #3002 $5,910
HR Conference Room Rio Grande Bldg. #2314 $23,142
Council Conference Room #2003 $25,105
Subtotal Equipment $290,155
Commissioning $43,523
Total Cost $333,678
Existing Uncommitted AV Budget ($21,127)
Net New Spending Authority Request $312,551
18
TRA
Things to Consider
$70K cost avoidance today, equipment could be landed over time
With what we know now about COVID, this package may not be sufficient.
Addresses infrastructure needs, but not diverse equipment needs.
Does not land the equipment needed to effectively operate during a public
health crisis.
Audio Visual Option 2 – Partial Package
Room #/Description Equipment Cost: Full Connectivity
Council Chambers #3020 $166,142
Multi-Purpose Room #3003 $47,937
Civic Lobby #3002 $5,910
Subtotal Equipment $219,989
Commissioning $32,998
Total Cost $252,987
Existing Uncommitted AV Budget ($21,127)
Net New Spending Authority Request $231,860
19
Email: newcityoffices@cityofaspen.com
Webpage: cityofaspen.com/newcityoffices
24-Hour Hotline: 970-429-1793
Thank you for your time.
20
Exhibit A
GrassRoots Television Inc. 110 E. Hallam St. Suite 132 Aspen CO 81611 970-925-8000
Aspen City Council
130 S. Galena Street
Aspen, CO 81611
Re: New Aspen City Hall video broadcast and streaming capability
An all-new contemporary video streaming and broadcasting system is essential for clearly and universally
transmitting and archiving the content, speech and actions of Council, presenters, citizens and other
entities using Council chambers and other meeting rooms in the new Aspen City Hall. This ability to
include the citizens of Aspen and other interested parties both within and outside the City in civic
discussions, and to disseminate their participation in government decisions, live over multiple digital
media platforms, is integral to a healthy and engaged community.
As the past year has demonstrated, the new system must be able to accommodate and integrate the
reception, participation and transmission of multiple remote participants, including their presentation
materials. Contemporary, main-stream, high-quality audio and video technology should be installed to
ensure the longest possible life-time and technical relevancy of the system.
All components of the video, audio, broadcast and streaming system currently in use in Council
Chambers in the Armory relies on antiquated, standard definition video equipment that has served far past
its expected life and technical relevancy. The computers are operating on unsupported software and
operating systems. Streaming is possible only due to a patchwork of temporary solutions. The decade
old video switcher is literally rattling and wheezing. The system is not totally obsolete, however. It can
be kept in place and employed for ancillary meeting use in the current chambers until either the Armory
building is renovated or the equipment fails.
Respectfully,
John Masters
Executive Director
GrassRoots Television Inc.
21
Audio Video Experts
565 25 Road Suite 106
Grand Junction CO 81505
Phone 970-242-3900
Fax 970-797-1470
www.myavexpert.com
Aspen City AV Systems:
We have designed AV systems that will all work very similarly so each room is very similar in
operation. Our experience has been that when all rooms work similarly it creates synergy and
ease of operation from room to room. All of the rooms feature video conferencing capacity with
the exception of the overflow space. We recommend that the city furnish a fixed pc (small form
factor for each conference room) This will allow universal connection to any type of video
conferencing software, zoom, go to meeting, meets, and many others. All rooms will have a
touchscreen for control of audio video devices, source selection display on and off, volume
control etc. Each touch panel will reside on the table in the room. Outside of the room will be a
scheduling panel which will say if the room is available or in use and when connected to the
city’s calendar service will allow the room to be reserved for upcoming meetings. All rooms will
have pan tilt zoom camera’s allowing for the camera to be adjusted for larger or smaller
meetings. Each room will have hidden ceiling microphones with digital dsp to manage calls and
audio quality. HDMI inputs will be at the table for laptop sharing with a concealed table box with
power for devices. Large 4k light commercial grade flat panel displays will be in each room for
good video quality and extended life over residential grade displays.
Council chambers will feature video conferencing, as well as television broadcast. This will be
capable of high definition video broadcast and features all new equipment. 5 camera’s will cover
the room and 3 large flat panel displays, 1 behind council, and 2 next to council that can be
aimed towards the audience or towards council. There will also be a monitor, facing the head of
the table(Mayors location) below table height. There will be 14 gooseneck microphones for
council and presenters, as well as a wireless microphone for the movable presenters podium.
These microphone and the ceiling microphones will work to provide sound for both broa dcast
and videoconferencing. There will be a large touch screen control at the clerk location and a
local audio recorder for the record. There will be an overhead document camera for
presentations. There will be a hearing assist system in the floor which will work with T-coil
hearing adis and hip pack receivers for the hearing impaired. Video and audio can be shared to
the overflow area. Each room could call another room via video conferencing or join all rooms
together for larger meetings or social distancing. The city will need to furnish fixed pc’s and
wireless keyboards for those devices. Laptops will be for local presentations, but will not join the
larger video conferencing systems.
Exhibit B
22